Entron, Inc. v. Callais Cablevision, Inc.

307 So. 2d 787, 1975 La. App. LEXIS 3780
CourtLouisiana Court of Appeal
DecidedFebruary 10, 1975
Docket10111
StatusPublished
Cited by5 cases

This text of 307 So. 2d 787 (Entron, Inc. v. Callais Cablevision, Inc.) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Entron, Inc. v. Callais Cablevision, Inc., 307 So. 2d 787, 1975 La. App. LEXIS 3780 (La. Ct. App. 1975).

Opinion

307 So.2d 787 (1975)

ENTRON, INC.
v.
CALLAIS CABLEVISION, INC.

No. 10111.

Court of Appeal of Louisiana, First Circuit.

February 10, 1975.

*788 Stanley L. Perry, Galliano, for appellant.

Jerry Brown, Monroe & Lemann, New Orleans, for appellee.

*789 Before LANDRY, BLANCHE and NEHRBASS, JJ.

LANDRY, Judge.

Defendant (Callais) appeals from judgment awarding plaintiff (Entron) the sum of $18,653.55, comprising the balances due on two contracts for construction of a cable television system and an open account for the purchase of materials and supplies ordered by Callais to supplement and augment the system. Callais reconvened denying that any balances were due and asserting a claim for allegedly defective materials furnished by Entron in fulfillment of the construction contracts. Entron has answered the appeal praying that its judgment be increased to $26,848.71. We amend the judgment to allow certain portions of Callais' reconventional demand. We reject certain portions of Entron's claims and render judgment in favor of Entron in the sum of $18,389.02.

Callais urges that the trial court erred in the following respects: (1) Allowing Entron any recovery whatsoever despite Entron's failure to establish sale and delivery of the items composing Entron's claim as required by law, namely, failure to produce signed receipts or delivery tickets; (2) Permitting Entron recovery on open account for merchandise included within the construction contracts, thus resulting in a double charge to Callais; (3) Granting open account claims for warranted merchandise replaceable at Entron's expense; (4) Permitting claims for merchandise either rejected by Callais or returned for credit, and (5) Failing to grant Callais credit for payments on account.

In answering the appeal, Entron contends the trial court erred in rejecting certain allegedly established claims. Entron concedes some minor credits are due Callais but urges that allowing for such credits, Entron is entitled to judgment in the sum of $26,848.71. Procedurally, Entron urges that the trial court erred in declining to declare its request for admissions and answers admitted by virtue of Callais' failure to timely answer said request as provided for by LSA-C.C.P. Article 1496.

Entron manufactures and supplies components and services used in the construction, operation and maintenance of cable television systems. Entron also designs and constructs cable television systems to specification for persons or firms who desire to furnish this type of service in any given locality. On August 29, 1968, pursuant to its designated Contract #1281, Entron contracted to construct a community cable television system for Callais in and around Golden Meadow, Louisiana, consisting of a 600 foot receiving tower, approximately ten aerial strand miles of cable and related amplification equipment. The contract stipulated a basic price of $76,688.00, including two options exercised by Callais when the agreement was confected. A third option provided for an additional maximum cost of $5,000.00 should it be determined that piling was required to support the tower. This option was accepted and approved by Callais in writing on or about January 22, 1969. Pursuant to Contract #1281, approximately 15 miles of cable were constructed. Seven contract deviations were suggested by Callais, and no amount is claimed therefor by Entron. Deviations 2, 3, 4 and 5 were duly approved by Callais, and the cost thereof added to the contract price by Entron. Deviation 6 is mentioned in a letter from Entron to Callais dated March 25, 1969. The nature of the deviation proposed is not shown nor was it accepted by Callais in writing as required by the contract. By deviation 7, Entron sought Callais' approval of additional tower construction expense in the sum of $3,350.00 resulting from the use of piling. This item was rejected by Callais based on the contract limitation of $5,000.00 in the event piling were required. Entron concedes that this $3,350.00 is not owed by defendant.

