M. O'Neil Supply Co. v. Petroleum Heat & Power Co.

19 N.E.2d 676, 280 N.Y. 50, 1939 N.Y. LEXIS 1286
New York Court of Appeals·Decided February 28, 1939·Published·Cited by 118 cases

Opinion

Rippey, J.

Plaintiff appeals, by permission of this court, from a judgment entered upon the order of the Appellate Division, first department, unanimously affirming the judgment entered upon an order of Special Term dismissing the first cause of action on motion of defendant under rule 106 of the Rules of Civil Practice on the ground that the complaint did not state facts sufficient to constitute a cause of action.

Plaintiff alleges that defendant and one Charles had entered into an agreement prior to July 16, 1936, whereby Charles agreed to do certain pipe installation and other work in connection with a heating plant that defendant was installing in the Lombardy Hotel and in adjacent buildings in New York city, that Charles had purchased certain materials from plaintiff and owed a balance thereon for which plaintiff was about to file a mechanic’s lien against the real property in course of improvement and against defendant and Charles, and that Charles had stopped work because of disagreements with defendant. It appears that defendant had the general contract for the work and that Charles was its subcontractor.

The plaintiff further alleges that the plaintiff, Charles and defendant thereupon entered into a tripartite agreement in writing which is made a part of the complaint. It is this contract which furnishes the basis for the cause of action which has been dismissed. In the contract, it is recited that differences have arisen between the parties under the subcontract, that Charles has filed a lien against the property and that defendant has made certain payments to Charles for work already done under the contract. Charles agreed to waive any right which he might have on the lien filed and to any claim against defendant by lien or otherwise for past or future labor and services upon payment by defendant to Charles or to his assignee of $950. Charles agreed promptly to proceed with and complete the *53 work remaining to be done. Plaintiff agreed to furnish the necessary materials for completion of the work and to waive any right to a lien on the premises or to any further claim for payment for the materials already furnished or to be furnished on payment by defendant to it of the sum of $2,800 at its request “ five days after the completion of the installation by said Thomas J. Charles in accordance with the contract or purchase orders No. 943, etc., above referred to and the specifications accompanying the same and approval of the same by Edwin A. Kingsley, engineer for Petroleum Heat & Power Company, Inc.”

Charles failed to complete the installation and defendant finished the work. Plaintiff refrained from filing any lien and furnished all materials required for the completion of the contract and alleges that it fully performed all obligations specified in the contract to be performed by it. Defendant refused to pay the $2,800 which it agreed to pay on the sole ground that Charles personally did not complete the work. In the complaint, it is alleged that it was intended and agreed between the parties that the sum of $2,800 should be paid by defendant to plaintiff five days after the completion of the work or within a reasonable time thereafter and that “ said completion bore upon plaintiff’s right of payment solely as convenient means of fixation of the time thereof, and not as condition precedent to the right of such payment and the parties intended said right of payment should be absolute.” To sustain the complaint, plaintiff is entitled to every favorable inference that reasonably may be drawn from the allegations that it contains.

Defendant claims, so far successfully, that completion of the installation by Charles was a condition precedent to its liability under the contract and much reliance is placed on Amies v. Wesnofske (255 N. Y. 156), but nothing was decided in that case which is contrary to the contentions of plaintiff. Upon the evidence-in that case, the jury found that defendants had agreed to pay to plaintiffs, acting as real estate brokers, certain commissions on the closing of *54 title ” to premises being sold by defendants to third parties. Title was never closed, the closing was neither prevented nor hindered by defendants and there was no waiver by defendants of the condition precedent to liability. It was held that plaintiffs could not recover. In such a case the obligation itself was contingent. The promise to pay extended to the debt itself. We think that here it could be found that it was the intention of the parties that the debt should be fixed and absolute and that the condition concerning payment attached solely to the event of completion of the work, the happening of which established a convenient time of payment (3 Williston on The Law of Contracts [Rev. ed.], § 799).

Free access — add to your briefcase to read the full text and ask questions with AI

M. O'Neil Supply Co. v. Petroleum Heat & Power Co., 19 N.E.2d 676, 280 N.Y. 50, 1939 N.Y. LEXIS 1286 (N.Y. 1939).

19 N.E.2d 676 (M. O'Neil Supply Co. v. Petroleum Heat & Power Co.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

25 Bay Terrace Assoc., L.P. v. Public Serv. Mut. Ins. Co.
2021 NY Slip Op 02776 (Appellate Division of the Supreme Court of New York, 2021)
Acushnet Company v. Beam, Inc.
93 N.E.3d 1186 (Massachusetts Appeals Court, 2018)
Pesa v. Yoma Development Group, Inc.
965 N.E.2d 228 (New York Court of Appeals, 2012)
Davidson v. Regan Fund Management Ltd.
13 A.D.3d 117 (Appellate Division of the Supreme Court of New York, 2004)
Aini v. Sun Taiyang Co., Ltd.
964 F. Supp. 762 (S.D. New York, 1997)
Ashland Management Inc. v. Janien
624 N.E.2d 1007 (New York Court of Appeals, 1993)
Burger King Corp. v. Horn & Hardart Co.
710 F. Supp. 103 (S.D. New York, 1989)
Corning Glass Works v. Southern New England Telephone Co.
674 F. Supp. 999 (W.D. New York, 1987)
William Rothenberg v. Lincoln Farm Camp, Inc.
755 F.2d 1017 (Second Circuit, 1985)
Dodge v. Dodge
466 N.E.2d 841 (Massachusetts Appeals Court, 1984)
Schiavone Construction Co. v. County of Nassau
717 F.2d 747 (Second Circuit, 1983)
Schering Corp. v. Home Insurance
544 F. Supp. 613 (E.D. New York, 1982)