Engelking v. City of Spokane

110 P. 25, 59 Wash. 446, 1910 Wash. LEXIS 1222
Washington Supreme Court·Decided August 1, 1910·No. No. 8836·Published·Cited by 17 cases

Opinion

Chadwick, J.

At the time of his death, H. W. Engelking was a common laborer in the employ of the city of Spokane. The city was engaged in erecting a concrete bridge over the Spokane river, a short distance above the falls. The bridge had been so far completed as to warrant the removal of the false work sustaining the arches, of which there were several. High water had taken out the false work from under the second arch, and the wooden forms had been moored by cables to the Great Northern railway bridge, a structure which paralleled the city bridge about two hundred feet up the stream and to the east. These forms were lying near the shore, with the bow of the arch to the center of the stream. In consequence, the flow of the current along the shore line was naturally deflected toward the center arch of the city bridge. A few feet below the concrete structure, a temporary bridge had been erected. A part of this had gone out a short time before, but it was in place below the south arch, so that anything floating under the south arch would lodge against it and be thus prevented from being carried over the falls.

Engelking and four others were directed by the foreman in charge for the city to take some timbers then at hand and [448] make a raft, to be floated down under the south arch and upon which they could stand while removing the false work. No further direction or superintendence was given or had over the men, although one of their number “seemed to take the lead.” Accordingly the men took eight sticks, ten by ten, with cross-pieces leaving a space between each two of them, so that when the framework was completed the raft was about fourteen feet wide and twenty feet long. Upon this they erected a superstructure to bring them within reach of the top of the arch. When the raft had been completed it is estimated that it weighed from eight «to nine thousand pounds. Between the moored arches and the south span of the bridge, there was an eddy in the stream. In this, and about thirty or forty feet above the city bridge, the raft was moored, that point being also about sixty or sixty-five feet south of the pier upon which the center and south arches centered. The raft had been let down into the eddy and was secured by a long rope, two inches in diameter, attached to the Great Northern bridge, about seventy-five feet from the shore. Other ropes were attached to the raft. There is testimony going to show that one of these should have been used as a guy rope, to be held or tied on the shore while the raft was let down under the arch; while the other was to be used in securing the raft to the bridge. On the other hand, there is testimony showing that the large cable was alone depended on to let the raft down, while both of the smaller ropes were intended to secure the raft to the bridge when in proper position. The jury having found for plaintiff, we shall accept her theory as the true fact in the case.

When all was done, one of the workmen crossed the river to get some tools. Another went up to the Great Northern bridge to man the cable, the end of which was wrapped around a batter post on the Great Northern bridge. While the workman was going up the bank of the stream to man the cable, the rope which snubbed the raft to the shore was cut loose, so that when he first observed the raft after reach[449] ing his post, it was drifting up and out into the stream, carried up on the eddying waters, and out by the long sweep of the two hundred and forty-foot cable, the most of which was submerged and a part of which had been struck by the main current of the stream. The cable described a sweep or curve so that, at some time the segment of the curve must have been below or to the west of the upper end of the raft. Whether Engelking and one of his companions pushed the raft out with pike poles is a disputed fact, but not material as we view the case. As the raft caught the swift current, the force of the current fell upon the cable, drifted the raft rapidly out to the center and, as soon as the cable straightened out, pulled it under the surface. Those on the raft having no means of controlling it, the workman on the bridge was signalled to let out more rope, and when he did so the raft rose to the surface, but when the rope came taut the raft was again pulled under the water, this time about two and one-half or three feet, or to the waist line of the men thereon. This continued until the workmen could no longer hold the rope, and the raft, being then opposite and almost under the center arch, was carried through it and over the falls. One of the workmen escaped and was a witness at the trial. The other two lost their lives. This action is prosecuted by the widow of Engelking, and from a judgment in her favor, the city has appealed.

Counsel for appellant has aptly summarized the theories upon which a recovery was sought and must rest if sustained. He says:

“(1) That these 10x10 timbers, forming the foundations of the raft, had, a month previous, been green timbers, and had, during the month preceding, been lying in the water. (2) That the rope by which the raft was moored to the Great Northern bridge was too heavy. (3) That there was no foreman over these men and in' charge of the construction of the raft.”

The first two grounds may be summarily disposed of. It [450] may be conceded — for the testimony shows — that the raft and the rope would, under ordinary conditions, or under the anticipated conditions — that is, if the raft had been floated under and moored beneath the south arch — have been a sufficient and proper appliance. The scheme failed because the workmen did not appreciate the danger arising from the submerged cable, the rapid flow, and conflicting currents of the stream which carried the raft beyond the south arch and opposite the center arch, and the further fact that the strength of the current was sufficient to pull the raft under the water when its weight came squarely upon the rope.

Free access — add to your briefcase to read the full text and ask questions with AI

Engelking v. City of Spokane, 110 P. 25, 59 Wash. 446, 1910 Wash. LEXIS 1222 (Wash. 1910).

110 P. 25 (Engelking v. City of Spokane) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Eiban v. Widsteen
198 P.2d 667 (Washington Supreme Court, 1948)
Turoff v. Richman
61 N.E.2d 486 (Ohio Court of Appeals, 1944)
Cummins v. Dufault
139 P.2d 308 (Washington Supreme Court, 1943)
City of Spokane v. Spokane Gas & Fuel Co.
26 P.2d 1034 (Washington Supreme Court, 1933)
Johnson v. Smith
203 P. 56 (Washington Supreme Court, 1921)
Howard v. Tacoma School District No. 10
152 P. 1004 (Washington Supreme Court, 1915)
Crawford v. Western Clay & Gypsum Products Co.
151 P. 238 (New Mexico Supreme Court, 1915)
Williams v. City of Spokane
131 P. 833 (Washington Supreme Court, 1913)
Wolpers v. City of Spokane
131 P. 230 (Washington Supreme Court, 1913)
Peterson v. Seattle Electric Co.
128 P. 650 (Washington Supreme Court, 1912)
Parr v. City of Spokane
121 P. 453 (Washington Supreme Court, 1912)
Martin v. Hill
119 P. 849 (Washington Supreme Court, 1912)
Swanson v. Gordon
116 P. 470 (Washington Supreme Court, 1911)
Jacobsen v. Rothschild
113 P. 261 (Washington Supreme Court, 1911)
Beseloff v. Strandberg
113 P. 250 (Washington Supreme Court, 1911)
State v. Letica
112 P. 748 (Washington Supreme Court, 1911)
Hall v. Northwest Lumber Co.
112 P. 369 (Washington Supreme Court, 1910)