Embee Corp. v. Ringler

194 Misc. 2d 400
CourtNew York Supreme Court
DecidedOctober 11, 2002
StatusPublished

This text of 194 Misc. 2d 400 (Embee Corp. v. Ringler) is published on Counsel Stack Legal Research, covering New York Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Embee Corp. v. Ringler, 194 Misc. 2d 400 (N.Y. Super. Ct. 2002).

Opinion

OPINION OF THE COURT

Leslie E. Stein, J.

Petitioner Embee Corp. (hereinafter Embee) and petitioner Taub’s Carpet and Tile Corporation (hereinafter Taub’s) were successful bidders on an invitation for bids (hereinafter IFB) released by respondent in September 2001. Respondent notified petitioners by letter dated February 13, 2002 that they had each been awarded a contract. However, in April 2002, respondent’s counsel contacted petitioners by telephone and advised them that a review of the bid proposals indicated that an award should not have been made because their hourly labor rate was below the prevailing wage rate that applies to public works contracts. By letter dated April 5, 2002, petitioners were notified that the contracts were being terminated effective April 22, 2002. Petitioners assert that they were not given an opportunity to discuss or contest respondent’s decision to terminate their contracts. Petitioners further allege that respondent never asked to review their records. They also allege that they believe that they pay prevailing wage rates consistent with the industry standards for Suffolk County. In addition, petitioners assert that the contract provides for 60 days’ notice prior to termination and that such notice was not given.

Petitioners commenced this CPLR article 78 proceeding seeking the following relief: enjoining and restraining respondent from withdrawing the notice of awards of their respective contracts and from terminating said contracts; enjoining and restraining respondent from notifying the authorized users under the contracts of their purported termination; or, in the event the contracts were already terminated, directing that respondent restore petitioners to their status as approved vendors. Petitioners assert that respondent’s determination to [402]*402terminate the contracts was arbitrary and capricious and an abuse of discretion and that there is no adequate administrative remedy available without relief from the court. Pending the hearing and determination of the petition, respondents were stayed, enjoined and restrained from taking any action to withdraw and/or terminate petitioners’ status with regard to the contracts and from notifying any authorized users under the contracts the petitioners had been or will be terminated and further providing that petitioners shall not respond to any request for proposals or submit bids for work involving the miscellaneous hourly rate under said contracts.

Respondent answered the petitions, asserting that the court lacks subject matter jurisdiction in that any relief lies within the exclusive jurisdiction of the Court of Claims and that the petitions fail to state a cause of action.

Petitioners assert that a prospective contractor whose bid is rejected can challenge the determination in an article 78 proceeding (citing Burke’s Auto Body, Inc. v Ameruso, 113 AD2d 198; Matter of C.K. Rehner, Inc. [City of New York], 106 AD2d 268; Matter of Konski Engrs. v Levitt, 69 AD2d 940). Petitioners also assert that a contractor with the state may contest a decision to terminate their contracts in an article 78 proceeding (citing Nassau Roofing & Sheet Metal Co. v Facilities Dev. Corp., 70 AD2d 1021).

Respondent argues that the court lacks subject matter jurisdiction over this proceeding, as this is an action for breach of contract, which should be brought in the Court of Claims (citing Matter of Barrier Motor Fuels v Boardman, 256 AD2d 405; Matter of Granger & Sons v Comptroller of State of N.Y., 220 AD2d 945; Court of Claims Act § 9). Respondent also asserts that the fact that petitioners’ damages may be difficult to ascertain and that the petitions seek specific performance, as opposed to money damages, does not transform the matter into one cognizable under an article 78 proceeding (citing Matter of Barrier Motor Fuels, supra). Respondent further argues that petitioners’ reliance on Nassau Roofing & Sheet Metal Co. v Facilities Dev. Corp. (supra) is misplaced, as that case involved an article 78 proceeding in which the petitioner sought to prohibit a state agency from disqualifying a contractor from bidding on future contract proposals by virtue of deficient performance.

Respondent further alleges that the wage rates of $35 per hour which were bid by petitioners for each county in question were facially defective and nonresponsive to the IFB, as they [403]*403were in violation of the requirement of section III.7 of the IFB.1 Respondent alleges that the prevailing wage rate plus supplemental benefits is $56.19 ($33.28 wages plus $22.81 supplemental benefits) for all regions in which petitioners bid, except for Sullivan and Ulster Counties, in which Taub’s bid and in which the proper rate is $36.20 ($24.80 wages plus $11.40 supplemental benefits).

Respondent alleges that the relevant prevailing wage and benefit information was made available to each attendee at a prebid meeting. Respondent further alleges that Embee’s representative attended this meeting, but that Taub’s representative did not. Respondent alleges that the failure of the rates quoted by petitioners to comply in the first instance with the IFB and the Department of Labor prevailing wage laws was not discovered prior to the award of the contract due to an error in respondent’s office.

