Erickson v. United States

107 F. 204, 1901 U.S. App. LEXIS 4517
U.S. Circuit Court for the District of Washington·Decided March 23, 1901·Published·Cited by 2 cases

Opinion

HANFORD, District Judge.

In February, 1897, the government of the United States, through the agency of Capt. W. L. Fisk, of the corps of engineers, United States army, entered into a contract with the plaintiff to prepare the ground and erect buildings for the Gray’s Harbor light station, in this state, under the supervision of the engineer for the Thirteenth light-house district, and according to plans and specifications and detail drawings attached to the contract. The contract included the furnishing of boilers and engines, but other ironwork necessary for the buildings and lantern glass for the light-house tower were to be furnished by other contractors. All the materials and workmanship were required to be inspected by an inspector to be employed by the engineer in charge, who was to be constantly on the ground for the purpose of seeing that all materials met the requirements of the contract, and that the work was properly done. Eight calendar months from the 18th day of February, 1897, were allowed for completion of the contract, and the contractor was subjected to a penalty of $30 per day for each day’s delay exceeding the time limited, and by subsequent agreements the time limit was extended to the 18th day of January, 1898, but the contract was not completed, and the work finally accepted, until March 26, 1898, and the government has retained 82,100 from the contract price as a forfeiture, under the penalty clause, for delay. The plaintiff sues to recover the amount so retained, also to recover from the government for extras, and for losses incurred in doing work and furnishing materials not specified or required by his contract, but which were exacted as the work progressed by the inspector, acting under the authority of the engineer in charge. The plaintiff claims that the delay in completing the contract beyond the time originally specified was caused entirely by capricious and unreasonable exactions and interference with the workmen on the part of the inspector assigned to the work, and delay on the part of other contractors in furnishing the ironwork and lantern glass, and delay on the part of the government officers in inspecting the boilers and other materials, and by bad weather, and that the fault of the government officers and agents and independent contractors has the effect to entirely abrogate the penalty clause of the contract. It is an admitted fact in the case that the iron materials required were not delivered until after the time fixed by the original contract for the completion of the work, and That the lantern glass was not delivered until 20 days after the limit [206] fixed by the last agreement for an extension, and yet the government claims that the extensions granted were sufficient to compensate for all delays not occasioned by the contractor’s own fault, and it is denied that any work or materials not specified in the contract were exacted, and it is denied that the contractor suffered any loss or expenses by arbitrary or capricious conduct on the part of the inspector.

On the face of the contract, it appears that the contractor engaged to execute the contract during that part of the year when the weather would be most favorable for such work, and the evidence proves conclusively that he made his calculations and arrangements accordingly; he was prompt in providing materials of lumber, stone, bricx, gravel, and cement, and went upon the ground with laborers and teams in the month of April, but an inspector was not sent to the place until about three weeks afterwards, and stakes which had to be set by the engineer for the exact location of the different structures were not set until some days after the inspector arrived. The boilers were ready for inspection and notice given in August, but there was two months’ delay on the part of the officers of the government in performing their duty in that particular. Kiln-dried flooring lumber was delivered on the ground in good season, and it could have been inspected in time to have replaced any part of it which might have been found to be' unsatisfactory, without retarding the work, but, instead of acting fairly, the inspector waited until the floors were laid, and then condemned the material, and the engineer required part of the floors to be taken up and replaced with new lumber. The delay in delivering the ironwork necessarily prevented the completion of the work during the dry season of the year, and the delay in the delivery of the lantern glass prevented the inclosure-of the tower, so that the cementing and painting inside could not be completed until after the expiration of the time for completing the whole work, as fixed by the last extension granted. It is also an undisputed fact that from about the 1st of November the weather was wet and stormy, so that the work from that time was necessarily slow and expensive. It is 'my opinion that these conditions entitle the contractor to claim that the delay was caused by the fault of the government and by the elements, and constitute a legal bar to enforcement of any forfeiture for delay.

Free access — add to your briefcase to read the full text and ask questions with AI

Erickson v. United States, 107 F. 204, 1901 U.S. App. LEXIS 4517 (circtdwa 1901).

107 F. 204 (Erickson v. United States) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Henry Shenk Co. v. Erie County
178 A. 662 (Supreme Court of Pennsylvania, 1935)
Mason Tire & Rubber Co. v. Cummins-Blair Co.
157 N.E. 367 (Ohio Supreme Court, 1927)