ENTERGY ARKANSAS, INC., AND ENTERGY OPERATIONS, INC. v. SUSAN ALLEN, INDIVIDUALLY AND AS ADMINISTRATRIX of the ESTATE OF WADE WALTERS

2021 Ark. App. 71
Court of Appeals of Arkansas·Decided February 17, 2021·Published·Cited by 3 cases

Opinion

Cite as 2021 Ark. App. 71 Elizabeth Perry I attest to the accuracy and ARKANSAS COURT OF APPEALS integrity of this document DIVISION I 2023.06.22 13:20:35 -05'00' No. CV-19-68 2023.001.20174 ENTERGY ARKANSAS, INC., AND Opinion Delivered: February 17, 2021 ENTERGY OPERATIONS, INC.

APPELLANTS APPEAL FROM THE POPE COUNTY CIRCUIT COURT

V. [NO. 58CV-13-166]

SUSAN ALLEN, INDIVIDUALLY AND AS ADMINISTRATRIX OF THE HONORABLE DENNIS CHARLES ESTATE OF WADE WALTERS, SUTTERFIELD, JUDGE DECEASED

APPELLEE AFFIRMED

RAYMOND R. ABRAMSON, Judge This case is one of several that arose from an accident that occurred at Entergy’s Arkansas Nuclear One (“ANO”) plant in Russellville on March 31, 2013. A temporary crane failed as it lowered one of the plant’s decommissioned main turbine generator stators onto a transport vehicle that was parked one story below, in the facility’s train bay. The stator, which weighed over five hundred tons, fell approximately thirty feet. Several iron workers and carpenters were working below the crane when it failed. Eight of them were injured as fragments of the crane fell to the ground. Ronnie Francis sustained injuries as he attempted to help a man who had become trapped under one of the beams of the fallen crane. Twenty-four-year-old Wade Walters was killed.

Susan Allen, the plaintiff in the case below, is Wade Walters’s mother and the administratrix of his estate. Following the accident, Ms. Allen, Mr. Francis, and at least three

other plaintiffs filed separate lawsuits in the Pope County Circuit Court against Entergy and several contractors that were involved in the stator-lift project. One of those contractors, Bigge Power Company (“Bigge”), supplied the crane that failed.

Events that occurred in Mr. Francis’s lawsuit are significant here. In that case, Bigge propounded interrogatories to Entergy that requested reports of the root-cause evaluation that Entergy performed in the aftermath of the accident. Entergy objected, and Bigge filed a motion to compel. Entergy sought an order of protection, arguing that the work-product rule and attorney-client privilege protected the reports from disclosure. The circuit court denied an order of protection and directed Entergy to provide the reports to Bigge and to Mr. Francis, who had joined Bigge’s motion to compel.

Entergy filed an interlocutory appeal, see Entergy Ark., Inc. v. Francis, 2018 Ark. App.

250, 549 S.W.3d 362, and this court affirmed the circuit court’s order in part and reversed it in part. We held that the circuit court did not abuse its discretion by denying the order of protection and by ordering Entergy to produce the reports to Bigge. We reversed the order, however, insofar as it ordered Entergy to produce the reports to Mr. Francis. We held that Mr. Francis had not served Entergy with interrogatories or requests for production and therefore did not have standing to join Bigge’s motion to compel. Id. at 13, 549 S.W.3d at 370.

The issue in this appeal is whether the Francis decision should have any bearing on the course of discovery in Allen’s lawsuit, where Entergy again asserted that the root-cause evaluation reports were protected by attorney-client privilege and the work-product rule. The circuit court granted Allen’s motion to compel Entergy to produce the reports finding

that Francis was law of the case that precluded any further consideration of Entergy’s claims that they were privileged.

Entergy has now filed another interlocutory appeal challenging the circuit court’s order. We affirm because the circuit court did not abuse its discretion when it determined that Francis has a preclusive effect on Entergy’s renewed assertions of privilege.

