Empire Development Co. v. Johnson

770 P.2d 525, 236 Mont. 433, 1989 Mont. LEXIS 77
CourtMontana Supreme Court
DecidedMarch 21, 1989
Docket88-130
StatusPublished
Cited by5 cases

This text of 770 P.2d 525 (Empire Development Co. v. Johnson) is published on Counsel Stack Legal Research, covering Montana Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Empire Development Co. v. Johnson, 770 P.2d 525, 236 Mont. 433, 1989 Mont. LEXIS 77 (Mo. 1989).

Opinion

MR. JUSTICE HUNT

delivered the Opinion of the Court.

Bob Johnson, doing business as Rails Inn, appeals from a judgment of the District Court of the Thirteenth Judicial District, Yellowstone County, awarding damages of $920 to Empire Development Com *435 pany, doing business as Billings Neon Company (Billings Neon), for payments and deposit due under two sign rental agreements. Billings Neon cross-appeals from that part of the judgment relieving Johnson of liability for further payments under the leases. We affirm.

Johnson raises the following issue:

Did the District Court err by failing to credit Johnson for payments made under two lease agreements?

Billings Neon puts forth an additional issue for review:

Did the District Court err in concluding that Billings Neon failed to properly install and maintain rented signs as provided in the lease agreements?

On February 28,1981, Bob Johnson, owner of the Rails Inn in Forsyth, entered into a contract with Billings Neon for the lease of one pylon display. The contract provided that, for a monthly rental of $565, Billings Neon would erect and maintain a pylon display consisting of a four-column structure on which a remote control clock and two “Rails Inn” signs were posted. The agreement also required Johnson to pay an advance deposit of $2,260.

On December 9, 1982, the parties negotiated a second lease, which expressly canceled and superseded the first. The purpose of the second lease, apparently, was to remedy some visibility problems with pylon display. The second contract covered the existing pylon display and, in addition, required Billings Neon to erect and maintain a roof display “Motel” sign. The lease called for monthly payments of $600 for 60 months, plus an advance deposit of $2,400. The parties agreed to transfer the $2,260 deposited under the first lease to the second, leaving a balance of $140 on the advance deposit. Johnson never paid the deposit balance.

On January 28, 1983, Johnson guaranteed a lease entered into between Billings Neon and Clara E. Irons. The contract required Irons, who leased the Beanery Cafe and Sidetrack Lounge from Johnson, to pay monthly rent of $260 for a “24 Hour Cafe” sign to be erected and maintained by Billings Neon. The contract also provided for an advance deposit of $1,040, which Irons paid.

The “Motel” and “24 Hour Cafe” signs were installed by approximately March 23, 1983. On July 20, 1983, a strong windstorm wrenched the motel sign off its supports, damaging the roof of the Rails Inn. Johnson’s insurance paid for all but $100 of the repairs to the roof. Billings Neon did not compensate Johnson for the $100 *436 although the contract required the sign company to carry insurance that indemnified against property damage claims.

The windstorm also damaged the cafe sign. One day after the gale, Billings Neon was notified of the damage to the signs. Billings Neon never repaired either sign, although it retrieved the motel sign and took it to Billings, where it was later destroyed.

Neither Irons nor Johnson made any monthly payments under the cafe sign contract. Johnson did not make any payments under the motel sign lease until January 19, 1984. At that time, Johnson paid $1,000 to Billings Neon. The Billings Neon bookkeeper testified that she did not credit this payment to the motel sign lease, but instead applied the payment to the month of October 1982 and part of November 1982 under the first lease. On June 25, 1984, Johnson paid $1,500 to Billings Neon. The bookkeeper applied part of that payment to the first contract and the rest to other accounts Johnson kept with Billings Neon.

On December 5, 1984, Billings Neon notified Johnson in writing that he was in default on the motel sign lease, giving him five days to pay the balance due. Johnson failed to make the payment requested. Therefore, on December 12, 1984, Billings Neon accelerated the contract, demanding payment of $33,740. Johnson did not pay.

Both the first and second Rails Inn leases provided for a remote control clock on the pylon display. Johnson testified that he understood that the remote control box was to be installed in the motel office. His employees, however, could not locate the box, which caused a great deal of inconvenience during Forsyth’s frequent power outages.

Apparently, at some point between July 1983 and April 1985, the pylon display quit working. In April 1985, the new manager of the Rails Inn contacted Billings Neon to inquire about repairing the display. The manager was told that if he paid some money, the sign might be fixed. The manager sent a $600 payment in response. A few days later, a local electrician appeared and began to work on the display. When the motel manager discovered that the electrician thought he was working for the motel, not Billings Neon, the manager informed him that Rails Inn would not be responsible for the bill. The electrician left.

The pylon display stood unrepaired until, some time later, Johnson hired his own electrician to work on it. This electrician discovered that the control box for the remote control clock was located on one *437 of the display poles approximately 10 or 12 feet from the ground. He was unable to repair the controls.

On October 18, 1985, Billings Neon filed a complaint against Bob Johnson, alleging breach of the second lease and claiming damages of $33,740. Billings Neon also sought damages for breach of the cafe sign lease from either Clara Irons, as primary beneficiary of that agreement, or Johnson, as guarantor. Irons, however, had filed a petition for bankruptcy on June 10, 1983, which barred any action against her.

In response to the complaint, Johnson filed a counterclaim against Billings Neon, alleging breach of the first and second leases for failure to properly construct and maintain the signs and seeking a refund of all monies paid under the leases. Johnson additionally sought $129.50 in bills incurred by Billings Neon employees at the Rails Inn. At trial, Billings Neon admitted that it had authorized these bills. Thus, the charges are not at issue in this appeal.

After a one-day bench trial on April 22, 1987, the District Court found that Billings Neon failed to properly install and maintain the signs under the two Johnson leases and to maintain the sign under the Irons lease. The court concluded that Johnson was not liable for any rentals due under the leases subsequent to such failures. The court found, however, that Johnson was liable for the months of April, May and June 1983, under the Irons’ lease, for a total of $780. It also found that Johnson was liable for the $140 advance deposit he failed to pay under the second lease. In addition, the court awarded Johnson $129.50, representing the room and meal charges incurred by the Billings Neon employees. The court refused to grant either party attorney fees. From this judgment, both parties appeal.

Johnson argues that the District Court erred by failing to credit him for rental payments made under the first and second lease agreements.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

AVANTA FEDERAL CREDIT UNION v. Shupak
2009 MT 458 (Montana Supreme Court, 2009)
Stanley v. Lemire
2006 MT 304 (Montana Supreme Court, 2006)
Grenfell v. Anderson
2002 MT 225 (Montana Supreme Court, 2002)
Rod and Rifle Inn Inc. v. Giltrap
902 P.2d 38 (Montana Supreme Court, 1995)

Cite This Page — Counsel Stack

Bluebook (online)
770 P.2d 525, 236 Mont. 433, 1989 Mont. LEXIS 77, Counsel Stack Legal Research, https://law.counselstack.com/opinion/empire-development-co-v-johnson-mont-1989.