Emlenton Area Municipal Authority v. Miles

548 A.2d 623, 378 Pa. Super. 303, 1988 Pa. Super. LEXIS 2961
CourtSupreme Court of Pennsylvania
DecidedOctober 5, 1988
Docket121 and 122
StatusPublished
Cited by19 cases

This text of 548 A.2d 623 (Emlenton Area Municipal Authority v. Miles) is published on Counsel Stack Legal Research, covering Supreme Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Emlenton Area Municipal Authority v. Miles, 548 A.2d 623, 378 Pa. Super. 303, 1988 Pa. Super. LEXIS 2961 (Pa. 1988).

Opinion

BROSKY, Judge:

This is an appeal from the Order of December 30, 1987, which permanently stayed arbitration of the disputes between the parties. Appellant now contend? that the trial court erred in finding that the contract between the parties required mutual agreement before any disputes arising from the contract could be submitted to arbitration.

*305 Upon consideration of the record and the briefs of counsel, we now reverse and remand for further proceedings consistent with this Opinion.

On March 13, 1985, appellee Emlenton Area Municipal Authority (“Emlenton”) entered into a contract with appellant Sidney L. Miles, d/b/a Miles Developing and Contracting (“Miles”), wherein Miles was to construct a municipal waste water collection and treatment works in Venango and Clarion Counties, Pennsylvania. During the performance of the contract, certain disputes pertaining to the contract arose between the parties, causing them to assert claims for damages against one another.

On June 2, 1986, Miles, in an attempt to resolve his claims against Emlenton, filed a demand for arbitration with the American Arbitration Association. Emlenton responded on August 6, 1986, by filing an application for stay of arbitration proceedings with the Clarion County Court of Common Pleas.

With that matter still pending, Emlenton then filed, on May 4, 1987, an action at law in the same court, asserting its claims for damages against Miles and his surety, 1 Fidelity and Deposit Company of Maryland. In response to the action at law, Miles filed, on June 5, 1987, an application to compel arbitration. The court entered an order that same day to stay the proceedings at law, pending resolution of the issue of the arbitrability of the dispute.

On October 1, 1987, an order was entered with respect to Miles’ claims against Emlenton, granting Emlenton’s application for a stay of arbitration; similarly, on October 7, 1987, an order was entered in Emlenton’s action at law against Miles, denying Miles’ application to compel arbitration. In both instances, the court held that those portions of the contract comprising the parties’ agreement to arbitrate, only provide for the submission of any dispute or disputes to arbitration upon the mutual consent of the parties to so submit, and that, in light of Emlenton’s opposi *306 tion to arbitration of these disputes, Emlenton could not be compelled to submit to arbitration in either action.

Miles requested reconsideration in both cases, and reconsideration was expressly granted by the order of October 28, 1987. On December 30, 1987, however, the court entered a final order in equity in both actions, permanently staying arbitration. This timely consolidated appeal followed.

Appellant now argues that the trial court erred in finding that the agreement to arbitrate contained within the parties’ contract requires mutual consent for the submission of any particular dispute or disputes to arbitration, and maintains that the court’s narrow reading of the agreement precluding arbitration violates the liberal policy favoring arbitration, as well as the relevant rules of contractual interpretation and construction, expressed in Pennsylvania appellate law. 2 Conversely, appellee maintains that Pennsylvania law requires strict construction of arbitration agreements, and that a party may be compelled to arbitrate a dispute only *307 upon the finding of a clear, express, and unequivocal agreement to do so.

Our scope of review of an adjudication in equity is well established. The chancellor’s findings of fact have the force of a jury verdict, and are not to be disturbed where supported by competent evidence. Presbytery of Beaver-Butler of United Presbyterian Church in US. v. Middlesex Presbyterian Church, 507 Pa. 255, 267, 489 A.2d 1317, 1323 (1985), cert den. 474 U.S. 887, 106 S.Ct. 198, 88 L.Ed.2d 167; Sechler v. Sechler, 403 Pa. 1, 7, 169 A.2d 78, 80 (1961). However, the chancellor’s conclusions of law are always reviewable, as they are no more than his reasoning from the underlying facts. Presbytery of Beaver-Butler, supra; Sechler, supra; Village Beer and Beverage, Inc. v. Vernon D. Cox & Co., Inc., 327 Pa.Super. 99, 102, 475 A.2d 117, 118 (1984).