I. Facts and Procedural History A. The Accident and Subsequent Internal Investigation Several of the facts that we recounted in Francis bear repeating here. In 2011, Entergy contracted with Siemens Energy, Inc. (“Siemens”), to remove and replace one of ANO’s main turbine generator stators, which, powered by steam from the plant’s nuclear reactor, generated the electricity produced at the plant. Siemens subcontracted with Bigge for temporary crane and rigging services to remove the original stator and install its replacement. The temporary crane was intended to lift the stator from its mooring on the plant’s main turbine deck, carry it several feet to the train-bay opening, and then lower the stator onto a transport vehicle that waited below.

The stator lift began at approximately 7:40 a.m. on Sunday, March 13, 2013. After the lift was underway, the workers who were supervising the lift realized that the stator would not clear a guardrail at the opening of the train bay. Several iron workers, including Mr. Francis and Mr. Walters, were called in to remove the guardrail while the stator lift was in progress. Shortly after the guardrail was removed, the temporary crane failed, and the stator, as well as pieces of the crane, fell to the main turbine deck and through the train-bay

opening. As indicated above, several of the workers standing by, including Mr. Francis, were injured in the accident. Mr. Walters was killed.

Entergy immediately began an internal investigation, or root cause-evaluation, of the accident. The root-cause evaluation was required by the Nuclear Regulatory Commission (“NRC”) and Entergy’s internal policy, and its purpose was to identify and determine the cause(s) of “conditions adverse to quality” and to document the “corrective action taken to preclude repetition.”

Entergy issued its first root-cause evaluation report on July 22, 2013. The report concluded that the root cause of the stator drop was the crane’s defective design, which did not ensure that the crane “could support the loads anticipated for the lift.” The report also found, as an additional root cause, that Bigge, which designed and furnished the crane, “failed to perform required load testing of their [crane] prior to its use at ANO in accordance with OSHA regulation.” The report further concluded, in pertinent part, that Bigge and Siemens contributed to the accident by “inaccurately represent[ing] that the [crane] had been used at other electric power stations to lift components that exceeded the anticipated weight of the . . . stator,” and Siemens failed “to provide adequate oversight and control of Bigge’s performance.”

The NRC later observed, during its own inspection of the ANO facility, that the July 2013 root-cause evaluation was not adequate. Specifically, the report “did not address Entergy’s oversight of the contractors involved with the stator lift,” and the NRC inspectors further determined that “Entergy did not ensure adequate supervisory and management oversight of the contractors and other supplemental personnel involved with the stator lift,

and this contributed to the event.” Consequently, on December 10, 2014, Entergy issued its second root-cause evaluation that identified additional root causes of the accident, including that the project “was not organized or managed in a manner that provided sufficient oversight of the vendor’s design and testing for the [crane]” and that Entergy’s internal procedures “provided insufficient guidance to identify and manage risk items with high consequence, particularly where the probability of the event was judged to be very low.” The second root-cause evaluation also found that Entergy’s “[w]eak implementation of administrative controls”; Entergy’s failure to provide “clear guidance regarding the level of review required to approve the design and testing of vendor-supplied special lift equipment”; Entergy’s “undue confidence in the vendor’s capabilities”; and the inadequacy of a prior corrective-action plan were contributing causes of the accident.

B. Entergy v. Francis

Mr. Francis filed a complaint on November 21, 2013, alleging several claims of negligence against Entergy, Siemens, Bigge, and other contractors associated with the stator- lift project.

Free access — add to your briefcase to read the full text and ask questions with AI

ENTERGY ARKANSAS, INC., AND ENTERGY OPERATIONS, INC. v. SUSAN ALLEN, INDIVIDUALLY AND AS ADMINISTRATRIX of the ESTATE OF WADE WALTERS, 2021 Ark. App. 71 (Ark. Ct. App. 2021).

2021 Ark. App. 71 (ENTERGY ARKANSAS, INC., AND ENTERGY OPERATIONS, INC. v. SUSAN ALLEN, INDIVIDUALLY AND AS ADMINISTRATRIX of the ESTATE OF WADE WALTERS) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Robinson Nursing & Rehabilittion Center, LLC v. Briley
2022 Ark. App. 85 (Court of Appeals of Arkansas, 2022)
James D. Merica v. S&S Home Improvements, Inc.
2021 Ark. App. 197 (Court of Appeals of Arkansas, 2021)