Elway Company, LLP, Dale K. Elrod, Jeffrey L. Elrod, and Mary Ann Waymire v. Champlain Capital Partners, L.P.

114 N.E.3d 1
CourtIndiana Court of Appeals
DecidedOctober 26, 2018
DocketCourt of Appeals Case 18A-CC-443
StatusPublished
Cited by2 cases

This text of 114 N.E.3d 1 (Elway Company, LLP, Dale K. Elrod, Jeffrey L. Elrod, and Mary Ann Waymire v. Champlain Capital Partners, L.P.) is published on Counsel Stack Legal Research, covering Indiana Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Elway Company, LLP, Dale K. Elrod, Jeffrey L. Elrod, and Mary Ann Waymire v. Champlain Capital Partners, L.P., 114 N.E.3d 1 (Ind. Ct. App. 2018).

Opinion

Bailey, Judge.

Case Summary

[1] Elway Company, LLP, ("Elway Company") and siblings Dale K. Elrod ("Dale"), Jeffrey L. Elrod ("Jeffrey"), and Mary Ann Waymire ("Mary Ann") (collectively and at times taken together with Elway Company, "the Elrod Plaintiffs") appeal a grant of summary judgment in favor of Champlain Capital Partners, L.P. ("Champlain") upon remand from an appeal of prior litigation related to eight construction projects ("the Bonded Projects") covered by a Bonding Collateral Agreement ("the Agreement") executed by the Elrod Plaintiffs and Safeco Surety ("Safeco"), now Liberty Mutual Insurance Company. We remand "to permit the introduction of evidence so that the trial court may consider and rule on whether the various projects from which bond claims arose ... were completed within the scope of the meaning of completion as set forth by the Agreement." Champlain Capital Partners, L.P. v. Elway Co., LLP , 58 N.E.3d 180 , 201 (Ind. Ct. App. 2016), trans. denied (" Champlain I ").

Issues

[2] The Elrod Plaintiffs present for our review three consolidated and restated issues:

I. Whether the law-of-the-case doctrine should be discarded under the circumstances of this case;
II. Whether the trial court improperly granted summary judgment upon its determination that all bonded projects were complete, *3 thereby triggering the reimbursement provision of the Agreement; and
III. Whether prejudgment interest was properly awarded. 1

Facts and Procedural History

[3] In 2004, Dale, Jeffrey, and Mary Ann were majority shareholders in the John K. Elrod Company ("JKE"), a business involved in construction of stadium seating and safety barriers. See Champlain I . In 2005, Champlain, a Delaware investment firm focused on small business acquisition and growth, acquired JKE in a leveraged buyout. The Elrod siblings were then minority shareholders.

[4] Before and after the leveraged buyout, JKE obtained its performance, payment, and supply bonds from Safeco. 2 After the buyout, Safeco determined that it would no longer accept personal indemnities from a family member and instead demanded $3.5 million collateral in the form of an irrevocable letter of credit ("ILOC"). See id. The Elrod siblings agreed to loan $3.5 million to JKE from the proceeds of the sale of the business to Champlain. The ILOC was placed with Fifth Third Bank.

[5] JKE's finances became unstable and Fifth Third Bank moved JKE's loans to a workout division in anticipation of foreclosing on the loans. See id. at 186 . During July and August of 2006, the Elrod Plaintiffs, Champlain, JKE's lenders, and other minority shareholders in JKE negotiated a transaction to restructure JKE's finances. The Elrod Plaintiffs contributed several million dollars in capital to JKE, and Elway Corporation 3 acquired, with the Elrod funds, certain JKE assets, thereby contributing $4.7 million to JKE. Safeco released the $3.5 million ILOC, replaceable by a $3.5 million ILOC using capital from Champlain ("the Substitute LOC").

[6] With JKE on more solid financial footing, its goal was to expand its business to include larger jobs. For this, JKE needed to increase its bonding limits with Safeco. To address the availability of collateral so that Safeco would increase JKE's bonding limits, the restructuring transaction included the Agreement. The Agreement required Champlain to provide the Substitute LOC in a value not to exceed $3.5 million and this had been done before the Agreement was executed. The Agreement also required the Elrod Plaintiffs to provide collateral not to exceed $3.5 million to Safeco, but the terms did not include a time limit. See id. at 186-87 .

[7] By mid-October of 2006, JKE's cash flow situation was dire, and it defaulted on lease payments to Elway Company. On October 16, 2006, Champlain, as the majority shareholder, placed JKE into liquidation bankruptcy proceedings. JKE ceased performance on the Bonded Projects. Consequently, Safeco acted to draw down the funds in the Substitute LOC. See id. at 188 . Safeco placed the $3.5 million into a bank account to use for paying claims against bonds Safeco had issued on JKE's behalf. Safeco used all but $591,023.98 of funds from the Substitute LOC to reimburse itself for claims against JKE bonds and pay expenses associated with bond claims and litigation. Eight construction *4 project owners had potential bond claims: Michigan International Speedway ("MIS"), Darlington Raceway, Watkins Glen, Maine Township High School, Kewanee School, Rialto School, Speedway Bid, and Speedway Grandstand.

[8] Champlain demanded reimbursement from the Elrod Plaintiffs for the Safeco draw-down of funds, but the Elrod Plaintiffs disputed the demands. On December 22, 2010, the Elrod Plaintiffs filed a declaratory judgment complaint, alleging that their obligations under the Agreement were limited to payments made from the Substitute LOC for defaults on only performance bonds. Champlain filed a counterclaim, alleging that the Elrod Plaintiffs had breached the terms of the Agreement by failing to post an additional $3.5 million in collateral and by withholding reimbursement for claims paid related to the Bonded Projects. In addition to alleging breach of contract, Champlain asserted claims of unjust enrichment and breach of an implied covenant of good faith and fair dealing. 4

[9] The parties filed cross-motions for summary judgment, and the trial court granted partial summary judgment to the Elrod Plaintiffs, concluding that the Agreement applied only to performance bonds and that an unjust enrichment claim could not proceed when the rights of the parties were controlled by a contract.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

August Wohlt v. Christi Wohlt
Indiana Supreme Court, 2024
State v. Trimble
2022 Ohio 1906 (Ohio Court of Appeals, 2022)

Cite This Page — Counsel Stack

Bluebook (online)
114 N.E.3d 1, Counsel Stack Legal Research, https://law.counselstack.com/opinion/elway-company-llp-dale-k-elrod-jeffrey-l-elrod-and-mary-ann-waymire-indctapp-2018.