Estey v. MacKenzie Engineering Inc.

927 P.2d 86, 324 Or. 372
CourtOregon Supreme Court
DecidedFebruary 4, 1997
DocketCC 9212-08572; CA A82218; SC S42716
StatusPublished
Cited by29 cases

This text of 927 P.2d 86 (Estey v. MacKenzie Engineering Inc.) is published on Counsel Stack Legal Research, covering Oregon Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Estey v. MacKenzie Engineering Inc., 927 P.2d 86, 324 Or. 372 (Or. 1997).

Opinion

*374 VAN HOOMISSEN, J.

Plaintiff appeals a Court of Appeals’ decision affirming a circuit court’s grant of summary judgment in favor of defendants on plaintiffs claims for negligence, negligent misrepresentation, and breach of contract. Estey v. MacKenzie Engineering Inc., 137 Or App 1, 902 P2d 1220 (1995). The dis-positive issue is whether a clause in the parties’ contract limiting defendants’ liability “to the Contract Sum” applies to plaintiffs negligence claim. We hold that the clause does not limit defendants’ liability for negligence. Accordingly, we reverse the contrary ruling of the Court of Appeals.

Plaintiff hired defendant MacKenzie Engineering, Incorporated (MEI) to perform a “limited visual review” of a house that he intended to purchase. The review was intended to identify major structural deterioration, if any, including settlements to the structure. The parties’ contract set out the estimated contract sum of $200. It also provided:

“The liability of MEI and the liability of its employees are limited to the Contract Sum.”

Plaintiff signed the contract. MEI’s employee, defendant Krombein, a licensed professional engineer, conducted a limited visual review of the house and gave plaintiff a two-page written report. The report noted past moisture infiltration, “minor cracks” in the walls, “stretch marks” in the floors, and some settlement. The report further stated in part that “[t]he structure appeared to be in generally good condition,” that “[n]o major areas of structural deterioration were observed,” and that “ [although some previous movement of the foundation and structure was evident, it did not appear that any major failure or immediate movement of the foundation was eminent.”

After he received MEI’s report, plaintiff purchased the house. Six weeks later, plaintiff discovered that a broken water pipe had been leaking under the house before the date of Krombein’s inspection. He also noticed that the floors in the house slanted in an easterly direction and that, when opened, the doors swayed in the same direction. Plaintiff hired another engineering firm to inspect the house. That *375 firm reported that “It appears probable that at the time of original construction the easterly half of the residence was constructed on uncompacted fill which over time consolidated. The consolidation resulted in settlement of the footings and the recent breaking of the water service line has resulted in additional settlement due to saturation of the underlying uncompacted surficial soils.” The subsidence caused extensive cracking and other damage to the house. At the time the summary judgment motion was filed, plaintiff already had spent about $190,000 on repairs and, based on contractors’ bids, he estimated that he would spend another $150,000 repairing and stabilizing the house.

Plaintiff brought this action against MEI and Krom-bein, alleging negligence, negligent misrepresentation, and breach of contract. Plaintiff sought damages of $340,000 for the cost of repairing and stabilizing his house. Defendants moved for summary judgment, asserting the limitation of liability clause in the parties’ contract as an affirmative defense. Plaintiff moved for partial summary judgment on the ground that the limitation of liability clause is unenforceable.

The circuit court granted defendants’ motion for summary judgment, concluding that the contract limited defendant’s liability for negligence, negligent misrepresentation, and breach of contract. The parties stipulated that, if enforceable, the limitation of liability clause constitutes a complete bar to plaintiffs claims for damages. The Court of Appeals affirmed, holding that the limitation clause barred plaintiff s claim, because it was conspicuous, clear and unequivocal, and did not violate public policy. Estey, 137 Or App at 5-6. We allowed plaintiffs petition for review.

Plaintiff argues that the limitation of liability clause is unenforceable with respect to his negligence claim, because the clause does not clearly and unequivocally express an intent to limit defendants’ liability for negligence. Plaintiff further argues that a professional engineer who performs residential inspection services is charged with a duty of public service and, therefore, may not insulate himself from the consequences of his own negligence.

