Equity Inns Partnership v. Yun, Unpublished Decision (10-28-1999)

CourtOhio Court of Appeals
DecidedOctober 28, 1999
DocketNo. 74160.
StatusUnpublished

This text of Equity Inns Partnership v. Yun, Unpublished Decision (10-28-1999) (Equity Inns Partnership v. Yun, Unpublished Decision (10-28-1999)) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Equity Inns Partnership v. Yun, Unpublished Decision (10-28-1999), (Ohio Ct. App. 1999).

Opinion

Defendant-appellant Dae Kee Yun (hereafter "defendant") appeals from an order that quieted title to certain real property in favor of plaintiff-appellee Equity Inns Partnership, L.P. (hereafter "plaintiff"). Ruling on the parties' cross motions for summary judgment, the court entered a final judgment in favor of plaintiff on its complaint to quiet title and on defendant's amended counterclaim for breach of contract and specific performance. Defendant asserts that summary judgment was inappropriate because there existed genuine issues of material fact as to whether defendant had an interest in the property and whether plaintiff frustrated the defendant's performance. We conclude that the trial court was correct in granting summary judgment in plaintiff's favor. Accordingly, we affirm.

This controversy arises from an agreement that initially did not involve either of the parties. On December 28, 1988, Westlake Associates, as Lessor, entered into a Ground Lease with Thomas J. Unik, Trustee, and R.G.I. Investments, as Lessees, for certain real property located on Detroit Road in Westlake, Ohio.1 Section 2.01 of the lease established the lease's term at ninety-nine years commencing on December 15, 1988.2 Under Section 2.03, the lessee was required to pay $150,000 by November 1, 1989, as advance rent for the entire initial term of the lease.3

Section 11.02 of the lease authorized the lessor to terminate the lessee's right of possession if any event creating default occurred. The lessee's "abandonment" of the leased land and improvements would constitute a default under Section 11.01(d), which provided:

Lessee's abandonment of the leased land and improvements shall constitute a default under this lease. For the purposes of this Lease, "abandonment" shall be defined as Lessee's failure to begin construction of Improvements within five years following the date of this Lease.

It is undisputed that this section required construction of improvements to begin by December 28, 1993.4

On November 1, 1989, lessees Unik and R.G.I. Investments, with the consent of the lessor, assigned all of their right, title, and interest in the lease to defendant. Defendant agreed that the assignment contained all the covenants and agreements contained in the lease and that he would become the sole lessee. Defendant accordingly paid advance rent in the sum of $150,000.

Buildings, structures, or other improvements could not be constructed on the property without first obtaining a building permit from the City of Westlake. There were three stages to obtain a building permit: an applicant had to submit an application for a development plan; the city planning commission had to recommend either approving or disapproving the proposed development plan to the city council; and the city council had to approve the proposed development plan.

By approximately July 1993, defendant retained architect Victor Probst to prepare plans and blueprints for the construction of the proposed restaurant. On August 12, 1993, Probst submitted an incomplete application requesting the Westlake Planning Commission's approval for the proposed restaurant and a set of proposed blueprints. Probst submitted a complete application on September 23, 1993, and Westlake began processing the application that day upon the payment of the $500 review fee. On January 12, 1994, defendant submitted revised drawings and blueprints. Defendant submitted further revised drawings and blueprints on March 23, 1994. He submitted a survey for the proposed restaurant on March 28, 1994. On April 11, 1994, defendant submitted five revised drawings and blueprints to the Westlake planning director.

Apparently unbeknownst to defendant, original lessor Westlake Associates conveyed all of its right, title, and interest in the subject real property to plaintiff Equity Inns on or about March 1, 1994. On April 15, 1994, plaintiff's chairman and chief executive officer, Phillip H. McNeill, Sr., wrote to the Westlake planning commission's planning director to advise him of plaintiff's acquisition of the property and that plaintiff had not had any contact with the defendant on matters pertaining to the defendant's proposed improvements. McNeill's April 15, 1994 correspondence said in closing: "In summary, until such time as we have such discussions with the Lessee and all of the various legal and business requirements set forth in the lease are complied with; [sic] we request you withhold any approval of their application."

Upon learning of plaintiff's acquisition, architect Probst sent McNeill on April 18, 1994 the five revised drawings which had been submitted to the Westlake planning director on April 11, 1994. Probst later averred that he requested plaintiff's review and approval of the drawings but that Probst never received any response from plaintiff. For his part, McNeill testified in deposition that he noted his concerns on the April 11, 1994 plans and sent them to either Probst or the defendant, but McNeill did not retain a copy of his response.

By April 21, 1994, the Westlake Planning Department had identified five remaining issues that prevented the planning commission from approving defendant's April 11, 1994 drawings. Defendant and/or his counsel then began a series of correspondences to plaintiff that sought plaintiff's cooperation in order to resolve the planning department's outstanding concerns. Defendant claims that other than an April 29, 1994 correspondence in which McNeill agreed to meet with the defendant and his counsel in Memphis, Tennessee, McNeill did not respond to the defendant's follow-up inquiries dated May 5, 1994; May 6, 1994; May 27, 1994; or June 3, 1994.

