Ellis v. Chevron U. S. A. Inc.

650 F.2d 94
CourtCourt of Appeals for the Fifth Circuit
DecidedJuly 8, 1981
DocketNo. 80-3648
StatusPublished
Cited by34 cases

This text of 650 F.2d 94 (Ellis v. Chevron U. S. A. Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fifth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ellis v. Chevron U. S. A. Inc., 650 F.2d 94 (5th Cir. 1981).

Opinion

JERRE S. WILLIAMS, Circuit Judge:

Decedent, Michael L. Ellis, was killed while working on a stationary drilling plat[96]*96form in the Gulf of Mexico more than three miles off the coast of Louisiana. This action was brought by his surviving parents under the Outer Continental Shelf Lands Act, 43 U.S.C. § 1331 et seq. Asserted applicability also of diversity jurisdiction does not lie. Aymond v. Texaco, Inc., 554 F.2d 206, 211 (5th Cir. 1977).

Michael Ellis was working as an employee of Houma Welders, Inc. on the platform owned by defendant Chevron. Houma had been hired as an independent contractor to reduce the size of the header unit on the drilling platform. The unit had been installed in the early part of August 1976. Chevron had found the header system was too large so it had hired Houma to reduce its size, and Houma began work around October 11, 1976, approximately two months after the completion of the original job.

In the course of carrying out the contracted work a small crew of employees of Houma, including Ellis, were engaged in removing heavy valves from the header system. These valves were located approximately five feet off the floor of the platform and because of their weight had to be lowered by a pulley system.

On October 12, 1976, the crew undertook to remove the first valve. The valve was secured by a cable on a pulley or block and tackle system by another employee while Ellis removed the bolts. When the bolts had been removed the valve remained stuck. As he was shaking it free, it suddenly came loose and Ellis lost his balance and fell backward holding the valve. This movement of the valve caused the cable in the pulley system to shift its normal position and strike and dislodge a heavy 12 x 12-timber about ten feet long which was lying above the valve on the structure of the platform. This large piece of timber, estimated to weigh more than 200 pounds, fell on top of Ellis and crushed him, causing his death.

The evidence showed that the timber which fell and killed Ellis was a shipping brace which had been used in bringing to the barge the original header system components which had been installed in early August. . It belonged to Chevron and had simply been left on the structure at this point without being secured in any way and without serving any useful purpose.

On these facts the jury found that Chevron was solely responsible for the accidental death of Ellis. Ellis was found not to have been negligent nor to have assumed the risk. Houma Welding also was found not to have been negligent. Judgment was rendered on behalf of plaintiffs Clifford Ellis and Doris Ellis in the sum of $167,-043.40 together with seven percent interest from the date of judicial demand. Later the district court revised its judgment to provide for interest only from the date of judgment. Chevron’s demand for defense and indemnity against Houma Welders and its insurers was dismissed.

Chevron appeals, claiming the district court was in error in refusing to direct a verdict in its favor and denying post trial motions for a new trial and for judgment notwithstanding the verdict. Chevron first challenges the sufficiency of the evidence to uphold the verdict of the jury. It asserts that the district court erred in not directing a verdict in its favor and in denying motions for a new trial or for judgment n. o. v.

The standards under which the denial of such motions is to be reviewed is well established in this court. Although Chevron attempted to develop a distinction between the standard for granting a motion for directed verdict and the standard for granting a motion for a judgment n. o. v., Boeing Co. v. Shipman, 411 F.2d 365 (5th Cir. 1969, en banc), establishes the law of this Circuit. On p. 374 that standard is stated:

On motions for directed verdict and for judgment notwithstanding the verdict the Court should consider all of the evidence — not just that evidence which supports the non-mover’s case — but in the light and with all reasonable inferences most favorable to the party opposed to the motion. If the facts and inferences point so strongly and overwhelmingly in [97]*97favor of one party that the Court believes that reasonable men could not arrive at a contrary verdict, granting of the motions is proper. On the other hand, if there is substantial evidence opposed to the motions, that is, evidence of such quality and weight that reasonable and fair-minded men in the exercise of impartial judgment might reach different conclusions, the motions should be denied, and the case submitted to the jury.