In the matter sub judice, the chancellor was called upon to determine whether the parties had agreed to submit any and all disputes to arbitration. Voluntary arbitration is purely a matter of contract, and, absent an express agreement between the parties to arbitrate their disputes, they cannot be compelled to arbitrate. Gaslin, Inc. v. L.G.C. Exports, Inc., 334 Pa.Super. 132, 139, 482 A.2d 1117, 1121 (1984). As such, it is for the court to determine whether an agreement to arbitrate exists, for the construction and interpretation of contracts is a question of law. Utica Mutual Ins. Co. v. Contrisciane, 504 Pa. 328, 334, 473 A.2d 1005, 1008 (1984). As a question of law, therefore, the chancellor’s conclusion as to whether the parties have agreed to arbitrate, is reviewable by this Court.

Upon undertaking such review, we are confronted with two basic, and seemingly contradictory, propositions, as noted by the parties themselves: (1) arbitration agreements are to be strictly construed and not extended by implication; and (2) when parties have agreed to arbitrate in a clear and unmistakable manner, every reasonable effort should be made to favor the agreement, unless it may be said with positive assurance that the arbitration clause involved is not *308 susceptible to an interpretation that covers the asserted dispute. See Hassler v. Columbia Gas Transmission Corp., 318 Pa.Super. 302, 307, 308, 464 A.2d 1354, 1356, 1357 (1983); also see Lincoln University of the Comm. System of Higher Education v. Lincoln University Chapter of the American Assoc. of University Professors, 467 Pa. 112, 119-20, 354 A.2d 576, 581-82 (1976). Obviously, some tension may arise between the two propositions; in making every effort to favor the settlement of a dispute by arbitration, one must be careful not to extend the arbitration agreement by implication beyond the clear, express, and unequivocal intent of the parties as manifested by the writing itself. Hassler, supra.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Bair v. Manor Care of Elizabethtown, PA
108 A.3d 94 (Superior Court of Pennsylvania, 2015)
Muschlitz Excavating, Inc. v. LTS Dev., LLC
20 Pa. D. & C.5th 217 (Monroe County Court of Common Pleas, 2010)
Gaffer Insurance v. Discover Reinsurance Co.
936 A.2d 1109 (Superior Court of Pennsylvania, 2007)
Trombetta v. Raymond James Financial Services, Inc.
907 A.2d 550 (Superior Court of Pennsylvania, 2006)
Smay v. E.R. Stuebner, Inc.
864 A.2d 1266 (Superior Court of Pennsylvania, 2004)
Neuhard v. Travelers Insurance
831 A.2d 602 (Superior Court of Pennsylvania, 2003)
Highmark Inc. v. Hospital Service Ass'n of Northeastern Pennsylvania
785 A.2d 93 (Superior Court of Pennsylvania, 2001)
School Dist. of City of Monessen v. Apostolou Associates, Inc.
761 A.2d 597 (Superior Court of Pennsylvania, 2000)
CGU Insurance v. Pinkerton Computer Consultants Inc.
49 Pa. D. & C.4th 481 (Philadelphia County Court of Common Pleas, 2000)
Calabrese v. Colonial Insurance
45 Pa. D. & C.4th 228 (Lackawanna County Court of Common Pleas, 2000)
Moses Taylor Hospital v. GSGSB
46 Pa. D. & C.4th 176 (Lackawanna County Court of Common Pleas, 2000)
Midomo Co. v. Presbyterian Housing Development Co.
739 A.2d 180 (Superior Court of Pennsylvania, 1999)
Smith v. Cumberland Group, Ltd.
687 A.2d 1167 (Superior Court of Pennsylvania, 1997)
Hazleton Area School District v. Bosak
671 A.2d 277 (Commonwealth Court of Pennsylvania, 1996)
HL Libby Corp. v. Skelly and Loy, Inc.
910 F. Supp. 195 (M.D. Pennsylvania, 1995)
Duquesne Light Co. v. New Warwick Mining Co.
660 A.2d 1341 (Superior Court of Pennsylvania, 1995)
Muse v. Cermak
630 A.2d 891 (Superior Court of Pennsylvania, 1993)

Cite This Page — Counsel Stack

Bluebook (online)
548 A.2d 623, 378 Pa. Super. 303, 1988 Pa. Super. LEXIS 2961, Counsel Stack Legal Research, https://law.counselstack.com/opinion/emlenton-area-municipal-authority-v-miles-pa-1988.