The opinion of the court was delivered by

Thiele, J.:

Plaintiff brought his action to recover damages caused by alleged negligence of the defendant in the construction of a bridge and highway improvements. In response to rulings of the trial court, certain amendments were made to the petition, and [44]*44thereafter a demurrer to the petition as amended was sustained. Plaintiff appeals from that ruling.

Omitting much of the detailed allegations, it was alleged in the amended petition that the plaintiff was the owner of certain lands in Clay county, Kansas, bordering on the east bank of the Republican river and immediately south of U. S. highway No. 24 (formerly No. 40), and that in October, 1934, plaintiff contracted with the state highway commission to convey to the state of Kansas for highway purposes a tract of about six acres bordering the public highway for a consideration of $851.49. This contract specified the price to be paid for the lands to be deeded and for removing fence, and further:

“Any and all verbal agreements are merged in this written contract and it is understood and agreed that the consideration for said real estate above stated is in full payment for the purchase of said real property and all other damages arising from the transfer of said property and its use for the purposes set out.”

The deed provided was duly executed and delivered. There were allegations with respect to the course of the river and the conditions of the surrounding country upstream from plaintiff’s land, and that on plaintiff’s land a strip about 180 feet wide next to the river was two to three feet higher than the lands to the east thereof, which strip was covered with underbrush and trees. It was also alleged that defendant Aldridge was a bridge contractor, and, under a contract with the state highway commission, erected a bridge upon a portion of the lands purchased from plaintiff, and in so doing carelessly, negligently and wrongfully removed the trees and underbrush from the bank of the river, and removed dirt in such manner as to lower the surface about four and one half feet; that plaintiff protested against removal of the trees and brush and the digging of the ditch; that defendant built a high fill or grade on the east side of the erected bridge for approaches to the highway, the fill being about six feet higher than it formerly was. It was also alleged that the plans and engineering under which the work was done were fundamentally defective in that it was unnecessary to cut the ditch or to remove the trees, and that efficient floodgates should have been installed to prevent water from coming through the ditch and damaging plaintiff’s land; that floodgates were practicable; that the work as planned and done was so obviously and patently defective in engineering and workmanship an ordinarily prudent man could and should have foreseen that damage would result to plaintiff’s [45]*45land. It was further alleged that in June, 1935, the river went out of its banks and flooded the surrounding lands; that during said time the waters collected and flowed through the ditch and depression caused by the wrongful removal of the trees, underbrush and bank, and on to plaintiff’s land, causing the cutting of holes, and the deposit of sand, to plaintiff’s damage in the sum of $4,725; that it also damaged his barn in the sum of $200, and deprived him of ingress and egress to a part of his farm, to his damage in the sum of $1,000, and that all of the damages were proximately caused by the wrongful construction of the fill constituting the bridge approach and by the removal of the trees, underbrush and dirt to form the ditch, which, coupled with the natural bottleneck caused by bluffs along the river, caused the damages which should have been foreseen.

Appellant’s principal contention is that appellee, an independent contractor, is liable to him in damages by reason of appellee’s executing plans and specifications of the state highway commission for highway improvement abutting appellant’s lands, where the plans and specifications were so fundamentally defective and such obviously poor engineering that an ordinarily prudent man could have foreseen that the execution of such plans and specifications would cause unnecessary damage to appellant’s lands; and that he cannot escape liability merely because he completed the work and turned it over to the state highway commission before the damage occurred.

Appellant concedes that the state highway commission is immune from suit under the circumstances and that he has no cause of action against it for building the bridge and approaches, but he. argues that while a large number of courts give to independent contractors the same immunity as given the state, the rule is without sound reason to support it and the contractor should be held responsible for damages that result because the improvement was made under plans and specifications alleged to be obviously unsound as a matter of engineering practice, and that such unsoundness was known to the contractor when he performed the work.

A brief review of the statutes under which this improvement was made shows that the highway commission is authorized to enter into contracts incident to the construction of the state highway system (G. S. 1935, 68-407) after giving notice and receiving bids (G. S. 1935, 68-408) based upon plans and specifications previously prepared (G. S. 1935, 68-409), the contractor to give bond condi[46]*46tioned in part that he “will faithfully perform such contract in every respect,” and also that he will pay bills for supplies, materials and labor, etc. (G. S. 1935, 68-410). It would thus appear that a contractor having undertaken an improvement was obligated by his contract and bond to perform according to the plans and specifications furnished by the state highway commission, and that he could neither change the plans nor quit the work because he believed the improvement as projected was bad from an engineering standpoint. The statutory provisions would seem to put the contractor in the same position as the state highway commission.

In connection with his argument that the contractor is responsible for carrying out an obviously unsound engineering project, appellant directs our attention to Shanks v. Pearson, 66 Kan. 168, 71 Pac. 252, and Murphy v. Fairmount Township, 89 Kan. 760, 133 Pac. 169. The Shanks case was an injunction to enjoin the road overseer from digging a deep ditch along the highway in front of plaintiff’s residence and farm, and it was there held that such officer, while acting within the scope of his authority, is vested with a very broad discretion with which the courts will not interfere except in case of fraud or where there is abuse of discretion. The real point in issue and decided was that the trial court erred in refusing testimony tending to show special injury, that the improvement was being made to subserve private and personal .ends, and further tending to show bad faith. .In the Murphy case the plaintiff sought to recover damages occasioned by an insufficient culvert, and to enjoin its maintenance. In that case there is a review of many of our decisions touching the power and discretion of highway officials in making improvements and liability therefor, and it was said:

“This court has gone only to the extent of holding that counties and townships in instances like this are not required to respond in damages for injuries already caused; not that they may be permitted to continue a nuisance or that they may not be enjoined from so doing.” (p. 765.)

Free access — add to your briefcase to read the full text and ask questions with AI

Related

State v. Hunt
476 P.3d 530 (Court of Appeals of Oregon, 2020)
Portis v. Folk Construction Co.
694 F.2d 520 (Eighth Circuit, 1982)
Portis v. Folk Construction Company, Inc.
694 F.2d 520 (Eighth Circuit, 1982)
Kristek v. Catron
644 P.2d 480 (Court of Appeals of Kansas, 1982)
Yellowstone Pipe Line Co. v. Grant Const. Co., Inc.
520 P.2d 249 (Idaho Supreme Court, 1974)
Talley v. Skelly Oil Co.
433 P.2d 425 (Supreme Court of Kansas, 1967)
Gates v. Pickett & Nelson Construction Co.
432 P.2d 780 (Idaho Supreme Court, 1967)
Meier v. Frank Mashuda Co.
168 N.E.2d 319 (Ohio Court of Appeals, 1959)
Coleman v. S. Patti Construction Co.
318 P.2d 1028 (Supreme Court of Kansas, 1957)
Russell v. Arthur Whitcomb, Inc.
121 A.2d 781 (Supreme Court of New Hampshire, 1956)
Soden v. Bennett
244 P.2d 1204 (Supreme Court of Kansas, 1952)
Tillotson v. Fair
159 P.2d 471 (Supreme Court of Kansas, 1945)
Jackson v. Kansas Gas & Electric Co.
102 P.2d 1038 (Supreme Court of Kansas, 1940)

Cite This Page — Counsel Stack

Bluebook (online)
75 P.2d 290, 147 Kan. 43, 1938 Kan. LEXIS 10, Counsel Stack Legal Research, https://law.counselstack.com/opinion/engler-v-aldridge-kan-1938.