Erickson v. Levin

236 Ill. App. 245, 1925 Ill. App. LEXIS 100
Appellate Court of Illinois·Decided February 11, 1925·No. Gen. No. 29,238·Published

Opinion

Mr. Justice Taylor

delivered the opinion of the court.

On December 21, 1921, the plaintiff, Advance Plastering Company, brought suit against the defendants, Michael Levin, George Silver and Tillie.Silver, claiming that it was entitled to a “mechanic’s lien” against certain property of George and Tillie Silver for the sum of $435. There was a trial before the court, without a jury, and a judgment entered against the defendant Michael Levin in the sum of $435; and a judgment in favor of the defendants, George Silver and Tillie Silver, against the plaintiff. This appeal is from the latter judgment.

It is admitted that in the early part of 1922 a written contract was made between the defendant Levin and the defendants Silvers whereby Levin agreed to make certain changes in the Silvers’ house at 7246 Coles avenue for $4,385; and that on May 6, 1922 the plaintiff entered into a subcontract, in writing, with Levin to do certain parts of the stucco, lath and plaster, carpentry and cement work, for $763.75, upon the premises in question; and that the plaintiff, on the latter date, entered into another subcontract with the defendant Levin to do certain similar work in the south sun parlor of the same premises for an additional $72. It was admitted, also, that the Silvers, before the work began, paid to Levin $1,000; and that Levin still owed the plaintiff $435.

It is the theory of the Silvers (1) that the work was completed on July 26, 1922, and as the plaintiff did not serve a notice for mechanic’s lien until October 24, 1922, it being more than sixty days (the statutory period) from the time of the completion of the work, the plaintiff was not entitled to recover; and (2) that as suit was not begun by the plaintiff until December 21, 1922, nearly four months (the statutory period) from the date of the completion of the work, the plaintiff cannot recover.

On the other hand, it is the theory of the plaintiff that the work was completed on August 30, 1922, and that, therefore, the notice for mechanic’s lien of October 24, 1922, was within sixty days from the time of the completion of the work, and as this suit was begun on December 21,1922, it was within the statutory period of four months.

This being a suit in the municipal court by a subcontractor against the original contractor and owner, it is evidently brought under section 28 of the Mechanics’ Liens Act [Cahill’s St. ch. 82, ][ 28]. As held in Voightmann & Co. v. Cross-Conklin Co., 183 Ill. App. 312, the only action on a subcontractor’s claim for a mechanics’ hen of which the municipal court of Chicago has jurisdiction is an action at law in assumpsit jointly against the owner and contraetor under section 28 of that Act. It is provided in section 28 that a subcontractor may file his petition and enforce his hen as provided for in the Mechanics’ Liens Act, but, also, that “he may sue the owner and contractor jointly for the amount due him in any court having jurisdiction of the amount claimed to be due, and a personal judgment may be rendered therein, as in other cases.” That section further provides that, “such action at law shall be maintained against the owner only in case the plaintiff establishes his right to the hen.” It further provides that, “all suits and actions by subcontractors shall be against both contractor and owner jointly. * * * Such judgments, where the hen is estabhshed shall be against both jointly, * * * but this shall not preclude a judgment against a contractor, personally, where the hen is defeated.”

It, therefore, becomes important in the instant case, to determine at what time the work of the plaintiff was completed, whether by July 26 or not until August 30. As the Mechanics’ Liens Act provides that the subcontractor shall within sixty days after completing his work serve notice of his claim upon the owner, and shall within four months after the completion of the work institute suit, if the evidence proves that the work was finished by July 26, then it follows that the plaintiff was not entitled to a judgment against the owner under section 28, and will only be entitled to a judgment against the contractor Levin.

It is the testimony of Levin that after work was begun the contract was entirely changed, and that certain rooms were built larger than were provided for in the contract; that certain doors, bedrooms', closets and shelves, and certain electrical work, were all changed from what was provided for in the original contract, and that a large amount of extra work was done.

In the course of the work, apparently, when it was nearly all completed, on July 10, 1922, Levin, as contractor, gave to the defendants, Silvers, a contractor’s statement, which was subscribed and sworn to before a notary public, to the effect that he, Levin, was the general contractor for all the remodeling work on the building in question; and “that all materials used and labor employed for said work are paid for in full.” That document recited further that it was “made for the purpose of inducing Geo. and Tillie Silver to make a payment on account of above mentioned building.” It then recites that the contract price was $4,385; that there were no extras; that he had been paid $4,150, and that there was a balance due him, Levin, of $235. Also, on the same date, Levin gave the Silvers a written waiver of lien “for all labor and materials for remodeling on building known as 7246 Coles avenue, George and Tillie Silver owners.”

Free access — add to your briefcase to read the full text and ask questions with AI

Erickson v. Levin, 236 Ill. App. 245, 1925 Ill. App. LEXIS 100 (Ill. Ct. App. 1925).

236 Ill. App. 245 (Erickson v. Levin) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Voightmann & Co. v. Cross-Conklin Co.
183 Ill. App. 312 (Appellate Court of Illinois, 1913)