ERKA Construction Co., Ltd.

CourtArmed Services Board of Contract Appeals
DecidedMarch 9, 2016
DocketASBCA No. 57618, 58515
StatusPublished

This text of ERKA Construction Co., Ltd. (ERKA Construction Co., Ltd.) is published on Counsel Stack Legal Research, covering Armed Services Board of Contract Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
ERKA Construction Co., Ltd., (asbca 2016).

Opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS

Appeals of -- ) ) ERKA Construction Co., Ltd. ) ASBCA Nos. 57618, 58515 ) Under Contract No. W91GF5-07-M-4004 )

APPEARANCE FOR THE APPELLANT: Paul D. Reinsdorf, Esq. Frankfurt, Germany

APPEARANCES FOR THE GOVERNMENT: Raymond M. Saunders, Esq. Army Chief Trial Attorney MAJ James P. Leary, JA LTC Jose A. Cora, JA Trial Attorneys

OPINION BY ADMINISTRATIVE JUDGE O'CONNELL

These appeals arise out of a contract between the government and ERKA Construction Co., Ltd. (ERKA) in which ERK.A operated a "bum pit" at Joint Base Balad in Iraq. The contract provided for the government to furnish ERKA fuel to perform the contract work. The government contends that ERKA stole hundreds of thousands of gallons of fuel, which it then sold outside the base, among other things. Before the Board is a government claim for $482,212.22, which represents the government's calculation of the value of the fuel allegedly stolen. The Board conducted a three-day hearing from 9-11 March 2015 in Falls Church, Virginia. Only entitlement is before the Board.

FINDINGS OF FACT

Notable Contract Provisions

On 19 February 2007, the parties entered into the contract referenced above; it included a base year with a firm-fixed-price of $1,659,600, plus several six-month options (R4, tab 1 at 1-10). Due to these options, ERKA was still performing the contract work in 2009 when the events at issue took place (R4, tabs 3, 8, 11).

Joint Base Balad (the Base) was the largest American base in Iraq. The Base produced an enormous amount of trash per day, including in excess of 120 tons of burnable materials, plus recyclable metals and construction debris. However, it lacked a permanent landfill or a viable method to transport waste off the installation. The contract provided for ERKA to operate a 28-acre bum pit. (R4, tab 1, performance work statement (PWS) at 1) In the bum pit, ERKA performed screening and inspection, burning, metal removal, concrete crushing, and site remediation operations (id. at 24; tr. 11189). The contract provided for ERKA to transport the ash generated by the burning operations to a certified landfill (R4, tab 1 at 26). Eventually, the government learned that there was no certified landfill 1 in all of Iraq, which resulted in the government requiring an alternate method to dispose of the ash (tr. 1/203-04). Disposition of this ash played some role in the events that followed.

The government provided ERKA with fuel "for official use only in support of this Contract," which prohibited ERK.A from transporting "bulk fuel" off the Base. The contract also provided that ERKA's contract price should take into account the fuel provided by the government and that the government would investigate contractors who were suspected of fraud, waste or abuse. (R4, tab 1at15, ~ 13.27)

The Byles Investigation

ERKA was not the only contractor entitled to receive fuel without charge to perform its contract work (tr. 1/240). The government provided fuel to these contractors on what might be described as the honor system because there was no oversight to ensure that they took only the amount reasonably required to perform their contract work (tr. 1149, 2/31). Not surprisingly, allegations arose that contractors were abusing this system.

