ETU, Inc. v. Environmental Quality Commission

162 P.3d 248, 343 Or. 57, 2007 Ore. LEXIS 593
CourtOregon Supreme Court
DecidedJune 28, 2007
DocketDEQ LQ/T-NWR-02-096; CA A121106; SC S53634
StatusPublished
Cited by2 cases

This text of 162 P.3d 248 (ETU, Inc. v. Environmental Quality Commission) is published on Counsel Stack Legal Research, covering Oregon Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
ETU, Inc. v. Environmental Quality Commission, 162 P.3d 248, 343 Or. 57, 2007 Ore. LEXIS 593 (Or. 2007).

Opinion

*59 GILLETTE, J.

This is an administrative law case involving a Department of Environmental Quality (DEQ) final order assessing civil penalties against ETU, Inc. (ETU) and Ed Niemi Oil Company, Inc. (Niemi) (collectively, respondents 1 ). The issues presented are whether DEQ erred in choosing to serve a notice of violation and subsequent default orders only on respondents’ registered agent, rather than also serving them on their lawyer, Bakalian. A derivative issue involves whether, if the manner of service was not itself error, DEQ nonetheless erred in denying respondents’ late request for a hearing, when the request arose out of DEQ’s failure to provide Bakalian with copies of the notice and orders in question. The Court of Appeals concluded that respondents did not timely seek judicial review of the default orders and, therefore, the Court of Appeals lacked jurisdiction over that part of the case. It also held that DEQ did not abuse its discretion, and therefore did not err, in denying respondents’ late request for a hearing. ETU, Inc. v. Environmental Quality Commission, 205 Or App 282, 134 P3d 1019 (2006). For the reasons that follow, we reverse the decision of the Court of Appeals.

The facts of this case are mainly undisputed and are adequately set out in the Court of Appeals opinion. We quote them here:

“Niemi owns a gas station, and ETU owns the gas station’s underground storage tanks. In February 1999, while Niemi and ETU were upgrading the underground storage tanks, petroleum product was discovered in the soil and groundwater in the area surrounding the tanks; such uncontained petroleum is referred to as ‘free product.’ In March 1999, DEQ issued respondents a notice of noncompliance, requesting that they, among other actions, engage in removal of the free product. In the ensuing three years, respondents failed to conduct free product removal to DEQ’s satisfaction.
*60 “In early 2002, respondents retained their current attorney, Bakalian. In April of that year, Bakalian notified DEQ that he would be representing respondents with regard to the contamination of the area around the gas station. That same month, DEQ issued respondents a second notice of noncompliance for failing to conduct free product removal; DEQ served Bakalian with a copy of the notice. Following that notice, respondents conducted free product removal on a regular basis.
“In August 2002, Bakalian met with DEQ representatives to discuss the status of the second notice of noncompliance issued against respondents. At that meeting, the DEQ representatives indicated that DEQ was in the process of [assessing] penalties against respondents for several alleged past violations. Bakalian gave one of them his business card and requested that he be notified of any actions taken against respondents.
“On September 19, 2002, DEQ issued respondents, jointly and severally, a notice of violation assessing a civil penalty in the amount of $126,522.* * * The notice of violation indicated that it would become final ‘by operation of law without any further action or proceeding’ unless DEQ received a request for a hearing on the matter, accompanied by a written answer to allegations made in the notice, within 20 days. Despite Bakalian’s earlier request, DEQ did not serve the notice on Bakalian. Instead, DEQ served respondents’ registered agent, Bechtolt (who was also Niemi’s president), by certified mail with return receipt.
“Although Bechtolt wrote a letter dated October 1 requesting that DEQ hold a hearing and send all information pertaining to the matter to Bakalian, DEQ found that it never received that letter. Because DEQ did not receive a response from respondents within 20 days, it * * * issued default final orders. Although a single notice of violation had been issued to respondents jointly and severally, the default final orders were issued to respondents separately: to Niemi on October 11 and to ETU on October 16. Again, DEQ served Bechtolt, but not Bakalian.
“Bakalian first learned of the default final orders when a consultant notified him of the penalty sometime between October 18 and October 23, prompting him to contact DEQ for copies of the documents on October 23. Respondents then attempted to obtain a hearing by submitting an *61 answer and late request for hearing on October 31. In their request, they contended that Bechtolt, in fact, had written to timely request a hearing; that DEQ had failed to serve Bakalian; and that therefore they were making the late request because of circumstances beyond their reasonable control, as provided in administrative rules applicable to late hearing requests. In answer to the notice of violation, they responded to DEQ’s allegations and offered affirmative defenses. DEQ concluded that respondents did not have good cause for failing to file a timely answer and, accordingly, on November 26, denied the late hearing request.
“Respondents petitioned for reconsideration on December 23.* * * In the petition, respondents sought reconsideration of the October 11 default final order and the November 26 order denying the late hearing request. DEQ denied that petition on January 29, 2003. On March 31, 2003, respondents filed a petition for judicial review.”

205 Or App at 284-86 (footnotes omitted).

In their petition for judicial review in the Court of Appeals, respondents sought relief from the January 29, 2003, final order as well as from the underlying default final orders assessing the civil penalty, arguing that DEQ had erred by failing to serve the notice of violation on Bakalian, by failing to serve counsel with the notices of default, and by denying their late request for a hearing and subsequent petition for reconsideration.

The Court of Appeals began its analysis by noting that its jurisdiction over such matters is governed by ORS 183.482(1), which confers jurisdiction on the Court of Appeals to review final orders in contested cases. That statute provides:

“Jurisdiction for judicial review of contested cases is conferred upon the Court of Appeals. Proceedings for review shall be instituted by filing a petition in the Court of Appeals. The petition shall be filed within 60 days only following the date the order upon which the petition is based is served unless otherwise provided by statute. If a petition for rehearing has been filed, then the petition for review shall be filed within 60 days only following the date the order denying the petition for rehearing is served. If the agency *62 does not otherwise act, a petition for rehearing or reconsideration shall be deemed denied the 60th day following the date the petition was filed, and in such cases, petition for judicial review shall be filed within 60 days only following such date. Date of service shall be the date on which the agency delivered or mailed its order in accordance with ORS 183.470.”

Free access — add to your briefcase to read the full text and ask questions with AI

Related

State v. Mullins
284 P.3d 1139 (Oregon Supreme Court, 2012)
SAIF Corporation v. Miguez
277 P.3d 601 (Court of Appeals of Oregon, 2012)

Cite This Page — Counsel Stack

Bluebook (online)
162 P.3d 248, 343 Or. 57, 2007 Ore. LEXIS 593, Counsel Stack Legal Research, https://law.counselstack.com/opinion/etu-inc-v-environmental-quality-commission-or-2007.