Elmer Brown v. State

Court of Appeals of Texas·Decided April 17, 2014·No. 02-12-00532-CR·Published

Opinion

COURT OF APPEALS

SECOND DISTRICT OF TEXAS

FORT WORTH

NO. 02-12-00532-CR

ELMER BROWN APPELLANT V.

THE STATE OF TEXAS STATE

----------

FROM COUNTY CRIMINAL COURT NO. 4 OF DENTON COUNTY ----------

MEMORANDUM OPINION 1

----------

Appellant Elmer Brown appeals his conviction for deceptive business practice. We affirm.

Background Facts

In early 2007, Bonnie Serben sought bids from contractors to repair and remodel her mother’s house. In May 2007, she received a bid from Appellant’s

1 See Tex. R. App. P. 47.4.

company, Brown and Company. Appellant proposed to, among other things, replace the roof and siding, replace the exterior doors and windows, replace the septic tank system, install skylights, perform landscaping, rewire the electrical system, install a HVAC system, replace sheetrock and insulate the walls, install cabinets and bathroom fixtures, and refinish the hardwood floors.

Serben and Appellant negotiated a contract for Appellant’s services.

Serben agreed to pay Appellant $118,176. The contract stipulated that Serben would pay $35,963 of the contract price as a deposit “to be used by [Appellant] for the purchase of all exterior materials, equipment, and tools required and permits necessary to begin the Work.” Serben agreed to pay for the rest of the services as they were completed upon submission of a payment request by Appellant. The contract stated,

The submission of a payment request by Contractor will constitute a representation by Contractor to Owner that the Work has progressed to the point indicated and that, to the best of Contractor’s knowledge, information[,] and belief, the quality of the Work is in accordance with this Agreement and generally accepted industry standards applicable in Texas.

The parties agreed that Serben would retain 15% of each invoice amount for thirty days after completion of the entire project. The contract also provided for an early completion bonus if Appellant completed the work in one hundred working days and a late completion penalty if Appellant did not finish the project within 146 working days. The parties signed the contract in June 2007.

Serben received an invoice for the deposit ($30,568.55 after the 15% retainage), which she paid by check on June 16, 2007. Serben received a second invoice on June 26, 2007, for $6,800 for the installation of the roof. She paid that invoice by check on July 2, 2007. Serben received a third invoice also dated June 26, 2007 for $24,990 for “interior demolition,” “clear[ing] debris/shrubs,” “remov[ing] trees/prun[ing] trees,” and electrical wiring and materials, air conditioning unit and duct materials and accessories, and copper lines for plumbing. Serben paid that invoice by check on July 7, 2007.

In September 2007, Serben requested and received a cost report from Appellant showing how the funds had been applied. In the cost report, Appellant stated that he had performed and bought material for $46,671 worth of work, including installing the skylights, cabinets, and the HVAC system and performing electrical and plumbing work, none of which had actually been performed. The cost report also included $5,099 for “Administrative.”

Also in September 2007, Serben requested a contract change order adding $6,339 of work to the contract. On September 14, 2007, Serben received a fourth invoice for $12,196.95 for siding, tree trimming, insulation and drywall installation, and a number of the items from the change order. Serben paid the invoice by check on September 15, 2007.

In early October 2007, Serben attempted to reach Appellant because “nothing was getting done” on the house. She called him “[n]umerous times,” but he did not answer the phone and eventually the number was disconnected. On

October 8, 2007, Appellant emailed Serben and said that he had been away at his grandmother’s funeral in Arkansas and that he had “a very ag[gressive] schedule to make up for lost time.” He told Serben that he was expecting to complete the project some time in November. Serben testified that Appellant did no more work after he sent that email. None of the things that Appellant said in the email he would complete, such as installing the HVAC system, completing the plumbing, installing the sheetrock, and finishing the carpentry work, were completed.

On November 20, 2007, Serben’s husband, John, emailed Appellant a letter regarding what work still needed to be completed on the house. The letter said,

It continues to be very difficult to contact you. You don’t answer your cell phone and never seem to empty your cell phone mailbox, and, as a result, we cannot leave messages for you! . . . In addition, you have not shown up for several meetings with us that you requested.

