Equistar Chemicals, L.P. v. Indeck Power Equipment Company

CourtDistrict Court, S.D. Texas
DecidedMarch 24, 2021
Docket4:19-cv-03757
StatusUnknown

This text of Equistar Chemicals, L.P. v. Indeck Power Equipment Company (Equistar Chemicals, L.P. v. Indeck Power Equipment Company) is published on Counsel Stack Legal Research, covering District Court, S.D. Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Equistar Chemicals, L.P. v. Indeck Power Equipment Company, (S.D. Tex. 2021).

Opinion

IN THE UNITED STATES DISTRICT COURT March 24, 2021 FOR THE SOUTHERN DISTRICT OF TEXAS Nathan Ochsner, Clerk HOUSTON DIVISION

EQUISTAR CHEMICALS, L.P., § § Plaintiff, § § v. § CIVIL ACTION NO. H-19-3757 § INDECK POWER EQUIPMENT CO., § § Defendant. §

MEMORANDUM AND ORDER ENTERING FINDINGS OF FACT AND CONCLUSIONS OF LAW

This case arises from a contract and warranties for two industrial steam boilers. Equistar Chemicals, L.P. contracted with Indeck Power Equipment Company to obtain the steam boilers, related instrumentation and equipment, and technician services for installation and start-up at Equistar’s Illinois plant. Equistar and Indeck planned on 36 days for Indeck’s service technician to do the necessary work. Instead, it took two Indeck service technicians working for a total of 186 days to identify, then help correct, defects in the boilers. That work increased Equistar’s costs and nearly caused its plant to shut down. In 2019, Equistar sued Indeck, asserting claims for breach of warranty, breach of contract, and negligence, based on alleged equipment-design and manufacturing defects and negligent service-technician work. Equistar seeks its out-of-pocket damages, not lost profits or other consequential losses, and attorneys’ fees. In February and March 2021, the court conducted a six-day bench trial by Zoom.1 The court’s detailed findings and conclusions are set out below. In summary, based on the pleadings,

1 The court finds that the technology allowed a clear, efficient, and thorough presentation of the witnesses and the relevant evidence, and that the remote presentation of the proceedings did not infringe on any rights of either party or cause any prejudice. briefs, exhibits, testimony, arguments of counsel, and applicable law, the court finds and concludes as follows:  Indeck is liable for breach of warranty for supplying Equistar with a defective forced- draft fan, fuel-gas skid, and two water bridles, resulting in $313,861 in damages to Equistar;

 Indeck is not liable for breach of warranty for supplying Equistar with boilers that vibrated excessively, because Equistar did not provide timely written notice to Indeck under the Master Contract;

 Indeck is not liable for professional negligence for designing boilers that vibrated excessively, because Equistar’s negligence claim is precluded by the economic-loss rule;

 Indeck is liable for breach of contract for providing Equistar with inefficient start-up services, because one Indeck service technician’s work had to be substantially redone and two service technicians had to spend substantial time fixing problems that should not have arisen or should have been fixed before the equipment was delivered to Equistar, resulting in $286,998 in damages to Equistar;

 Indeck is liable for breach of contract for providing Equistar with inefficient transportation services, because Indeck delayed releasing customs paperwork for the boiler shipment across the Canadian border, which delayed shipment and added a month to Equistar’s railcar rental charges, resulting in $44,000 in damages to Equistar; and

 Indeck is liable for Equistar’s reasonable attorneys’ fees under Chapter 38 of the Texas Civil Practice and Remedies Code.

Based on the record evidence, the total damage award in favor of Equistar is $644,859. Equistar must submit a proposed final judgment, consistent with the court’s findings and conclusions, no later than April 1, 2021. It may submit its attorneys’ fee application in accordance with Rule 54 of the Federal Rules of Civil Procedure. The detailed findings of fact and conclusions of law are set out below. I. Introduction and Background A. The Issues Equistar owns and operates facilities used in producing chemicals, plastics, and other products. Indeck manufactures and sells industrial steam boilers. In 2015, Equistar and Indeck entered into a contract for Indeck to provide two steam boilers, related equipment, and services to

