Elite Concepts, Inc. v. David Field and Bria Field

CourtCourt of Appeals of Texas
DecidedJune 4, 2026
Docket15-25-00050-CV
StatusPublished

This text of Elite Concepts, Inc. v. David Field and Bria Field (Elite Concepts, Inc. v. David Field and Bria Field) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Elite Concepts, Inc. v. David Field and Bria Field, (Tex. Ct. App. 2026).

Opinion

Affirmed and Memorandum Opinion filed June 4, 2026.

In The

Fifteenth Court of Appeals

NO. 15-25-00050-CV

ELITE CONCEPTS, INC., Appellant

V.

DAVID FIELD AND BRIA FIELD, Appellees

On Appeal from the 471st Judicial District Court Collin County, Texas Trial Court Cause No. 471-05833-2022

MEMORANDUM OPINION

In this dispute over a residential pool construction project, Elite Concepts, Inc. appeals from a final judgment awarding damages to David and Bria Field and failing to award it attorneys’ fees. We hold that the parties’ contract did not exclude remedial damages, that sufficient evidence supports the award of those damages, and that Elite was not entitled to attorneys’ fees. We affirm.

BACKGROUND Bria and David Field were planning to build a custom home when they met Mike Nantz, a contractor with 36 years’ experience in the pool industry and the owner of Elite Concepts, Inc. Nantz prepared a rendering of a pool for the Fields, and later a detailed proposal and construction contract, which the Fields and Elite (by Nantz) signed in June 2021. Among other provisions, the construction contract listed a payment plan for the $222,144 price consisting of a down payment followed by four payments at or after certain points of the project.1 The contract provided that “Contractor’s liability and Buyer’s sole and exclusive remedy are limited to repair of the swimming pool.”2 The contract also provided that if suit was brought “for the purpose of determining or enforcing the rights of either party hereunder, the party prevailing in such action or proceedings shall be entitled to recover from the other party all costs and expenses incurred by the prevailing party, including reasonable attorney’s fees.” Construction began in August 2021 and proceeded much like any other. Some work had to be redone, there were delays (some due to the weather), and there were changes to the plans as construction progressed that added to the overall cost of the project. For example, the Fields requested that the pool be moved 24-30 inches immediately after the hole was dug; they made a number of upgrades, including to the pool tile, the pavers and underlayment for the deck surrounding the pool, and the built-in swim system; and they requested other changes, including to the fire pit. Nantz discussed the additional costs with the Fields, made the upgrades and changes, and submitted three change orders reflecting the costs.

1 Specifically, a $22,000 down payment, three payments of $60,043.20, and a final payment of $20,014.40. 2 In the very next sentence, the contract says, “In no event will Contractor be liable for any damages, including without limitation, incidental and consequential damages and damages for lost profits or inability to use the swimming pool, even if Contractor has been advised of such possibility.” Despite the broad “any damages” language, Elite acknowledges that the contract permits recovery of at least “the cost to remedy or repair the pool.”

2 A payment dispute brought the project to a halt about a year after it began. In addition to the down payment, the Fields made the next three payments of $60,043.20 as contemplated by the contract. But of the three change orders, they paid only the first. After Nantz requested payment of the second change order ($51,412.48), and the Fields assured him they would pay but did not, Elite “walked the job” and repossessed some pool equipment.3 When Elite left the job, the Fields owed $61,114.98 for the second and third change orders.4 The Fields also did not make the final payment under the contract of $20,014.40 because it had not yet come due (“at plaster”). The Fields paid a different contractor $81,199.57 to complete the pool—almost exactly the amount they had agreed to pay Elite upon completion but did not. The Fields sued Elite and Nantz for breach of contract and other theories seeking damages and attorneys’ fees. Elite and Nantz counterclaimed for breach of contract and quantum meruit and also sought attorneys’ fees. Trial was to the bench at which the Fields, Nantz, and an expert for each side testified. The trial court later signed a final judgment that contained the following findings, among others: • Elite “breached the contract by stopping work for non-payment of change orders, which were outside the contract”; • the Fields’ “cost to complete the pool was $68,000.00”; • the Fields “were damaged by [Elite’s] breach, for the cost of completion of the pool, in the amount of $68,000.00, pursuant to their claim for Breach of Contract”; • the Fields “requested, and received additions and upgrades to the pool project, for which they knew [Elite] expected to be paid, in the amount of $61,114.98”;

3 Nantz learned that David had contacted some of his suppliers, which gave Nantz the impression that David “was trying to work around [Nantz] and not pay [him] what was due.” 4 Elite filed a lien against the Field’s property pursuant to Article XVI, § 37 of the Texas Constitution in the same amount.

