Eller Bros., Inc. v. Home Federal Savings & Loan Ass'n of Nashville

623 S.W.2d 624, 1981 Tenn. App. LEXIS 551
CourtCourt of Appeals of Tennessee
DecidedMarch 2, 1981
StatusPublished
Cited by10 cases

This text of 623 S.W.2d 624 (Eller Bros., Inc. v. Home Federal Savings & Loan Ass'n of Nashville) is published on Counsel Stack Legal Research, covering Court of Appeals of Tennessee primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Eller Bros., Inc. v. Home Federal Savings & Loan Ass'n of Nashville, 623 S.W.2d 624, 1981 Tenn. App. LEXIS 551 (Tenn. Ct. App. 1981).

Opinion

MATHERNE, Judge.

The plaintiff (Eller) sues for the balance due for work and material furnished in the completion of certain improvements on the property of the defendant (Home Federal). By counterclaim Home Federal seeks credit for certain amounts paid by it to other parties for the completion of portions of the contract work and, also, $500 per day liquidated damages allowed by the contract for each day beyond the date the work by Eller was to have been completed.

The chancellor found that under the contract Home Federal owed Eller $37,155, which figure is not disputed in this court. The chancellor further found that Eller did not complete the contract for 40 days beyond the contract completion date, and allowed Home Federal a set-off of $500 per day liquidated damages, or $20,000. The chancellor also allowed Home Federal an additional $500 expended due to a faulty blow-off valve installed by Eller. These set-offs resulted in a $16,655 judgment for Eller.

Eller appeals, insisting that (1) the chancellor erred in awarding $500 per day liquidated damages when Home Federal’s proof established its actual damage to be a much lower figure, and (2) Home Federal is es-topped to rely upon the liquidated damages provision due to its commission of certain acts during the contract period.

I.

Home Federal did not formally perfect an appeal, but by brief it seeks affirmative relief under three issues for review. Home Federal’s argument is that the contract was not completed until August 21, 1978, and that if its actual damages are computed to that date, it would still be entitled to the $20,000 delay damages. Home Federal’s position is that should this court hold that the $500 per day liquidated damages can not be enforced, its actual damages would justify the $20,000 delay damages award.

By brief in this court, Eller argues that Home Federal, not having appealed, can not now assert its affirmative claim as above outlined. We disagree with that argument.

Rule 27(b) T.R.A.P. provides as follows: If appellee is also requesting relief from the judgment, the brief of the appellee shall contain the issues and arguments involved in his request for relief as well as the answer to the brief of the appellant.

The relief sought by Home Federal involves mixed questions of law and fact. Rule 13(a) T.R.A.P. governs the raising of questions of law on appeal, as follows:

Except as otherwise provided by Rule 3(e) any question of law may be brought up for review and relief by any party. Cross-Appeals, separate appeals and separate applications for permission to appeal are not required.

Rule 13(d) T.R.A.P. governs the scope of review of findings of fact in civil non jury lawsuits, as follows:

Unless otherwise required by statute, review of findings of fact by the trial court in civil actions shall be de novo upon the record of the trial court, accompanied by a presumption of the correctness of the finding, unless the preponderance of the evidence is otherwise.

We, therefore, hold that Home Federal may on appeal assert its claim for affirmative relief as herein noted.

II.

The pertinent provisions of the contract provide, as follows:

The undersigned proposes to furnish all materials and perform all labor necessary to complete the following: On Rolling River Estates, Phase II shown on the plat prepared by James L. Murphy, Jr., Co. Consulting Engineers dated July 1, 1977: to grade roads, install drainage system water mains and complete sanitary sewer system and to put down six inch stone base on roads. Said work to be done in *626 accordance with plans and specifications prepared by James L. Murphy, Jr. & Co. Consulting Engineers dated July 1, 1977, a copy of which is attached and made a part hereof, and to meet the requirements of Metropolitan Department of Public Works on roads, and Harpeth Valley Utility District on water and sewer system.
The above described work is to be completed on or before December 23, 1977. If the undersigned is delayed by bad weather conditions more than 60 days beyond December 23,1977 the owner will incur liquidated damages in the amount of $500.00 per day beginning February 24, 1978, and continuing until all work described above other than paving is completed, which liquidated damages the contractor will pay to Home Federal without demand. (Tr. Vol. V 452).
******
Final payment shall be made within sixty (60) days after the completion and acceptance has been given to a particular section by the Metropolitan Public Works Department (Roadway and Drainage). Harpeth Valley Utility District (Water and Sewers); FHA inspection has been obtained and the approval of the Engineer and Owner. The contractor shall be responsible for getting these inspections made and supplying the Owner with letters so stating these approvals. (Tr. Vol. V 460).

Home Federal had previously financed the development of Rolling River Estates, but it had to foreclose on that property. A part of the property had been developed to the extent that lots could be sold and residences constructed. The parties refer to that area of the development as Rolling River Estates, Phase I. As the sale of lots progressed in Phase I, Home Federal decided that the remainder of the property should also be developed to the extent that residences could be built. The contract under consideration was to develop that additional area as specified therein, which area was designated Rolling River Estates, Phase II.

Ellis began work in August 1977. There is an abundance of proof that the weather during the winter of 1977-78 was severe and that this weather delayed Eller’s completion of the contract for a period beyond the 60 days the contract allowed for such delay. For that reason, Eller claims he should be excused from failure to meet the contract completion date. We disagree with that insistence and agree with the chancellor that bad weather was taken into consideration by the parties, and 60 days were allowed for delay caused thereby. If bad weather caused a delay of over 60 days, Eller is responsible for damages due to the excessive delay.

III.

The first issue to be settled is the date the contract was completed. The chancellor found that the water and sewer portion of the contract was completed on December 16, 1977, when the system was tied-in with the system of the Harpeth Valley Utility District (Utility District). The chancellor further found that the road portion of the contract was completed on April 4, 1978, which he held to be the date the contract was completed. Home Federal insists that the contract was not completed until August 21, 1978, the date the water and sewer systems were “accepted” by the Utility District.

In December 1977 the Utility District had a Mr. K'ennie as the inspector on the job. Kennie and Eller reached an agreement that the Phase II water and sewer systems would be tied-in with the system of the Utility District on December 16, 1977. After this was done, the Utility District placed a Mr. Eades on the job as its inspector. Eades made out a punch list of items to be corrected by Eller.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Tina Marie Hodge v. Chadwick Craig
382 S.W.3d 325 (Tennessee Supreme Court, 2012)
Guiliano v. Cleo, Inc.
995 S.W.2d 88 (Tennessee Supreme Court, 1999)
Guliano v. Cleo
Tennessee Supreme Court, 1999
Kimbrough & Co. v. Schmitt
939 S.W.2d 105 (Court of Appeals of Tennessee, 1996)
Beasley v. Horrell
864 S.W.2d 45 (Court of Appeals of Tennessee, 1993)
Harmon v. Eggers
699 S.W.2d 159 (Court of Appeals of Tennessee, 1985)
Glover v. Hardeman County
713 S.W.2d 73 (Court of Appeals of Tennessee, 1985)
State v. Valentine
659 S.W.2d 27 (Court of Criminal Appeals of Tennessee, 1983)

Cite This Page — Counsel Stack

Bluebook (online)
623 S.W.2d 624, 1981 Tenn. App. LEXIS 551, Counsel Stack Legal Research, https://law.counselstack.com/opinion/eller-bros-inc-v-home-federal-savings-loan-assn-of-nashville-tennctapp-1981.