Environmental Defense Fund, Inc. v. Hoffmann

421 F. Supp. 1083, 9 ERC 1706, 7 Envtl. L. Rep. (Envtl. Law Inst.) 20152, 9 ERC (BNA) 1706, 1976 U.S. Dist. LEXIS 15992
CourtDistrict Court, E.D. Arkansas
DecidedMarch 22, 1976
DocketLR-71-C-199
StatusPublished
Cited by1 cases

This text of 421 F. Supp. 1083 (Environmental Defense Fund, Inc. v. Hoffmann) is published on Counsel Stack Legal Research, covering District Court, E.D. Arkansas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Environmental Defense Fund, Inc. v. Hoffmann, 421 F. Supp. 1083, 9 ERC 1706, 7 Envtl. L. Rep. (Envtl. Law Inst.) 20152, 9 ERC (BNA) 1706, 1976 U.S. Dist. LEXIS 15992 (E.D. Ark. 1976).

Opinion

MEMORANDUM OPINION

OREN HARRIS, Senior District Judge.

This controversial action has been the subject of consideration for some time. The Cache River — Bayou DeView Channelization Project has been a matter of public interest and discussion since prior to the enactment of the Flood Control Act of 1950. By the Flood Control Act of 1950, Congress authorized construction of the project. Planning funds were regularly appropriated from 1963 to 1971. In July, 1969, a general design for the project was completed. 1

In 1971, specific plans were completed for the first phase of the project. In July of that year, a contract was let to clear and excavate 6.7 miles of the lower Cache River to relieve backwater flooding. Two million dollars for this phase of construction was appropriated for fiscal 1972 and 1973. 2

On December 7, 1970, the Corps of Engineers filed a final environmental impact statement (EIS) as required by the National Environmental Policy Act of 1969 (NEPA).

On September 24, 1971, a draft environmental statement was filed by the Corps which discussed a “mitigation plan” to purchase thirty thousand acres of land in the basin to mitigate the wildlife losses.

On October 6,1971, the plaintiffs filed an action seeking to halt construction of the project. Construction was voluntarily postponed by the Corps to permit the trial court to consider the matter.

On May 12, 1972, the trial court filed a final judgment in favor of the defendants. 3

The plaintiffs appealed from the decision of the District Court. In its opinion, filed December 14, 1972, 4 the Eighth Circuit Court of Appeals held that the original impact statement, filed by the Corps of Engineers, was inadequate in that it failed to comply with the National Environmental Policy Act of 1969 (NEPA). The Circuit Court also found that the EIS failed to meet the guidelines adopted by the Council on Environmental Quality (CEQ) or the Corps itself.

The Circuit Court of Appeals, supra, further held that District Courts have an obligation to review substantive agency decisions on the merits to determine if they are in accord with NEPA although the ultimate standard of review is a narrow one. 5

The appellate court remanded the case to the District Court with the following instructions:

“(1) to require the Corps to submit a revised impact statement in accordance with the decision of Judge Eisele in the Cossatot case and in accordance with the current guidelines of CEQ and the Corps itself;
(2) to retain jurisdiction of the matter to rule on the sufficiency of the new envi *1085 ronmental impact statement if a prompt request for such review is made;
(3) to review the agency decision in light of the arbitrary and capricious test if a prompt request for such review is made; and
(4) to grant such injunctive relief as the court may feel is appropriate.”

Pursuant to remand, the Court scheduled a hearing and, subsequently, issued an order, on March 16, 1973, to implement the instructions of the Court of Appeals. In its order, the Court enjoined and restrained the Federal defendants from any further construction work of any kind related to or in connection with the Cache River — Bayou DeView Channelization Project. Certain cleanup work was allowed in terminating the existing contract. Defendants were specifically permitted to continue with planning in connection with the project short of actual construction. Defendants were to proceed with compiling a new environmental impact statement in accordance with the opinion of the Court of Appeals. The Court included in its order that the injunction continue until the defendants filed with the Council on Environmental Quality and with the Court a new final environmental statement as directed in the opinion of the Eighth Circuit Court of Appeals. The injunction is to remain in force until it is determined that the new final environmental statement is in accordance with the law, and that the defendants are otherwise in compliance with the National Environmental Policy Act, 42 U.S.C. §§ 4332-47.

On November 8, 1974, the defendants filed a new revised final environmental impact statement with the Council on Environmental Quality, and on December 17, 1974, defendants filed a motion to dissolve injunction and dismiss complaint. The plaintiffs filed a response to the motion on January 29, 1975. On February 28, 1975, defendants filed a motion for summary judgment. The Court, Henley, C. J., denied the pending motions on March 6, 1975, and directed the parties to proceed with discovery with a view of a hearing on the new EIS. After the plaintiffs responded to interrogatories submitted by the defendants, the defendants, on July 11, 1975, filed a renewed motion for summary judgment.

Subsequently, the case was reassigned by the Honorable G. Thomas Eisele, C. J., to this Court, Harris, J. 6

The Court scheduled a pre-trial hearing for August 12, 1975. The parties were directed to each file a “statement of issues.” 7

The Court scheduled a final hearing on the new EIS, filed by the Corps of Engineers, which commenced November 17 and continued through November 20,1975. The Court took the matter under advisement and, by request, the parties were permitted to submit briefs as to their respective contention on the revised EIS submitted by the Corps.

In the meantime, the Arkansas Game and Fish Commission and the Cache River— Bayou DeView Improvement District and landowners have been permitted to intervene. The Court has had the benefit of excellent briefs filed by plaintiffs, Federal defendants and intervenors. In addition, the Special Assistant Attorney General, William G. Peterson, has been permitted to file amicus curiae brief on behalf of the State of Minnesota. 8

*1086 As pointed out in the opinion of the Circuit Court of Appeals, Environmental Defense Fund, Inc. v. Froehlke, supra:

“Section 102(C) of NEPA requires the Corps to ‘[ijnclude in every recommendation or report on proposals for legislation and other major Federal actions significantly affecting the human environment, a detailed statement’ which discusses the impact of the action on the environment.” p. 348

It must be in such detail as to meet the standards of the Act and sufficient to form a basis for responsible evaluation and criticism.

Section 102(C)(iii) of NEPA specifically requires that the impact study discuss “[ajlternatives to the proposed action.” 9

Free access — add to your briefcase to read the full text and ask questions with AI

Related

National Audubon Society v. Andrus
442 F. Supp. 42 (District of Columbia, 1977)

Cite This Page — Counsel Stack

Bluebook (online)
421 F. Supp. 1083, 9 ERC 1706, 7 Envtl. L. Rep. (Envtl. Law Inst.) 20152, 9 ERC (BNA) 1706, 1976 U.S. Dist. LEXIS 15992, Counsel Stack Legal Research, https://law.counselstack.com/opinion/environmental-defense-fund-inc-v-hoffmann-ared-1976.