In 2009, Air Force Special Agent (SA) Matthew Byles was deployed to the International Contract Corruption Task Force. In late July 2009, he arrived at the Base. (Tr. 1/19) One of SA Byle's first actions was to print flyers in several languages that alerted people to a contract fraud tip line (tr. 1/28). Almost immediately, he received a call about theft at the "fuel farm," the area where the government, through another contractor, provided fuel to eligible contractors. SA Byles spoke with the caller at length on 30 July 2009, and then met with him in person on 31 July. (Tr. 1/29)

The informant described a systemic fuel theft problem. 2 The basic scheme, as it related to ERKA, involved a fuel truck obtaining fuel at the bulk fuel farm and driving to the bum pit. Then, it would distribute the fuel to vehicles to which the owners had added additional fuel tanks to carry more fuel, and which could then carry the fuel off

1 The record does not explain what a "certified" landfill is, but an understanding of this is not required to resolve these appeals. 2 Although SA Byles' hearing testimony appeared to focus on his interactions with one witness, SA Byles appears to have interviewed two witnesses on 31 July 2009 who told him similar stories (supp. R4, tab 38 at 16-17). In any event, our findings are based on what SA Byles saw, not what the informants told him.

2 the Base. (Tr. 1132-33) SA Byles was initially skeptical of the informant's allegations due to the volume of the thefts that he alleged - the informant stated that he had a standing offer to buy 7,000 liters of fuel per day (tr. 1129-30).

SA Byles then began an investigation in which he conducted visual surveillance and took advantage of security cameras around the Base that had zoom and thermal capabilities (tr. 1/33-34). Some components of this system are "aerial"; because they are classified, SA Byles declined to go into specifics beyond stating that they are a "very similar concept" to a blimp (tr. 11164-65). He conducted surveillance for approximately 30 days (tr. 1/67). In general, he observed dump trucks arriving at the Base gate in the morning where they would be met by an ERKA representative (tr. 1137). As part of the security screening at the entrance, the trucks would be scanned for organic materials (explosives). Because fuel is an organic material, SA Byles was able to ascertain that the trucks barely had any fuel on them when they entered the Base in the morning (tr. 1/70-71). After passing through security, the trucks would proceed to the bum pit area, which was two to three miles from the gate (tr. 1141-42).

At the bum pit, the drivers would park their trucks along a fence line and proceed into an ERKA trailer (tr. 1/42). On most days, he observed "a lot of socializing and a lot of parked vehicles" (tr. 11167). On some days, SA Byles observed the trucks spreading ash around the compound, or he saw a bucket-loader place a scoop of metals in a truck, usually not enough to fill the truck (tr. 1143-44), but most of the time the trucks were idle (tr. 1/45). SA Byles testified that the trucks left the Base with empty beds about 75 percent of the time (tr. 11109).

ERKA obtained fuel by sending a tanker truck to the fuel farm. On most days during SA Byles' surveillance, ERKA sent a 3,500 gallon tanker to the fuel farm, which would then return to the bum pit (tr. 1148-50). One day during the first week of his surveillance, SA Byles noticed more activity than usual. Specifically, he saw interaction between (1) ERKA's foreman (who held a ledger); (2) the man who fueled the trucks; and (3) the Iraqi drivers of the trucks. The man who filled the tanks had a ruler and was using it to measure the added tanks. Then, SA Byles saw the men entering numbers into a calculator or cellular phone. SA Byles interpreted this to mean that ERKA was charging the truck owners based on the amount of fuel they received. (Tr. 1163-64, 97-98)

SA Byles also observed that on some of the trucks the bed had to be raised because a second tank had been hidden and was not connected to the engine of the truck. Some of these tanks did not have a cap, and the workers would stuff a rag or plastic wrap in the hole. SA Byles observed an ERKA employee driving the tanker truck and distributing the fuel. (Tr. 1150-51) SA Byles also observed that all of the trucks had added tanks, and that an average of 20 to 30 ERKA trucks came on the base

3 each day (tr. 1/65-67; see supp.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Kellogg Brown & Root Services, Inc. v. United States
728 F.3d 1348 (Federal Circuit, 2013)
Schecter v. Merchants Home Delivery, Inc.
892 A.2d 415 (District of Columbia Court of Appeals, 2006)

Cite This Page — Counsel Stack

Bluebook (online)
ERKA Construction Co., Ltd., Counsel Stack Legal Research, https://law.counselstack.com/opinion/erka-construction-co-ltd-asbca-2016.