Defendants argue that the clause at issue in this case clearly and unequivocally expresses the parties’ intent *376 that defendants’ liability for negligence be limited to the contract sum and, therefore, it is enforceable. Defendants further argue that they did not assume a duty of public service by entering into the contract and, therefore, principles of public policy do not justify the invalidation of the clause.

In K-Lines, Inc. v. Roberts Motor Co., 273 Or 242, 248, 541 P2d 1378 (1975), this court held:

“Agreements to exonerate a party from liability or to limit the extent of the party’s liability for tortious conduct are not favorites of the courts but neither are they automatically voided. The treatment courts accord such agreements depends upon the subject and terms of the agreement and the relationship of the parties.”

This court has examined contractual provisions that purport to immunize a party from the consequences of his or her own negligence and has held such provisions to be enforceable under limited circumstances. In Transamerica Ins. Co. v. U.S. Nat’l Bank, 276 Or 945, 951, 558 P2d 328 (1976), the court held:

“[A] contract will not be construed to provide immunity from the consequences of a party’s own negligence unless that intention is clearly and unequivocally expressed, and * * * an ambiguous instrument * * * will be construed against the party who drafted it.”

See also Waterway Terminals v. P.S. Lord, 242 Or 1, 19, 406 P2d 556 (1965) (“a presumption will be indulged against an intention to contract for immunity from the consequence of one’s own negligence”); Southern Pacific Co. v. Layman, 173 Or 275, 279, 145 P2d 295 (1944) (“contracts of indemnity will not be construed to cover losses to the indemnitee caused by his own negligence unless such intention is expressed in clear and unequivocal terms”).

The court’s inquiry into the parties’ intent in this regard has focused not only on the language of the contract, but also on the possibility of a harsh or inequitable result that would fall on one party by immunizing the other party from the consequences of his or her own negligence. See, e.g., Commerce & Industry Ins. v. Orth, 254 Or 226, 231-32, 458 P2d 926 (1969) (so stating); Layman, 173 Or at 280 (same). That *377 inquiry in turn focuses on the nature of the parties’ obligations and expectations under the contract.

Layman provides a good example of this principle. The contract at issue in Layman allowed a landowner to construct a road across an adjacent railroad’s right-of-way.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Certain Underwriters v. TNA NA Manufacturing
523 P.3d 447 (Court of Appeals of Oregon, 2022)
Sugarman v. IRZ Consulting, LLC
E.D. California, 2022
Clement v. Ecolab, Inc.
341 F. Supp. 3d 1205 (D. Oregon, 2018)
Kaste v. Land O'Lakes Purina Feed, LLC
392 P.3d 805 (Court of Appeals of Oregon, 2017)
Stacy Sanislo v. Give Kids The World, Inc.
157 So. 3d 256 (Supreme Court of Florida, 2015)
Bagley v. Mt. Bachelor, Inc.
340 P.3d 27 (Oregon Supreme Court, 2014)
Bagley v. Mt. Bachelor, Inc.
310 P.3d 692 (Court of Appeals of Oregon, 2013)
Wood Park Terrace Apartments Ltd. Partnership v. Tri-Vest, LLC
297 P.3d 494 (Court of Appeals of Oregon, 2013)
Finch v. Inspectech, LLC
727 S.E.2d 823 (West Virginia Supreme Court, 2012)
Abraham v. T. Henry Construction, Inc.
249 P.3d 534 (Oregon Supreme Court, 2011)
State Ex Rel. Department of Forestry v. PacifiCorp
237 P.3d 861 (Court of Appeals of Oregon, 2010)
Dept. of Forestry v. PacifiCorp
237 P.3d 861 (Court of Appeals of Oregon, 2010)
National Union Fire Insurance v. Starplex Corp.
188 P.3d 332 (Court of Appeals of Oregon, 2008)
Blanchfill v. Better Builds, Inc.
982 P.2d 53 (Court of Appeals of Oregon, 1999)
Steele v. Mt. Hood Meadows Oregon, Ltd.
974 P.2d 794 (Court of Appeals of Oregon, 1999)

Cite This Page — Counsel Stack

Bluebook (online)
927 P.2d 86, 324 Or. 372, Counsel Stack Legal Research, https://law.counselstack.com/opinion/estey-v-mackenzie-engineering-inc-or-1997.