Empire Building Supply, Inc. v. EKO Investments, Inc.

596 P.2d 593, 40 Or. App. 739, 1979 Ore. App. LEXIS 2717
CourtCourt of Appeals of Oregon
DecidedJune 25, 1979
Docket77-349E, CA 11242
StatusPublished
Cited by12 cases

This text of 596 P.2d 593 (Empire Building Supply, Inc. v. EKO Investments, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Oregon primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Empire Building Supply, Inc. v. EKO Investments, Inc., 596 P.2d 593, 40 Or. App. 739, 1979 Ore. App. LEXIS 2717 (Or. Ct. App. 1979).

Opinion

*741 THORNTON, J.

Plaintiff, a building supply company, appeals a decree which (1) denied foreclosure of a materialman’s lien against an improvement owned and constructed by defendant EKO Investments, Inc., hereinafter referred to as owner, and (2) found that plaintiff was entitled to a personal judgment against defendant Reeder, hereinafter referred to as contractor. 1 Contractor cross-appeals the personal judgment, contending that all transactions with plaintiff were usurious. 2

The relevant facts are as follows. Owner and contractor entered into an agreement whereby contractor was to apply sheetrock and perform other services in an apartment complex being developed by owner. At the time he undertook these obligations, contractor was already indebted to plaintiff for materials supplied to other construction projects. Before submitting his bid on the EKO job, contractor telephoned plaintiff’s president, one Dale Woods, to find out whether and at what price Woods would be willing to furnish materials for the EKO apartments despite contractor’s unpaid bills. According to contractor’s testimony at trial, he explained to Woods that the only way he would be able to repay the old account would be to complete new jobs such as the one proposed by owner. He expressed concern that, because the EKO contract contained a liquidated damage clause of $100 per day, he could not afford to be shut down by a lien foreclosure for moneys already owing. At the conclusion of this conversation, contractor allegedly agreed to purchase all the materials for the EKO project from plaintiff in exchange for Woods’ promise to credit all *742 moneys received from contractor against the cost of materials supplied for the EKO apartments; only if there was an amount in excess of that figure would there be any moneys applied to contractor’s preexisting debt. In his testimony, Woods denied talking about segregating the billing and payment of the account for the EKO project and maintained that no separate accounting was kept.

When contractor began working for owner, plaintiff sent owner a notice of delivery of materials to be used in owner’s improvement. ¿SfecÓRS 87.021. Upon receiving the notice, Lewis Erbes, secretary-treasurer of owner, contacted Woods and expressed his concern about a possible lien foreclosure against the apartment complex under construction. According to Erbes’ testimony, he and Woods discussed contractor’s problems in paying his past bills and owner’s plans to make progress payments to contractor upon satisfactory completion of parts of his promised performance. He further stated that in order to safeguard plaintiff’s interest in receiving payment for materials furnished for the EKO job, as well as to protect owner from any future lien foreclosure, he would monitor expenses and contact Woods whenever he paid contractor. Erbes had already secured contractor’s assent to forward directly the initial progress payments to plaintiff and to request that plaintiff credit it against the cost of materials delivered to owner’s apartments.

Erbes asserted that had he not obtained Woods’ approval of this arrangement, he would have employed the customary means of avoiding material-man’s liens, which was to have both the contractor and the materialman sign a joint lien-waiver before issuing a check made payable to both parties. Erbes claimed that he had at least seven telephone conversations with Woods during the three-month period that followed the beginning of work on the apartment complex, the topic of which was always contractor’s account and the payments made to contractor. At least *743 three of those conversations preceded the receipt by plaintiff of three checks from contractor, the total of which exceeded the amount plaintiff claims under the lien as the reasonable value of the materials furnished to owner’s project.

At trial, Woods did not dispute that the three checks were received but disclaimed that he and Erbes had discussed partial payments to relieve contractor’s immediate financial difficulties or that Erbes had promised to advise him when such payments were made. Woods claimed that the only subject of conversation during the telephone calls was the money owner owed to contractor, and that he was unaware the three checks were in payment of the EKO job. Therefore, Woods followed his usual accounting procedure of crediting the payments to contractor’s oldest outstanding bills.

The disagreement as to the method of accounting came to light when plaintiff contacted owner and informed him that he was worried about not getting paid for the materials used in owner’s apartments. This announcement surprised owner, according to his testimony.

Plaintiff argues that in the absence of an agreement to waive the right to foreclose on a lien, see Gray v. Jones, 47 Or 40, 81 P 813 (1905), a materialman is not deprived of the right merely because an owner pays a contractor for materials furnished. ORS 87.021(2)(d). Plaintiff contends that there was no proof by a preponderance of the evidence that there was an agreement between owner and itself which constituted a waiver, and even if there had been such an agreement, there was insufficient evidence to conclude that owner had performed its part of the bargain so as to bar plaintiff from enforcing a lien. Plaintiff’s argument misses the point of the trial court’s findings, which in pertinent part provided:

"I further find by the greater weight of evidence that EKO and Empire Building Supply, through Mr. *744 Walker (sic), agreed to monitor the payments made by EKO to Reeder, that EKO did inform Empire Building Supply of the payments. Therefore, under ORS 87.021, (d) (sic), and Bohn vs. Wilson, 53 Or 490 and Portland Floor Company vs. Spaulding Logging Company, 64 Or 318,1 find that Empire Building had knowledge that the checks from Reeder on August 25, 1976, September 29,1976, and October 12,1976, were from EKO. I am finding for the Defendants and against the plaintiff.”

According to Bohn v. Wilson, 53 Or 490, 101 P2d 202 (1909), an agreement between an owner and a contractor to pay a materialman does not itself prevent the materialman from later seeking to foreclose a lien on the owner’s property. In Bohn, the owner gave the contractor a check payable to him as part payment on a building contract. It was understood between them that the check was to be delivered to the materialman and credited against the cost of the materials used to build the owner’s improvement. After endorsing the check, however, the contractor directed that it be applied against debts arising from materials supplied to a different construction project.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Johnston v. Palmer
2007 MT 99 (Montana Supreme Court, 2007)
Keith Brown Lumber Yard v. B & L Electric, Inc.
48 P.3d 209 (Court of Appeals of Oregon, 2002)
Beck v. Powell
832 P.2d 1254 (Court of Appeals of Oregon, 1992)
Teeny v. Haertl Constructors, Inc.
826 P.2d 1029 (Court of Appeals of Oregon, 1992)
E.C.A Environmental Management Services, Inc. v. Toenyes
679 P.2d 213 (Montana Supreme Court, 1984)
First State Bank v. Hoehnke Nursery Co.
667 P.2d 1022 (Court of Appeals of Oregon, 1983)
Anchor Concrete Co. v. Victor Savings & Loan Ass'n
664 P.2d 396 (Supreme Court of Oklahoma, 1983)
Minter-Wilson Drilling Co. v. Richins
655 P.2d 1060 (Court of Appeals of Oregon, 1982)
Tri-City Building Center, Inc. v. Stoneridge Development Co.
653 P.2d 1012 (Court of Appeals of Oregon, 1982)
Martin v. Dillon
642 P.2d 1209 (Court of Appeals of Oregon, 1982)
Stoner Electric, Inc. v. Gaudry
624 P.2d 155 (Court of Appeals of Oregon, 1981)

Cite This Page — Counsel Stack

Bluebook (online)
596 P.2d 593, 40 Or. App. 739, 1979 Ore. App. LEXIS 2717, Counsel Stack Legal Research, https://law.counselstack.com/opinion/empire-building-supply-inc-v-eko-investments-inc-orctapp-1979.