This standard has been confirmed as recently as Brown v. Bullard Indep. School Dist., 640 F.2d 651 (5th Cir. 1981).

It is also established that a lower court’s denial of the motion for a new trial should be tested by an “abuse of discretion” standard. Croce v. Bromley Corp., 623 F.2d 1084 (5th Cir. 1980); Conway v. Chemical Leaman Tank Lines, Inc., 610 F.2d 360 (5th Cir. 1980).

A review of this record reveals clearly that there is substantial evidence supporting plaintiffs’ contentions and that this evidence is of such quality and weight that reasonable and fair-minded persons in the exercise of impartial judgment could properly draw the conclusions reached by the jury. Ellis was killed by a large heavy timber which fell on him. The timber had no utilitarian value at all. It had simply been left by its owner, Chevron, on its platform from an earlier installation. There had been no attempt to stabilize it or tie it down or safeguard those who might be hurt by its falling. Further, it was caused to fall by being brushed by the cable of a proper block and tackle or pulley system being used for a proper purpose by its contractor. The record also reveals that Chevron knew that the timber remained there and knew that these workmen of Houma Welding would be working right by it. There simply is no foundation at all to disturb the jury verdict finding Chevron negligent in this case.

Chevron further claims that the deceased was guilty of contributory negligence or had assumed the risk. The record cannot establish one way or the other the extent to which the deceased had knowledge of the loose heavy piece of timber. It obviously was not part of his work or what he was supposed to deal with and yet it was nearby. It cannot be said that the failure to find negligence on his part was in error on the ground he should have been more aware of the surroundings, where he did not normally work, and in an environment which was strange to him and most familiar to defendant Chevron. The same factors militate against finding an assumption of risk by him which would justify upsetting the verdict of the jury.

Appellant also contends that it cannot be held liable for the acts or omissions of an independent contractor, in this case decedent’s employer, Houma Welding. It relies upon McCormack v. Noble Drilling Corp.,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

First United v. Church Mutual Ins
119 F.4th 417 (Fifth Circuit, 2024)
Gabarick v. Laurin Maritime (America), Inc.
900 F. Supp. 2d 669 (E.D. Louisiana, 2012)
Gary George v. Nabors International, Inc.
464 F. App'x 298 (Fifth Circuit, 2012)
Iglesias v. Chevron U.S.A. Inc.
656 F. Supp. 2d 598 (E.D. Louisiana, 2009)
Garcia v. Pfizer Inc.
268 F. App'x 270 (Fifth Circuit, 2008)
Graham v. Amoco Oil Co.
21 F.3d 643 (Fifth Circuit, 1994)
Heller International Corporation v. Alec Sharp
974 F.2d 850 (Seventh Circuit, 1992)
Heller International Corp. v. Sharp
974 F.2d 850 (Seventh Circuit, 1992)
Bank of San Antonio v. Swift (In Re Swift)
126 B.R. 725 (W.D. Texas, 1991)
Robinson v. Bump
894 F.2d 758 (Fifth Circuit, 1990)
Morgan v. Monessen Southwestern Railway Co.
518 A.2d 1171 (Supreme Court of Pennsylvania, 1986)
Tidelands Royalty "B" Corp. v. Gulf Oil Corp.
611 F. Supp. 795 (N.D. Texas, 1985)
McNeese v. Reading & Bates Drilling Co.
749 F.2d 270 (Fifth Circuit, 1985)
Mcneese v. Reading And Bates Drilling Company
749 F.2d 270 (Fifth Circuit, 1985)
Camplese v. Consolidated Rail Corp.
594 F. Supp. 44 (M.D. Pennsylvania, 1984)

Cite This Page — Counsel Stack

Bluebook (online)
650 F.2d 94, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ellis-v-chevron-u-s-a-inc-ca5-1981.