ELG Utica Alloys, Inc. v. Niagara Mohawk Power Corp.

CourtCourt of Appeals for the Second Circuit
DecidedJuly 17, 2025
Docket23-7575
StatusPublished

This text of ELG Utica Alloys, Inc. v. Niagara Mohawk Power Corp. (ELG Utica Alloys, Inc. v. Niagara Mohawk Power Corp.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Second Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
ELG Utica Alloys, Inc. v. Niagara Mohawk Power Corp., (2d Cir. 2025).

Opinion

23-7575 ELG Utica Alloys, Inc. v. Niagara Mohawk Power Corp.

1 In the 2 United States Court of Appeals 3 For the Second Circuit 4 5 6 August Term 2024 7 8 No. 23-7575 9 10 ELG UTICA ALLOYS, INC., 11 12 Plaintiff-Counter 13 Defendant-Appellant, 14 15 v. 16 17 NIAGARA MOHAWK POWER CORP., DBA NATIONAL GRID, 18 19 Defendant-Counter 20 Claimant-Third Party 21 Plaintiff-Cross Claimant- 22 Cross Defendant-Appellee, 23 24 SPECIAL METALS CORP., EMPIRE RECYCLING CORP., 25 26 Defendants-Cross 27 Defendants-Appellees, 28 29 GENERAL ELECTRIC COMPANY, 30 31 Defendant-Cross 32 Defendant-Cross 33 Claimant-Appellee, 34 35 CHICAGO PNEUMATIC TOOL COMPANY, LLC, 1 2 Defendant-Cross 3 Defendant-Cross 4 Claimant-Counter 5 Claimant-Appellee, 6 7 NATIONAL GRID GROUP PLC, 8 9 Defendant, 10 v. 11 12 CBS CORPORATION (successor-in-interest to Westinghouse Electric 13 Corporation) AKA PARAMOUNT GLOBAL, 14 15 Third-Party Defendant- 16 Cross Defendant-Appellee. 17 18 19 20 Appeal from the United States District Court 21 for the Northern District of New York 22 No. 16-cv-1523, Brenda K. Sannes, Chief District Judge, Presiding. 23 (Argued February 6, 2025; Decided July 17, 2025) 24 25 26 Before: PARKER, BIANCO, and NARDINI, Circuit Judges. 27 28 ELG Utica Alloys, Inc. (“ELG”) sued Defendants-Appellees, a group of its 29 former customers, in the United States District Court for the Northern District of 30 New York, asserting claims under the Comprehensive Environmental Response, 31 Compensation, and Liability Act (“CERCLA”). ELG remediated contamination at 32 one portion of a 23-acre facility in 2007, and pursuant to a 2015 consent order with 33 the New York State government, continues to remediate contamination at a 34 different portion of the facility. ELG seeks contribution for the costs of the 2015 35 cleanup from the Appellees, which ELG alleges are also responsible for the 36 contamination. Appellees moved for summary judgment, arguing that the six-

2 1 year statute of limitations applicable to certain CERCLA claims had elapsed. The 2 District Court (Sannes, C.J.) granted the motion, reasoning that, even though ELG 3 seeks costs only from 2015 onwards, the remediation began in 2007, and the 2015 4 work was a subsequent step in the work that commenced in 2007. Because the 5 2015 cleanup was part of the 2007 remediation, the District Court concluded that 6 the statute of limitations started to run in 2007 and elapsed in 2013, which was 7 before ELG sued. The District Court also imposed spoliation sanctions on ELG for 8 shredding over 23,000 pounds of potentially relevant documents. 9 We agree with the District Court that the statute of limitations on ELG’s 10 claims commenced once on-site physical remediation began in 2007. We also see 11 no error in the District Court’s imposition of spoliation sanctions. Accordingly, 12 we AFFIRM the judgment of the District Court and REMAND to the District Court 13 to order the agreed-upon spoliation sanction. 14 15 PETER T. STINSON, Steven W. Zoffer, Brett W. Farrar, Dickie, 16 McCamey & Chilcote, P.C., Pittsburgh, PA, and David L. Cook, 17 Phillips Lytle LLP, Rochester, NY, for Plaintiff-Counter 18 Defendant-Appellant ELG Utica Alloys, Inc. 19 20 KRISTIN C. ROWE, Dean S. Sommer, Young/Sommer LLC, 21 Albany, NY, for Defendant-Cross Defendant-Cross Claimant- 22 Appellee General Electric Company. 23 24 Yvonne E. Hennessy, Barclay Damon LLP, Albany, NY, for 25 Defendant-Counter Claimant-Third Party Plaintiff-Cross 26 Claimant-Cross Defendant-Appellee Niagara Mohawk Power 27 Corp., DBA National Grid. 28 29 James D. Mazzocco, Marc Felezzola, Babst Calland Clements 30 & Zomnir, P.C., Pittsburgh, PA, for Third-Party Defendant- 31 Cross Defendant-Appellee CBS Corporation. 32 33 Gary S. Bowitch, Castleton, NY, for Defendant-Cross 34 Defendant-Appellee Empire Recycling Corp. 35