On June 22, 1994, plaintiff, by and through McNeill, gave notice to the defendant that defendant was in default under Section 11.01(d) of the lease by having failed to begin construction of improvements within five years of December 28, 1988, that is, by December 28, 1993. Plaintiff thereby gave notice that the defendant's right, title, and interest as lessee was terminated and that it was required to quit and surrender the property. On October 12, 1994, defendant notified plaintiff that he intended to exercise the option to convert the lease to a purchase under Section 2.04 of the lease.

Plaintiff then filed this action on October 21, 1994 to quiet title, and defendant asserted a counterclaim against plaintiff for breach of contract and specific performance. The matter proceeded on cross-motions for summary judgment. Granting plaintiff's motion and denying defendant's motion, the trial court quieted title to the property in favor of the plaintiff as the complaint requested and entered judgment in plaintiff's favor on the defendant's counterclaim.

Defendant's appeal presents four assignments of error:

I. THE TRIAL COURT ERRED IN GRANTING APPELLEE'S (EQUITY INNS') MOTION FOR SUMMARY JUDGMENT ON APPELLEE'S ACTION TO QUIET TITLE.

II. THE TRIAL COURT ERRED IN GRANTING APPELLEE'S MOTION FOR SUMMARY JUDGMENT ON APPELLANT'S COUNTERCLAIM FOR BREACH OF CONTRACT.

III. THE TRIAL COURT ERRED IN GRANTING APPELLEE'S MOTION FOR SUMMARY JUDGMENT ON APPELLANT'S COUNTERCLAIM FOR SPECIFIC PERFORMANCE.

IV. THE TRIAL COURT ERRED IN GRANTING APPELLEE'S MOTION FOR SUMMARY JUDGMENT ON APPELLANT'S COUNTERCLAIM FOR RETURN OF RENTS PAID UNDER THE LEASE.

Defendant's brief does not separately argue these assignments of error but instead advances each as sub-arguments to his essential contention that the court erred in awarding summary judgment to the plaintiff.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Valentine v. Clippinger
212 N.E.2d 424 (Ohio Court of Appeals, 1965)
Software Clearing House, Inc. v. Intrak, Inc.
583 N.E.2d 1056 (Ohio Court of Appeals, 1990)
Fairbanks v. Power Oil Co.
77 N.E.2d 499 (Ohio Court of Appeals, 1945)
Gusman v. Mathews
163 N.E. 636 (Ohio Court of Appeals, 1928)
Renner v. Derin Acquisition Corp.
676 N.E.2d 151 (Ohio Court of Appeals, 1996)
Gorsuch Homes, Inc. v. Wooten
597 N.E.2d 554 (Ohio Court of Appeals, 1992)
Kersh v. Montgomery Developmental Center
519 N.E.2d 665 (Ohio Court of Appeals, 1987)
Southern Hotel Co. v. Miscott, Inc.
337 N.E.2d 660 (Ohio Court of Appeals, 1975)
Layne v. Baker
91 N.E.2d 539 (Ohio Court of Appeals, 1949)
Boehl v. Maidens
139 N.E.2d 645 (Ohio Court of Appeals, 1956)
Quill v. R.A. Investment Corp.
707 N.E.2d 35 (Ohio Court of Appeals, 1997)
Dynes Corp. v. Seikel, Koly & Co.
654 N.E.2d 991 (Ohio Court of Appeals, 1994)
Duramax, Inc. v. Geauga County Board of Commissioners
667 N.E.2d 420 (Ohio Court of Appeals, 1995)
Kallins v. Rex, Inc.
125 N.E.2d 371 (Ohio Court of Appeals, 1955)
North Coast Cable Ltd. Partnership v. Hanneman
648 N.E.2d 875 (Ohio Court of Appeals, 1994)
Welfare Federation v. Glander
64 N.E.2d 813 (Ohio Supreme Court, 1945)
Ralston Steel Car Co. v. Ralston
147 N.E. 513 (Ohio Supreme Court, 1925)
Temple v. Wean United, Inc.
364 N.E.2d 267 (Ohio Supreme Court, 1977)
Joseph J. Freed & Associates, Inc. v. Cassinelli Apparel Corp.
491 N.E.2d 1109 (Ohio Supreme Court, 1986)
Mitseff v. Wheeler
526 N.E.2d 798 (Ohio Supreme Court, 1988)

Cite This Page — Counsel Stack

Bluebook (online)
Equity Inns Partnership v. Yun, Unpublished Decision (10-28-1999), Counsel Stack Legal Research, https://law.counselstack.com/opinion/equity-inns-partnership-v-yun-unpublished-decision-10-28-1999-ohioctapp-1999.