Engineering & Construction Innovations, Inc. v. L.H. Bolduc Co.

803 N.W.2d 916, 2011 Minn. App. LEXIS 118, 2011 WL 3903277
Court of Appeals of Minnesota·Decided September 6, 2011·No. No. A11-159·Published·Cited by 3 cases

Opinions

OPINION

MUEHLBERG, Judge.*

This case comes to us on appeal from a district court’s award of summary judgment in favor of a subcontractor and an insurer on a general contractor’s breach-of-contract and declaratory-judgment actions. Because ECI’s reply brief raises an issue not raised in its principal brief, we grant the subcontractor’s motion to strike certain portions of the reply brief. Because the district court erred by concluding that the subcontractor and insurer’s obligations were limited to damage caused by the subcontractor’s negligence, we reverse and remand.

[919] FACTS

This case arises out of litigation stemming from damage to a pipeline following a construction project. Frontier Pipeline, LLC was hired by Metropolitan Counsel Environmental Services (MCES) as the prime contractor for a construction project located in White Bear Lake, White Bear Township, and Hugo (the project). Frontier subcontracted portions of the project to appellant Engineering & Construction Innovations, Inc. (ECI), including the installation of a lift station and the installation of Forcemain access structures at various locations along the route of the pipeline. ECI hired respondent L.H. Bol-duc Co. (Bolduc) to furnish, drive, and remove sheeting cofferdams required as part of ECI’s responsibilities under the project.

Pursuant to the terms of the subcontract agreement, Bolduc was required to purchase and maintain various types of insurance policies with specified liability limits during the project. Bolduc also was required to include ECI as an additional insured under its commercial general liability (CGL) policy. Respondent The Travelers Indemnity Company of Connecticut (Travelers) was the insurer on the CGL policy. The policy was effective at all times relevant to this appeal. Travelers issued an endorsement to the policy covering ECI as an additional insured.

In late 2007, Bolduc furnished and drove sheeting in connection with ECI’s construction of Forcemain Access Structure No. 1 (FAS-1). While doing this work, the sheeting struck and damaged the pipeline, which had been previously installed by Frontier. ECI discovered the damage to the pipeline and provided Bolduc and Travelers with written notice of the damage. MCES and Frontier demanded that ECI repair the damage to the pipeline; immediate repair was necessary to advance the project toward completion and to avoid assessment against ECI of liquidated damages of $5,000 per day. ECI incurred expenses of $235,339.89 in repairing the pipeline.

In March 2008, ECI submitted to Travelers a claim under the CGL policy seeking reimbursement of the expenses. Travelers denied the claim. The subcontract agreement between ECI and Bolduc called for ECI to pay Bolduc $32,513.29 for Bol-duc’s work on the project. ECI notified Bolduc that it was assessing a backcharge for the costs incurred in repairing the pipeline, and claimed that Bolduc owed ECI $202,826.60, representing the difference between the repair expenses incurred by ECI and the amount owed to Bolduc on the subcontract agreement.

ECI filed suit, alleging breach of contract and negligence against Bolduc and breach of contract and declaratory judgment against Travelers. Travelers filed a counterclaim for declaratory judgment, and Bolduc filed a counterclaim alleging breach of contract.

In November 2009, the district court bifurcated ECI’s negligence claim from the remaining claims. In March 2010, the parties stipulated that the only issues to be tried to the jury were “(a) ECI’s claim that Bolduc’s negligence resulted in damage to the pipe at FAS-1 on the [project], (b) Bolduc’s defense that it was ECI’s negligence that resulted in damage to the pipe, and (c) the amount of damages, if any, to which ECI is entitled if it prevails on its negligence claim.” The stipulation went on to state that ECI’s claims against Bol-duc for breach of contract and its claims against Travelers would be preserved for determination or resolution by the district court at a later date. Following trial, the jury returned a special verdict form finding that Bolduc was not negligent and that [920] ECI was not entitled to any money for its loss resulting from damage to the pipeline.

After the jury returned its verdict, ECI and Bolduc brought cross-motions for summary judgment on the remaining breach-of-contract claims. ECI and Travelers also brought cross-motions for summary judgment on the indemnification issue. The district court concluded that because a jury had determined that Bolduc was not negligent and the contract only required Bolduc to indemnify and insure appellant from damages caused by Bolduc’s negligence, Bolduc had not breached its contract with ECI. Under similar reasoning, the district court concluded that Travelers was not required to indemnify and insure ECI for the damage to the pipeline. The district court granted Bolduc and Travelers’ motions for summary judgment; denied appellant’s motions for summary judgment; and awarded Bolduc $45,965.53, plus prejudgment interest, on its breach-of-contract claim against appellant. This appeal follows.

ISSUES

1. Did the district court err by granting summary judgment in favor of Bolduc?

2. Did the district court err by granting summary judgment in favor of Travelers?

3. Is ECI’s argument that reversal of the district court’s award of summary judgment in favor of Bolduc require reversal of the district court’s award of $45,965.53 to Bolduc on Bolduc’s counterclaim properly before this court on appeal?

ANALYSIS

A motion for summary judgment shall be granted if “the pleadings, depositions, answers to interrogatories, and admissions on file, together with the affidavits, if any, show that there is no genuine issue as to any material fact and that either party is entitled to judgment as a matter of law.” Minn. R. Civ. P. 56.03. On an appeal from summary judgment, a reviewing court asks “whether the district court properly applied the law and whether there are genuine issues of material fact that preclude summary judgment.” Riverview Muir Doran, LLC v. JADT Dev. Grp., LLC, 790 N.W.2d 167, 170 (Minn.2010). An appellate court reviews both questions de novo, viewing the evidence in the light most favorable to the party against whom judgment was granted. STAR Ctrs., Inc. v. Faegre & Benson, L.L.P., 644 N.W.2d 72, 76-77 (Minn.2002). An award of summary judgment will be affirmed if it can be sustained on any ground. Winkler v. Magnuson, 539 N.W.2d 821, 827-28 (Minn.App.1995), review denied (Minn. Feb. 13, 1996).

I.

The indemnity language in the contract between ECI and Bolduc provides as follows:

Free access — add to your briefcase to read the full text and ask questions with AI

Engineering & Construction Innovations, Inc. v. L.H. Bolduc Co., 803 N.W.2d 916, 2011 Minn. App. LEXIS 118, 2011 WL 3903277 (Mich. Ct. App. 2011).

803 N.W.2d 916 (Engineering & Construction Innovations, Inc. v. L.H. Bolduc Co.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Judy Brown v. Judith M. Lee
859 N.W.2d 836 (Court of Appeals of Minnesota, 2015)
Engineering & Construction Innovations, Inc. v. L.H. Bolduc Co.
825 N.W.2d 695 (Supreme Court of Minnesota, 2013)