3 1 MARY L. D’AGOSTINO, Doreen A. Simmons, Hancock 2 Estabrook LLP, Syracuse, NY, for Defendant-Cross Defendant- 3 Appellee Special Metals Corp. 4 5 Agnieszka Antonian, Connell Foley LLP, New York, NY, for 6 Defendant-Cross Defendant-Cross Claimant-Counter 7 Claimant-Appellee Chicago Pneumatic Tool Company, LLC. 8 9 BARRINGTON D. PARKER, Circuit Judge:

10 Appellant ELG Utica Alloys, Inc. (“ELG”) sued Appellees, a group of its

11 former customers, in 2016 in the United States District Court for the Northern

12 District of New York, asserting claims under the Comprehensive Environmental

13 Response, Compensation, and Liability Act (“CERCLA”). 42 U.S.C. §§ 9601 et seq.

14 ELG’s predecessor companies had conducted scrap-metal recycling operations on

15 a 23-acre facility in Utica, New York, which released hazardous chemicals that

16 contaminated soil and groundwater at the site and in nearby areas. ELG

17 remediated the contamination at one portion of the facility in 2007, and pursuant

18 to a 2015 consent order with the New York State government, continues to

19 remediate contamination at a different portion of the site. ELG seeks contribution

20 for the costs of the 2015 cleanup from parties who allegedly shared responsibility

21 for the contamination: Appellees Niagara Mohawk Power Corporation (“National

22 Grid”), Special Metals Corporation, Empire Recycling Corporation, General

4 1 Electric Company, and Chicago Pneumatic Tool Company. 1 Appellees moved for

2 summary judgment, arguing that the applicable six-year statute of limitations to

3 sue for contribution had elapsed.

4 The District Court (Sannes, C.J.) granted Appellees summary judgment,

5 agreeing that the limitations period had elapsed. The District Court reasoned that

6 even though ELG seeks costs only from 2015 onwards, on-site remediation began

7 in 2007, and the 2015 work required by the consent order was a continuation of the

8 2007 remediation. Consequently, the District Court concluded that the statute of

9 limitations started to run in 2007 and elapsed in 2013—before ELG brought suit.

10 Further, ELG argued that the 2007 remediation occurred on a different facility than

11 the 2015 remediation, which, it contends, means the statute of limitations for the

12 2015 cleanup could not have started in 2007. But the District Court concluded that

13 both cleanups occurred on the same 23-acre facility (albeit different portions), and

14 therefore, the statute of limitations commenced in 2007. The District Court also

15 imposed spoliation sanctions on ELG for the shredding of over 23,000 pounds of

16 potentially relevant documents.

1 Appellee CBS Corporation was added to the case as a Third-Party Defendant/Cross Defendant in 2019. National Grid and Empire Recycling Corporation both asserted that, to the extent they may be held liable for cleanup costs at the facility, the CBS Corporation is responsible for a share of those costs.

5 1 We agree with the District Court that the statute of limitations on ELG’s

2 claims commenced once on-site remediation began in 2007. Accordingly, we

3 conclude that the applicable six-year limitations period elapsed in 2013, and ELG’s

4 contribution claim is time-barred. We also see no error in the District Court’s

5 imposition of spoliation sanctions.

6 BACKGROUND

7 I. Factual Background

8 A. The Contamination

9 Appellant ELG Utica Alloys, Inc. (“ELG”) is the successor to two companies

10 that conducted scrap-metal recycling operations on a 23-acre site in Utica, New

11 York: Utica Alloys, Inc. and Universal Waste, Inc. These two companies

12 coordinated recycling operations and were managed by the same corporate

13 officers before merging to become ELG.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
Sierra Club v. Seaboard Farms, Inc.
387 F.3d 1167 (Tenth Circuit, 2004)
Fujitsu Limited v. Federal Express Corporation
247 F.3d 423 (Second Circuit, 2001)
United States v. Moloney
685 F.3d 1 (First Circuit, 2012)
Niagara Mohawk Power Corp. v. Chevron U.S.A., Inc.
596 F.3d 112 (Second Circuit, 2010)
Axel Johnson, Inc. v. Carroll Carolina Oil Co.
191 F.3d 409 (Fourth Circuit, 1999)
Klipsch Group, Inc. v. ePRO E-Commerce Ltd.
880 F.3d 620 (Second Circuit, 2018)
United States v. Township of Brighton
153 F.3d 307 (Sixth Circuit, 1998)
West v. Goodyear Tire & Rubber Co.
167 F.3d 776 (Second Circuit, 1999)
Schaefer v. Town of Victor
457 F.3d 188 (Second Circuit, 2006)
Nurad, Inc. v. William E. Hooper & Sons Co.
966 F.2d 837 (Fourth Circuit, 1992)

Cite This Page — Counsel Stack

Bluebook (online)
ELG Utica Alloys, Inc. v. