Erickson v. United States

107 F. 204, 1901 U.S. App. LEXIS 4517
CourtU.S. Circuit Court for the District of Washington
DecidedMarch 23, 1901
StatusPublished
Cited by2 cases

This text of 107 F. 204 (Erickson v. United States) is published on Counsel Stack Legal Research, covering U.S. Circuit Court for the District of Washington primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Erickson v. United States, 107 F. 204, 1901 U.S. App. LEXIS 4517 (circtdwa 1901).

Opinion

HANFORD, District Judge.

In February, 1897, the government of the United States, through the agency of Capt. W. L. Fisk, of the corps of engineers, United States army, entered into a contract with the plaintiff to prepare the ground and erect buildings for the Gray’s Harbor light station, in this state, under the supervision of the engineer for the Thirteenth light-house district, and according to plans and specifications and detail drawings attached to the contract. The contract included the furnishing of boilers and engines, but other ironwork necessary for the buildings and lantern glass for the light-house tower were to be furnished by other contractors. All the materials and workmanship were required to be inspected by an inspector to be employed by the engineer in charge, who was to be constantly on the ground for the purpose of seeing that all materials met the requirements of the contract, and that the work was properly done. Eight calendar months from the 18th day of February, 1897, were allowed for completion of the contract, and the contractor was subjected to a penalty of $30 per day for each day’s delay exceeding the time limited, and by subsequent agreements the time limit was extended to the 18th day of January, 1898, but the contract was not completed, and the work finally accepted, until March 26, 1898, and the government has retained 82,100 from the contract price as a forfeiture, under the penalty clause, for delay. The plaintiff sues to recover the amount so retained, also to recover from the government for extras, and for losses incurred in doing work and furnishing materials not specified or required by his contract, but which were exacted as the work progressed by the inspector, acting under the authority of the engineer in charge. The plaintiff claims that the delay in completing the contract beyond the time originally specified was caused entirely by capricious and unreasonable exactions and interference with the workmen on the part of the inspector assigned to the work, and delay on the part of other contractors in furnishing the ironwork and lantern glass, and delay on the part of the government officers in inspecting the boilers and other materials, and by bad weather, and that the fault of the government officers and agents and independent contractors has the effect to entirely abrogate the penalty clause of the contract. It is an admitted fact in the case that the iron materials required were not delivered until after the time fixed by the original contract for the completion of the work, and That the lantern glass was not delivered until 20 days after the limit [206]*206fixed by the last agreement for an extension, and yet the government claims that the extensions granted were sufficient to compensate for all delays not occasioned by the contractor’s own fault, and it is denied that any work or materials not specified in the contract were exacted, and it is denied that the contractor suffered any loss or expenses by arbitrary or capricious conduct on the part of the inspector.

On the face of the contract, it appears that the contractor engaged to execute the contract during that part of the year when the weather would be most favorable for such work, and the evidence proves conclusively that he made his calculations and arrangements accordingly; he was prompt in providing materials of lumber, stone, bricx, gravel, and cement, and went upon the ground with laborers and teams in the month of April, but an inspector was not sent to the place until about three weeks afterwards, and stakes which had to be set by the engineer for the exact location of the different structures were not set until some days after the inspector arrived. The boilers were ready for inspection and notice given in August, but there was two months’ delay on the part of the officers of the government in performing their duty in that particular. Kiln-dried flooring lumber was delivered on the ground in good season, and it could have been inspected in time to have replaced any part of it which might have been found to be' unsatisfactory, without retarding the work, but, instead of acting fairly, the inspector waited until the floors were laid, and then condemned the material, and the engineer required part of the floors to be taken up and replaced with new lumber. The delay in delivering the ironwork necessarily prevented the completion of the work during the dry season of the year, and the delay in the delivery of the lantern glass prevented the inclosure-of the tower, so that the cementing and painting inside could not be completed until after the expiration of the time for completing the whole work, as fixed by the last extension granted. It is also an undisputed fact that from about the 1st of November the weather was wet and stormy, so that the work from that time was necessarily slow and expensive. It is 'my opinion that these conditions entitle the contractor to claim that the delay was caused by the fault of the government and by the elements, and constitute a legal bar to enforcement of any forfeiture for delay.

The claim for extras is supported by clear and positive testimony, and is -contradicted by the testimony of the inspector, and for the most part the questions at issue are questions of fact, which must be determined by consideration of contradictory evidence. The charge for an extra injector and an extra pump are the only items with relation to which the witnesses agree as to the facts. The contract plainly specifies that one injector and one pump should be supplied. It is admitted that two of each were furnished to satisfy the demands of the inspector and engineer, and it is claimed that two were necessary, because the contract required two boilers, and one clause-.of the.contract.provides that everything necessary to make the structures complete and., ready for use shall be furnished by the contractor, whether specified Or not, and'another clause provides that all [207]*207boiler attachments are to he duplicated. These general provisions, however, should not control the specific provisions for one injector and one pump, and the only proper construction of the contract, in my opinion, is the construction given to it by the witness Robert Moran, who testified that these specifications would be understood by manufacturers and persons skilled in the construction of machinery to require a single injector and a single pump of capacity sufficient to supply tw7o boilers. The theory that duplicates were necessary to make the construction complete is refuted by the fact that, although two were supplied, only one injector and one feed pump are used. With regard to all the other disputed items, there appears to me to he a clear and substantial preponderance of the evidence in favor of the plaintiff. The plaintiff and his witnesses are all men of mature experience, of sufficient intelligence to understand the matters with respect to which their testimony was given, and their testimony appears to,he positive and candid. I have not found that any one who gave testimony on the plaintiffs side prevaricated with respect to any material matter, or that his testimony was overcome by a preponderance of evidence to the contrary. The case for the government rests mainly upon the unsupported testimony of Mr. G. W. Leick, who acted as inspector from the latter part of May until the 4th of December, when, on account of complaints as to his behavior, he was recalled. He would have been recalled sooner, if another inspector had been available. It is shown by the evidence that, by reason of a lack of a sufficient number of men subject to control of the engineer, Mr.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Henry Shenk Co. v. Erie County
178 A. 662 (Supreme Court of Pennsylvania, 1935)
Mason Tire & Rubber Co. v. Cummins-Blair Co.
157 N.E. 367 (Ohio Supreme Court, 1927)

Cite This Page — Counsel Stack

Bluebook (online)
107 F. 204, 1901 U.S. App. LEXIS 4517, Counsel Stack Legal Research, https://law.counselstack.com/opinion/erickson-v-united-states-circtdwa-1901.