Ellis v. Phillips

110 N.W.2d 772, 363 Mich. 587
CourtMichigan Supreme Court
DecidedSeptember 21, 1961
DocketDocket 71, Calendar 48,382
StatusPublished
Cited by11 cases

This text of 110 N.W.2d 772 (Ellis v. Phillips) is published on Counsel Stack Legal Research, covering Michigan Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ellis v. Phillips, 110 N.W.2d 772, 363 Mich. 587 (Mich. 1961).

Opinions

Kavanagh, J.

Plaintiff was appointed receiver of Redford Cement Floor Company, a Michigan corporation, on February 7, 1958. Redford Cement Floor Company (hereinafter referred to as Redford) during its existence engaged in the business of installing flat cement in commercial projects. Defendant William J. Phillips, doing business as Phillips Construction Company, is a general contractor. Pie had not engaged in actual construction work for 3 or 4 years prior to the trial of this case, but carried on his general contracting through subcontractors.

[591]*591Plaintiff receiver on February 21, 1958, instituted this action in assumpsit declaring on a contractual agreement and also on the common counts. The declaration alleged that Bedford had fully performed a subcontract with defendant and had supplied labor and materials to defendant, and that there was owing to plaintiff under the subcontract for labor and materials furnished a balance in the amount of $15,033.09.

Defendant answered denying that Bedford had performed its subcontract; that defendant had breached the subcontract; or that any sum remained ■owing to Bedford or plaintiff.

At trial, documents consisting of a contract between Phillips and the city of Detroit, a performance bond, and a payment bond, comprising defendant’s exhibit F, were admitted in evidence over the objections of plaintiff. These documents tended to show that on February 5, 1957, defendant entered into a contract with the city of Detroit for certain construction work on the Detroit housing commission’s Brewster project; that the amount of said contract was $52,549; and that in connection with said •contract defendant furnished a performance bond with Travelers Indemnity Company as surety. Further testimony developed that defendant, on February 8,1957, invited bids on cement work and Bedford submitted a proposal for the work. The testimony disclosed that on February 19, 1957, defendant and Bedford executed an agreement, prepared and drafted by defendant. This contract enumerated the materials, equipment, and services to be supplied by Bedford according to the plans and specifications of the Detroit housing commission’s architect. Defendant agreed to pay Bedford in monthly payments the sum of $31,731 for materials and labor. Payments were to be made in accordance with defendant’s agreement with the Detroit housing commission.

[592]*592The subcontract included a provision that Redford would furnish bond and insurance certificates as required. It developed that Redford was unable to secure a bond, since it had not been in business long-enough and was not sufficiently capitalized. Mr. Bull, president and general manager of Redford, went to defendant and explained Redford’s predicament, and offered to withdraw from the subcontract.. Although there was conflict in the testimony, defendant said he thought Redford was going to furnish a bond; that he never informed Redford it did not have-to furnish a bond; that about a month after the execution of the subcontract Redford indicated it could not secure a bond and that he “let him go ahead.”' Redford began work under the subcontract in April, 1957, and allegedly completed the work the latter part of August, 1957. Shortly thereafter Redford went into receivership.

Defendant did not pay for the work done by Redford in monthly payments as provided by the terms-of the subcontract. Redford claims that because of defendant’s refusal to pay it became short of funds,, and eventually authorized defendant to pay some of its suppliers to the extent of $14,150.78. Defendant admitted owing a balance of $15,033.09 on the subcontract.

After Redford had allegedly completed its work,, defendant asserted Redford had left certain work unfinished as represented by deficiency lists received by defendant from the city of Detroit in connection with his contract. These items were relocation of fences and poles, repair of cracked cement, repair of' rough concrete surfaces, repair of a retaining wall,, cleaning away rubble, and failure to waterproof concrete. Defendant claims he expended $1,170.73 for-curing the deficiencies. Mr. Bull, testifying for Redford, stated Redford was not responsible for most of these deficiencies and that a number of the items [593]*593were not called for under Bedford’s subcontract or by the specifications.

During the trial defendant moved to transfer the cause from the law side to the equity side of the court, alleging equitable defenses which he should be permitted to present. Over objections of plaintiff, the trial judge entered an order transferring the cause to the equity side. The alleged equitable defenses were: Bedford was indebted to certain persons for materials and labor furnished on the job. Defendant had furnished the surety bond agreeing to save the city of Detroit harmless from any liens for labor and materials. As such it became surety for Bedford, a subcontractor who was working without bond. If defendant were required to pay the $15,033.09 balance to plaintiff, defendant eventually would be required to pay Bedford’s material and labor suppliers who were owed an amount approximately equal to the unpaid balance on Bedford’s subcontract.

The trial court, at the conclusion of proofs, ruled that $240.75 should be allowed defendant for work done and materials furnished to complete the job. The court further found that plaintiff receiver stood in the same position as the assignor, Bedford Cement Floor Company, and that any defenses that could be raised against Bedford could be raised against the receiver. In its opinion the court found that Bed-ford had not completed its contract in that it had not completed its work and had not furnished a surety bond.

The trial court found defendant to be a surety in fact and in law and one who should be protected from having to pay the receiver and then pay twice for the same work by having to pay Bedford’s creditors who could collect on defendant’s payment bond.

The trial court decreed payment should be made by defendant directly to Bedford’s creditors in the [594]*594amount of $15,033.09 from the fund established by defendant paying into court $2,532.33 and the sum of $12,500.76 paid into court by the garnishee defendant. The amount paid into the fund by defendant represented the difference between the amount unpaid by Phillips on the subcontract and the amount .garnisheed at the commencement of the action.

The trial court further decreed that defendant could offset claims of Bedford’s creditors against the action of the plaintiff receiver; that the same constituted an equitable setoff; and that full disbursement of such claims would constitute complete satisfaction of defendant’s liability to the plaintiff receiver.

On entry of decree, plaintiff appeals contending:

(1) There was no basis for the lower court’s action in transferring this cause from the law side of the court to the equity side.

(2) The lower court was not justified in allowing defendant equitable setoffs to the claim of plaintiff under the circumstances; there was nothing in the record to support such equitable setoffs as being-founded on any presently existing- determined, valid claims of defendant against the plaintiff.

(3) There was no basis for the lower court taking-jurisdiction over any asset of the receivership and making- disposition of it while such asset was under the control of the court having jurisdiction of the receivership.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Walker v. Farmers Insurance Exchange
572 N.W.2d 17 (Michigan Court of Appeals, 1998)
In re Forfeiture of $8,141 of United States Currency
432 N.W.2d 442 (Michigan Court of Appeals, 1988)
Michigan Nat'l Bank of Detroit v. Kellam
309 N.W.2d 700 (Michigan Court of Appeals, 1981)
Moore v. McDowell
221 N.W.2d 446 (Michigan Court of Appeals, 1974)
Duncan v. Beres
166 N.W.2d 678 (Michigan Court of Appeals, 1968)
Husted v. Consumers Power Co.
135 N.W.2d 370 (Michigan Supreme Court, 1965)
Ellis v. Phillips
110 N.W.2d 772 (Michigan Supreme Court, 1961)

Cite This Page — Counsel Stack

Bluebook (online)
110 N.W.2d 772, 363 Mich. 587, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ellis-v-phillips-mich-1961.