Callais made an initial deposit of $30,000.00 on Contract 1281. On January *790 20, 1969, Entron billed Callais for $48,466.00, which included the cost of approved option number 3 and deviations 2, 3, 4 and 5. On May 7, 1969, Callais was billed for $31,905.00, allegedly a final billing, by an invoice which recited that details were attached. The details alluded to were not made part of the record by either party. The record discloses a total billing by Entron to Callais on Contract 1281 of $110,371.00 as of May 10, 1969. However, when the basic contract price is added to the approved option and deviations, a total of $105,900.05 is indicated. Entron's failure to attach details to its May 7, 1969 final invoice for $31,905.00 makes it impossible to directly compute the amount due on Contract 1281 because Entron's accounting system did not include entry of Callais' $30,000.00 down payment on Entron's general ledger, and the only proof of the total billing consists of Entron's recapitulation hereinafter mentioned.

On September 23, 1969, Entron and Callais confected Contract 1330 which provided for the installation of up to 65 additional miles of cable as an extension of the original project. Under this agreement, 24.96 aerial strand miles of cables were installed for the unit price of $3,450.00 per mile, or a total price of $86,112.00. Pursuant to addendum #1, Entron installed anchors, anchor down guys, strand cables and other equipment costing $14,953.77. By mutual agreement, deviations 1 and 4 added $337.00 to Contract 1330 for additional wire cables and mounting brackets, respectively. One-half of freight costs amounting to $814.26 was charged to Callais as was also the sum of $426.60 for framing 237 poles. The total charges for this project, therefore, amounted to $102,643.63. Callais made a down payment of $10,350.00. By invoice #71770, dated December 15, 1969, Callais was billed for $31,050.00. On April 22, 1970, Entron rendered invoice #72326 in the sum of $42,283.63, which set out in detail all prior contract billings including addenda, deviations, all other charges, and which included all payments made by Callais. This invoice was intended by Entron to be a final billing for Contract 1330. Subsequently, however, Entron discovered that a payment of $20,000.00 made by Callais was, on March 20, 1969, erroneously credited both to Contract 1330 and to Callais' open account, which accounting error resulted in Callais being given a $40,000.00 credit for a $20,000.00 payment. The mistake was called to Callais' attention, and invoice #72326A, dated September 15, 1970, was sent to Callais to correct the error, showing a balance due of $18,950.00 on Contract 1330. Although Callais denied owing any balance on any account whatsoever, Callais concedes that it was erroneously given a $20,000.00 credit on Contract 1330, and that the $20,000.00 payment was ultimately credited to Callais on Contract 1330.

In December, 1968, while construction on Contract 1281 was still in progress, Callais began ordering various materials and supplies from Entron on open account. The numerous items involved were required to service Callais' subscribers and expand Callais' operation inasmuch as the demand for service exceeded Callais' expectations. The accounting details regarding this account are reflected in Entron's Exhibit 8, which is the general ledger of Callais' accounts kept by Entron as part of its normal business records. Postings on this general ledger are exact duplicates (carbon copies) of the statements rendered Callais from December, 1968, through and including April, 1970.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Phelps Dunbar, LLP v. Stout
914 So. 2d 44 (Louisiana Court of Appeal, 2005)
Vardaman v. Baker Center, Inc.
711 So. 2d 727 (Louisiana Court of Appeal, 1998)
Helena Chemical Co. v. Nichols
695 So. 2d 990 (Louisiana Court of Appeal, 1996)
DH Holmes Co., Ltd. v. Dronet
432 So. 2d 1135 (Louisiana Court of Appeal, 1983)
Cardinal Wholesale Supply, Inc. v. Rainbow Floor Covering
432 So. 2d 419 (Louisiana Court of Appeal, 1983)

Cite This Page — Counsel Stack

Bluebook (online)
307 So. 2d 787, 1975 La. App. LEXIS 3780, Counsel Stack Legal Research, https://law.counselstack.com/opinion/entron-inc-v-callais-cablevision-inc-lactapp-1975.