Equistar’s plant in Tuscola, Illinois. Indeck supplied the two steam boilers and the related equipment to Equistar and supplied service technicians who oversaw the installation and start-up. Indeck estimated that its service technician would get the boilers fully operating with 36 days of work after delivery. Instead, it took two technicians who worked on the boilers for a total of 186 nonconsecutive days. The causes and costs of that extended worktime are one basis of this lawsuit. In September 2019, Equistar sued Indeck for breach of contract, breach of warranty, and professional negligence.2 Equistar seeks reimbursement of $795,298 that it paid as a result of alleged defects in the boiler design or manufacture and inefficiencies in Indeck’s installation and start-up services. This represents out-of-pocket invoiced amounts that Equistar paid, not lost

profits or other consequential damages. In February and March 2021, the court held a six-day bench trial by Zoom. The parties presented and cross-examined witnesses, submitted many exhibits, and presented arguments on the following issues:  whether Indeck materially breached its contractual warranties by providing Equistar with defective materials;

 whether Indeck materially breached the parties’ Master Contract by providing inefficient services to Equistar and charging for excessive rework and for unreasonable railcar rental fees; and

2 In its original answer, Indeck asserted a counterclaim for a declaratory judgment. (Docket Entry No. 4 at ¶¶ 49–52). Indeck agreed to dismiss that counterclaim at the parties’ initial conference. (Docket Entry Nos. 15, 16).  whether Indeck was professionally negligent in its design and manufacture of the boilers.

Both sides were thorough and professional in their presentations. Without that, this case would have been more difficult and complex. The court appreciates the work of counsel for both sides. B. The Witnesses and Evidence

Equistar presented the following witnesses:  Michael Holt, an Equistar engineer;  Maureen Radi, an Equistar engineer;  Greg Wassilkowsky, Indeck’s director of engineering;  Perry Danniger Smith, project manager for Equistar’s boiler project; and  Richard A. Gehse, a licensed professional engineer designated as an expert witness.

Indeck presented the following witnesses:  David Pruyn, Indeck’s instrumentation and controls manager;  Bob Swanton, an Indeck service technician;  Ray Henry, a licensed professional engineer designated as an expert witness; and  Marsha Forsythe, Indeck’s president and chief executive officer.

Equistar submitted 37 exhibits, (Docket Entry No. 35), and Indeck submitted 119 exhibits, (Docket Entry No. 36). Those exhibits include documents relating to: Equistar’s Tuscola plant; the parties’ agreements and communications; the parties’ records and invoices; and the boiler schematics, testing, operation, and repairs. C. The Master Contract The parties’ disputes arise from Articles 2(a), 8(b), 13(a)(iii)(A), (B), 13(a)(v), 13(w)(i), 16, and 24 of the Master Contract. Article 2(a) reads: 2. Acceptance & Scope of Supply. a. Contract Documents. This Contract is expressly limited to the terms and conditions stated herein. This Contract shall consist of the Contract Documents issued under and incorporating the terms and conditions of this Contract.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Nichols v. Enterasys Networks, Inc.
495 F.3d 185 (Fifth Circuit, 2007)
Nabors Drilling, U.S.A., Inc. v. Escoto
288 S.W.3d 401 (Texas Supreme Court, 2009)
Parkway Co. v. Woodruff
857 S.W.2d 903 (Court of Appeals of Texas, 1993)
Great American Products v. Permabond International
94 S.W.3d 675 (Court of Appeals of Texas, 2003)
Solar Applications Engineering, Inc. v. T.A. Operating Corp.
327 S.W.3d 104 (Texas Supreme Court, 2010)
Sterling Chemicals, Inc. v. Texaco Inc.
259 S.W.3d 793 (Court of Appeals of Texas, 2007)
Pugh v. General Terrazzo Supplies, Inc.
243 S.W.3d 84 (Court of Appeals of Texas, 2007)
Associated Indemnity Corp. v. CAT Contracting, Inc.
964 S.W.2d 276 (Texas Supreme Court, 1998)
Southwestern Bell Telephone Co. v. DeLanney
809 S.W.2d 493 (Texas Supreme Court, 1991)
Parkway Co. v. Woodruff
901 S.W.2d 434 (Texas Supreme Court, 1995)
Conn Credit I, L.P. v. TF Loanco III, L.L.C.
903 F.3d 493 (Fifth Circuit, 2018)
Richard Frederking v. Cincinnati Insurance Company
929 F.3d 195 (Fifth Circuit, 2019)
Lamar Homes, Inc. v. Mid-Continent Casualty Co.
242 S.W.3d 1 (Texas Supreme Court, 2007)
Minsa Corp. v. SFTC, LLC
540 S.W.3d 155 (Court of Appeals of Texas, 2017)

Cite This Page — Counsel Stack

Bluebook (online)
Equistar Chemicals, L.P. v. Indeck Power Equipment Company, Counsel Stack Legal Research, https://law.counselstack.com/opinion/equistar-chemicals-lp-v-indeck-power-equipment-company-txsd-2021.