3 • Elite “was damaged by the [Fields’] failure to pay for the change orders, which were outside the contract, in the amount of $61,114.98, pursuant to its claim for Quantum Meruit”; and • the “Parties stipulated, and the Court finds, that the reasonable and necessary attorneys fees incurred by each party … is $75,000.00 per side” plus appellate attorneys’ fees.5 The trial court ordered that the Fields “shall have judgment against Elite Concepts” and awarded the Fields $6,885.02 and attorneys’ fees in amounts stipulated.6 The trial court ordered that Elite “take[] nothing.” Elite filed a motion to modify, overruled by operation of law, arguing that it too was entitled to attorneys’ fees as a prevailing party on its quantum meruit claim. After Elite appealed to the Fifth Court of Appeals, the appeal was transferred to this Court pursuant to a docket equalization order issued by the Texas Supreme Court under Chapter 73 of the Government Code.7

DISCUSSION Elite challenges the award of damages to the Fields and the failure to award it attorneys’ fees. We address each in turn.

I. The Fields’ Damages A. Damages under the construction contract Elite first argues that the Fields were not entitled to recover damages for the cost to complete the pool because the construction contract limited their damages to

5 Although findings “must not be recited in a judgment,” TEX. R. CIV. P. 299a, neither side objected to their inclusion in the judgment, nor are there any separately filed findings. 6 The trial court also rendered judgment for Nantz individually, since he signed the construction contract on behalf of Elite. 7 The parties filed a joint agreed motion to supplement the record with the preadmitted exhibits from the bench trial. We grant the motion. See TEX. R. APP. P. 34.6(d).

4 the cost to repair the pool, and there was no evidence of any such amounts.8 It is well settled that remedial damages is the proper measure of damages for breach of a construction contract when there has been substantial performance.9 “Once a construction project has been substantially completed, the damages for errors or defects in construction is the cost of completing the job or of remedying those defects that are remediable without impairing the building as a whole.”10 The standard is often stated in the disjunctive—“cost to complete or repair”—not because completion and repair are two different measures of damages, but because they are different types of remedial costs when construction is substantially complete.11 As the terminology suggests, one is based on the owner’s cost to complete work that was not done (“omissions”), whereas the other is based on the cost to repair work that was done but done incorrectly (“repairs”).12 Courts have occasionally referred to remedial damages as only one or the other of these measures,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Evanston Insurance Co. v. ATOFINA Petrochemicals, Inc.
256 S.W.3d 660 (Texas Supreme Court, 2008)
In Re 24R, Inc.
324 S.W.3d 564 (Texas Supreme Court, 2010)
Young v. Neatherlin
102 S.W.3d 415 (Court of Appeals of Texas, 2003)
Jernigan v. Langley
111 S.W.3d 153 (Texas Supreme Court, 2003)
Portland Gasoline Co. v. Superior Marketing Co.
243 S.W.2d 823 (Texas Supreme Court, 1951)
Green International, Inc. v. Solis
951 S.W.2d 384 (Texas Supreme Court, 1997)
Graham Central Station, Inc. v. Jesus Peña
442 S.W.3d 261 (Texas Supreme Court, 2014)
Wayne Ventling v. Patricia M. Johnson
466 S.W.3d 143 (Texas Supreme Court, 2015)
McGinty v. Hennen
372 S.W.3d 625 (Texas Supreme Court, 2012)
Ashford Partners, Ltd. v. Eco Resources, Inc.
401 S.W.3d 35 (Texas Supreme Court, 2012)

Cite This Page — Counsel Stack

Bluebook (online)
Elite Concepts, Inc. v. David Field and Bria Field, Counsel Stack Legal Research, https://law.counselstack.com/opinion/elite-concepts-inc-v-david-field-and-bria-field-texapp-2026.