John told Appellant,

It is obvious that there has been no activity by you [on the house] in nearly two months. . . . Your delays have caused us considerable anxiety, problems, time, money, disruption to our personal plans, inconvenience, etc[.], over your inability, desire, and wherewithal [to]

do what you committed to do. And, may I remind you, that we have paid you in advance, far more than the work completed thus far can justify.

In the email, John also said, “You have not delivered to us copies of paid invoices and the written proof of releases from your subcontractors as we have requested several times and is specified in our contract with you.” He told

Appellant that under the contract, he had until January 24, 2008 to complete the project.

On November 24, 2007, Appellant responded to the letter. He told the Serbens that he had been waiting for the windows to be installed and that he had “everyone scheduled to go in at the end of th[at] week.” He disputed the Serbens’ calculation of the last day of the contract period but said, “Once we begin, the final product should not take long to complete.” Serben received no further communications from Appellant.

On December 3, 2007, Serben emailed Appellant again and stated that still no more work had been done on the house. She said, “At this point, we would be happy to cancel the contract and either get the money we advanced for materials returned to us, or alternately, the materials that you purchased with that money!” She received no response from Appellant.

On January 23, 2008, Serben sent Appellant a letter stating that she was cancelling the contract. Serben also filed a complaint against Appellant with the Better Business Bureau and with the Flower Mound Police Department. A police detective assigned to the case spoke to Appellant by phone. Appellant told the detective that he had gotten sick and had turned the project over to somebody else. The detective asked to speak to Appellant in person. Appellant said he was in Houston for two weeks but that he would call when he got back to town. When the detective did not hear from Appellant, he forwarded the case to the District Attorney’s office.

In February 2009, Appellant was charged with committing a deceptive business practice. Trial was originally set for November 2011 but was reset repeatedly until it was finally set for August 7, 2012. On July 30, 2012, Appellant filed a motion for continuance stating,

[Appellant] is a severe diabetic who has been hospitalized numerous times since May 2012 in attempt to deal with the effects of his diabetes. [Appellant] has a cataract in his left eye that has completely blinded him and his right eye has a cataract that is diminishing his eyesight as well. [Appellant] has been scheduled for oral surgery on his jaw for August 1, 2012; retinal surgery on his right eye for August 7, 2012; and cataract surgery for August 31, 20[12].

The trial court spoke on the phone to Appellant’s doctors and, at a pretrial hearing, told the parties that “they said he should be fine to come up here and sit with [his attorney] on the day after” the August 7 surgery. The trial court denied Appellant’s motion for continuance and set trial for August 9, 2012.

Free access — add to your briefcase to read the full text and ask questions with AI

Elmer Brown v. State, (Tex. Ct. App. 2014).

Elmer Brown v. State (Elmer Brown v. State) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Jackson v. Virginia
443 U.S. 307 (Supreme Court, 1979)
Margraves v. State
34 S.W.3d 912 (Court of Criminal Appeals of Texas, 2000)
Laster v. State
275 S.W.3d 512 (Court of Criminal Appeals of Texas, 2009)
Morris v. State
301 S.W.3d 281 (Court of Criminal Appeals of Texas, 2009)
Montoya v. State
291 S.W.3d 420 (Court of Criminal Appeals of Texas, 2009)
Matson v. State
819 S.W.2d 839 (Court of Criminal Appeals of Texas, 1991)
Lewis v. State
911 S.W.2d 1 (Court of Criminal Appeals of Texas, 1995)
Moore v. State
999 S.W.2d 385 (Court of Criminal Appeals of Texas, 1999)
Morrow v. State
443 A.2d 108 (Court of Appeals of Maryland, 1982)
Kutzner v. State
994 S.W.2d 180 (Court of Criminal Appeals of Texas, 1999)
Turner, Albert James
422 S.W.3d 676 (Court of Criminal Appeals of Texas, 2013)
Winfrey, Megan AKA Megan Winfrey Hammond
393 S.W.3d 763 (Court of Criminal Appeals of Texas, 2013)
McDaniel v. State
98 S.W.3d 704 (Court of Criminal Appeals of Texas, 2003)