Euclid Asphalt Paving v. Pricom Asphalt, Unpublished Decision (12-29-2005)

2005 Ohio 7049
CourtOhio Court of Appeals
DecidedDecember 29, 2005
DocketNo. 2004-L-175.
StatusUnpublished
Cited by7 cases

This text of 2005 Ohio 7049 (Euclid Asphalt Paving v. Pricom Asphalt, Unpublished Decision (12-29-2005)) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Euclid Asphalt Paving v. Pricom Asphalt, Unpublished Decision (12-29-2005), 2005 Ohio 7049 (Ohio Ct. App. 2005).

Opinions

OPINION
{¶ 1} Appellant, Mount Zion Fellowship Church ("Mount Zion"), appeals from the judgment entry of the Lake County Court of Common Pleas finding it in breach of an oral construction contract entered between itself and appellee, Pricom Asphalt Sealcoating ("Pricom").

{¶ 2} In 2002, as part of a larger construction project, Mount Zion decided to pave a parking lot measuring 28,000 square feet. Pricom was engaged in other work for Mount Zion and was asked to bid on the job. Pricom contacted Euclid Asphalt Paving Company ("Euclid"), a subcontractor, and presented blueprints from which Euclid could estimate the cost. Euclid provided Pricom with a quote and Pricom submitted a bid to Mount Zion for a total of $47,000. Mount Zion accepted the bid and signed a written contract with Pricom.

{¶ 3} Euclid commenced paving the 28,000 square foot area; during this process, Euclid's president, Anthony Russo, noticed an area adjacent to, but outside the initial measurements. Russo spoke with Todd Tornstrom, Pricom's president, regarding the whether Mount Zion desired this additional area paved. Tornstrom contacted his office manager and asked her to call Mount Zion to determine whether it wanted the additional work done. Russo measured the additional area (18,000 square feet) and told Tornstrom he would charge the same amount per square foot as he had for the original 28,000 square foot area ($1.26 per sq. ft.). According to Tornstrom, Mount Zion assented to the work and Russo moved forward with the additional paving. All said, Euclid paved 46,000 square feet.

{¶ 4} Once the work was finished, Pricom submitted a bill for $72,900, the cost of the entire 46,000 square feet. Mount Zion disputed the bill and maintained it was obligated to pay only $47,000, the amount set forth in the original, written contract. In Mount Zion's estimation, the additional 18,000 feet was included in the original contract under an amount designated "additional area." The cost of the "additional area" was listed at $800. While the nature of the "additional area" is not entirely clear, Pricom maintained the charge was for "curves and lining." A handwritten notation stating "include curves and lining" appears above the $800 "additional area" charge.

{¶ 5} Prior to the commencement of the instant litigation, Mount Zion had paid Pricom $47,000, the amount set forth in the written agreement. However, pursuant to its billing invoice, Mount Zion still owed $25,900 for the additional work. Moreover, Pricom paid Euclid $43,000 for its work as subcontractor. However, at the time of the litigation, Pricom still owed Euclid $17,100 for performing the additional work.

{¶ 6} On September 22, 2003, Euclid filed a complaint against Mount Zion and Pricom for breach of contract. On December 5, 2003, Pricom filed its answer and a cross-claim against Mount Zion for breach of contract. On December 18, 2003, Mount Zion filed its answer to Pricom's cross-claim. On the same date, Mount Zion filed a motion for leave to file its answer and cross-claim instanter. Euclid opposed Mount Zion's motion and sought default judgment; however, on January 2, 2004, the trial court denied Euclid's motion for default judgment and permitted Mount Zion to file its answer and cross-claim instanter. On January 8, 2004, Mount Zion filed its answer to Euclid's complaint and cross-claim for reimbursement from Pricom in the event it is held liable to Euclid.

{¶ 7} On August 27, 2004, the matter was tried to the bench. On September 22, 2004, the trial court filed its judgment entry granting judgment to Pricom against Mount Zion for $25,900 plus costs and interests. The court also awarded judgment in Euclid's favor against Pricom in the amount of $17,100, plus costs and interests. Mount Zion's cross-claim against Pricom was dismissed.