Respondent asserts that, while there is a provision in the IFB allowing the reduction of a bid once the bids have been opened, there is no provision allowing a bidder to increase a bid after the bids have been opened. Respondent further asserts that the IFB requirements, together with the bid and notice of award, are material elements to the contract and that petitioners were unable to supply an essential element of the contract. Respondent argues that, if the purchasing officer had recognized the defect at the time the bids were opened, petitioners’ bids would have been disqualified. Thus, respondent contends that it exercised its right of cancellation for cause pursuant to section 59 of appendix B to the IFB, as petitioners were unable to meet the requirements of the contract relative to the prevailing wages and supplemental benefits.

Respondent argues that petitioners’ position that the state must “live with” its error is untenable. Respondent asserts that public contracts that violate express statutory mandates are unenforceable (citing Granada Bldgs. v City of Kingston, 58 NY2d 705). Respondent further asserts that erroneous approval of an improper contractual provision cannot bind the State or somehow give rise to estoppel (citing Williams Press v State of New York, 45 AD2d 397).

Respondent asserts that the improperly low prevailing wage rate bid by petitioners violates both article 8 of the Labor Law [404]*404and the express provisions of the contract and that there is no cognizable cause of action against a public entity for underpayment of prevailing wage requirements (citing Hoxie’s Painting Co. v Cato-Meridian Cent. School Dist., 76 NY2d 207; Sarbro IX v State of N.Y. Off. of Gen. Servs., 229AD2d 910; Armco Drainage & Metal Prods. v State of New York, 4 AD2d 366). Respondent further asserts that failure to pay the statutory prevailing wage is against public policy, that to continue a contract that was established in error is contrary to law and that the error should be remedied by the cancellation of the contract.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Brian Hoxie's Painting Co. v. Cato-Meridian Central School District
556 N.E.2d 1087 (New York Court of Appeals, 1990)
Williams Press v. State of NY
335 N.E.2d 299 (New York Court of Appeals, 1975)
Dondi v. Jones
351 N.E.2d 650 (New York Court of Appeals, 1976)
Granada Buildings, Inc. v. City of Kingston
444 N.E.2d 1325 (New York Court of Appeals, 1982)
Abiele Contracting, Inc. v. New York City School Construction Authority
689 N.E.2d 864 (New York Court of Appeals, 1997)
Armco Drainage & Metal Products, Inc. v. State
4 A.D.2d 366 (Appellate Division of the Supreme Court of New York, 1957)
Zara Contracting Co. v. Cohen
23 A.D.2d 718 (Appellate Division of the Supreme Court of New York, 1965)
Bradford v. Helman
24 A.D.2d 937 (Appellate Division of the Supreme Court of New York, 1965)
Williams Press, Inc. v. State
45 A.D.2d 397 (Appellate Division of the Supreme Court of New York, 1974)
Konski Engineers P. C. v. Levitt
69 A.D.2d 940 (Appellate Division of the Supreme Court of New York, 1979)
Nassau Roofing & Sheet Metal Co. v. Facilities Development Corp.
70 A.D.2d 1021 (Appellate Division of the Supreme Court of New York, 1979)
Fischbach & Moore, Inc. v. New York City Transit Authority
79 A.D.2d 14 (Appellate Division of the Supreme Court of New York, 1981)
In re C. K. Rehner, Inc.
106 A.D.2d 268 (Appellate Division of the Supreme Court of New York, 1984)
Burke's Auto Body, Inc. v. Ameruso
113 A.D.2d 198 (Appellate Division of the Supreme Court of New York, 1985)
R.W. Granger & Sons, Inc. v. Comptroller
220 A.D.2d 945 (Appellate Division of the Supreme Court of New York, 1995)
Sarbro IX v. State New York Office of General Services
229 A.D.2d 910 (Appellate Division of the Supreme Court of New York, 1996)
Barrier Motor Fuels, Inc. v. Boardman
256 A.D.2d 405 (Appellate Division of the Supreme Court of New York, 1998)
Albro Contracting Corp. v. Department of Public Works
13 Misc. 2d 846 (New York Supreme Court, 1958)
Zara Contracting Co. v. Cohen
45 Misc. 2d 497 (New York Supreme Court, 1964)
Gottfried Baking Co. v. Allen
45 Misc. 2d 708 (New York Supreme Court, 1964)

Cite This Page — Counsel Stack

Bluebook (online)
194 Misc. 2d 400, Counsel Stack Legal Research, https://law.counselstack.com/opinion/embee-corp-v-ringler-nysupct-2002.