Estey v. Susquehanna Pipeline Co.

199 Misc. 290, 98 N.Y.S.2d 560, 1950 N.Y. Misc. LEXIS 1794
New York Supreme Court·Decided March 31, 1950·Published·Cited by 4 cases

Opinion

Searl, J.

Plaintiffs have for many years been the owners of a farm located in the town of Tully, Onondaga County, New York. In December, 1947, Sun Pipeline Company, Inc., was merged into Susquehanna Pipeline Company, Inc., and assumed any and all liability of the former company. For convenience, defendant and its predecessor will be termed “ the company.”

In 1931, the company was installing a pipe line for the conveyance of gasoline from Marcus Hook, -Pennsylvania, to the Barge Canal Terminal outside the western limits of the city of Syracuse. On the 15th day of January, 1931, an agreement was executed between the plaintiffs and Sun Pipeline, Inc., providing for the grant of an easement and right of way across plaintiffs’ lands for the installation, maintenance, repair and operation of one steel pipe, six and five-eighths inches outside measurement, weighing 19.97 pounds per foot, with welded joints, placed in a trench twelve inches wide, to be dug with a digging machine six feet wide over all, or by hand. The pipe was to be covered not less than twenty-four inches with dirt, the dirt to be replaced in the trench by machine and by hand and left six inches above the normal level of the ground to allow for settling. The agreement further provided that all surplus dirt and stone was to be removed, the ground to be left clear and all fences replaced, the top soil not to be replaced as top soil, the total depth of the trench to be from thirty to thirty-six inches. At ditches and places where the line was subject to damage, the depth of the trench could be greater according to the protection needed. The agreement further provided that the fine be constructed and maintained in such manner as not to prevent or interfere with the drainage of plaintiff’s farm or adjoining land, or with any open ditch required for draining purposes. The grantee, Sun Pipeline, Inc., agreed to use the right of way in such a manner as to not unnecessarily interfere with the grantor’s use of the premises and to pay any damages that might arise to the grantor’s lands adjoining the pipe line, or to crops, fences, drains or buildings, either from installation, maintenance, or operation of the pipe line. The grantee agreed to patrol the line twice a week and at such other times as it might be in need of inspection in order to insure safety. Further, the easement, or right of way, was defined as a strip of land twelve feet in width between parallel lines, each six feet measured at right angles on each side of, and parallel to, the center line.

It appears that shortly thereafter, the Sun Pipeline Company, Inc., constructed the pipe line in a trench twelve inches wide [293]*293and commenced operations by using the same for the transportation of gasoline and petroleum products. The line apparently functioned satisfactorily until the year 1940, when it was found that the acidity of the soil at certain points along the pipeline caused pitting in the steel pipe, and threatened, if continued, to cause leakage and damage. Accordingly, in the year 1940, the defendant, at certain points along its right of way, including that portion of the pipe line which ran through the so-called “bottom land” of plaintiff, encased the pipe within a twelve inch square wooden box and surrounded the pipe with a material intended to prevent further pitting. The evidence disclosed that in the first instance, Sun Pipeline Company, Inc. paid to these plaintiffs as a consideration for the easement the sum of $2,381.10. When the work was done in 1940, an additional sum of $50 was paid to the plaintiffs for any damage that the plaintiffs suffered in that particular repair operation.

From the time the original pipe line was installed in 1931, and since the boxing of the pipe in 1940, a coating for pipes has been discovered, a patented product known as ‘ ‘ Somastic. ’ ’ When applied to the outer surface of metal pipes, this cement-like covering apparently effectually prevents further deterioration by pitting due to an acid soil condition.

The repair operation was commenced by defendant at a point south of plaintiffs’ farm land and continued northward toward Syracuse. On or about August 22, 1946, defendant moved its equipment necessary for this work upon plaintiffs’ property. The covering of the pipe extending through this farm for a distance of 2,080 feet over defendant’s right of way was completed some twenty days later. The work was accomplished by use of a specially built machine some twenty feet in width which held the pipe after it was raised from its trench, intact. First, the outer surface of the pipe was cleaned and polished by a system of revolving wire brushes. The same machine contained a heating apparatus which melted to a volatile state, by a high degree of heat, the so-called “ Somastic ”. This was automatically applied by the operation of the same machine to the outside of the pipe to the thickness of 7/16 of an inch. Doubling this would increase the outside diameter of the pipe from 6% inches, as originally installed, to 7% inches. The evidence fairly discloses, however, that this substance is not deleterious to crop raising or proper husbandry, so far as the operation of the farm is concerned. The pipe returned to its trench is not sufficiently [294]*294close to the surface to interfere with plowing, cultivating, nor fitting of the soil.

As to the pleadings: Plaintiffs’ original complaint set forth two alleged causes of action. The first alleged that the work performed by defendant in 1946 was done without consent of the plaintiffs, that it constituted a trespass. The complaint asked a declaratory judgment to effect that the operation violated plaintiffs’ property rights and was in excess of rights granted defendant in the original agreement of 1931. The complaint asked a judgment directing defendant to remove the “ Somastic ” coating.

The second cause of action sought $8,500 damages alleged to have been sustained by reason of the work performed by defendant in 1946.

An amended complaint was served in which a mandatory injunction and restraining order was demanded in addition to the relief sought in the original complaint.

The answer alleges that plaintiffs granted a right of way and license to defendant to perform the acts complained of, as well as loches, and that an adequate remedy at law exists.

We must start our consideration of the merits of plaintiffs’ claims with the knowledge that defendant is a pipe line corporation as defined by section 80 of the Transportation Corporations Law “ to construct and operate ” as well as “to maintain and operate for public use” — “lines of pipe for conveying or transporting therein petroleum, gas, liquids or any products or property.” Section 81 permits such corporation to lay out its route not exceeding twelve feet in width and in case of its inability to agree for the purchase of any real property to acquire title thereto by condemnation, subject to certain restrictions including buildings, dooryards, lawn, garden or orchard.

Granting that defendant caused some damage to plaintiffs’ property in this 1946 operation, to be referred to later more in detail, it is proper to consider first whether there was a willful trespass on the property, and second, whether there is evidence justifying a conclusion that such trespass is likely to be repeated. The evidence discloses that prior to the arrival of the equipment on plaintiffs’ premises in 1946, a representative of defendant called on plaintiffs, telling them that the application of the coating to the line would require more than a twelve-foot right of way.

Free access — add to your briefcase to read the full text and ask questions with AI

Estey v. Susquehanna Pipeline Co., 199 Misc. 290, 98 N.Y.S.2d 560, 1950 N.Y. Misc. LEXIS 1794 (N.Y. Super. Ct. 1950).

199 Misc. 290 (Estey v. Susquehanna Pipeline Co.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Davis v. Arkansas Louisiana Gas Co.
454 S.W.2d 331 (Supreme Court of Arkansas, 1970)
Thomas v. Cilbe, Inc.
104 So. 2d 397 (District Court of Appeal of Florida, 1958)
Brearton v. Fina
3 Misc. 2d 1 (New York County Courts, 1956)