{¶ 8} Mount Zion now appeals and asserts seven assignments of error for our review.

{¶ 9} Before addressing its assigned errors, we must mention Mount Zion's brief fails to comply with App.R. 19(A) which requires appellate briefs to be double spaced. Although we do not hold this oversight fatal, we beseech all parties to consult the appellate rules before submitting their briefs to the court.

{¶ 10} Mount Zion's first assignment of error asserts:

{¶ 11} "[1.] The trial court erred when it considered parol evidence to change a contract clear and unambiguous on its face."

{¶ 12} Mount Zion contends the trial court improperly considered extrinsic evidence to interpret the clear and unambiguous contract in violation of the parol evidence rule. Although Mount Zion alleges the trial court used parol evidence, the trial court's September 22, 2004 judgment entry states:

{¶ 13} "Where there exists a written contract, the express terms of the contract must be followed and oral agreements outside of the written contract may not be used to modify the contract or explain its terms. Shifrin v. Forest CityEnterprises, Inc. 64 Ohio St.3d 635, 638, 1992-Ohio-28. Likewise, parol evidence is not admissible to explain contract terms unless the contract is ambiguous. Id. The court finds the contract between Mount Zion and Pricom is clear and the terms are not ambiguous."

{¶ 14} Clearly, the trial court's judgment entry nominally belies Mount Zion's challenge. However, with respect to the issue of ambiguity, we find both the trial court's and Mount Zion's position problematic.

{¶ 15} The contract provides for paving of 28,000 square feet at a cost of $46,200. At the bottom of the contract, the phrase "additional area" appears for which Pricom charged $800. Further, hovering in the right margin of the contract are the handwritten words "curves and lining include." The total cost listed on the contract is $47,000. The trial court maintained the contract is clear and unambiguous because the only reference to paving is in relation to a 28,000 square foot area whose cost is $46,200. Alternatively, Mount Zion argues the agreement is clear and unambiguous because "additional area" referred to in the contract denoted the extra 18,000 square feet of paving. One thing is clear, these two competing interpretations demonstrate the contract is not unambiguous.

{¶ 16} The parol evidence rule states: "absent fraud mistake or other invalidating cause, the parties' final written integration of their agreement may not be varied, contradicted or supplemented by evidence of prior or contemporaneous oral agreements, or prior written agreements." Galmish v. Cicchini,90 Ohio St.3d 22, 26, 2000-Ohio-7, quoting 22 Williston Contracts, (4th Ed. 1999), 569-570, Section 33:4. However, "[w]here a term is ambiguous, parol evidence is admissible to interpret, but not contradict, the express language of the contract." Sherock v. Ohio Mun. League Joint Self-Ins. Pool, 11th Dist. No. 2003-T-0022, 2004-Ohio-1515, at ¶ 16.

{¶ 17} Here, the contract in question is reasonably susceptible to more than one interpretation, i.e. one could reasonably find the agreement ambiguous by virtue of the undefined character of the phrase "additional area." As we examine the trial court's application of law in a breach of contract action de novo,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

5500 S. Marginal Way, L.L.C. v. Parker
2022 Ohio 1071 (Ohio Court of Appeals, 2022)
Ma v. Cincinnati Children's Hosp.
2020 Ohio 1471 (Ohio Court of Appeals, 2020)
Crandall v. Crandall
2020 Ohio 625 (Ohio Court of Appeals, 2020)
Hague v. Kosicek
2019 Ohio 2089 (Ohio Court of Appeals, 2019)
Thompson v. Faddis, Unpublished Decision (3-2-2007)
2007 Ohio 891 (Ohio Court of Appeals, 2007)

Cite This Page — Counsel Stack

Bluebook (online)
2005 Ohio 7049, Counsel Stack Legal Research, https://law.counselstack.com/opinion/euclid-asphalt-paving-v-pricom-asphalt-unpublished-decision-12-29-2005-ohioctapp-2005.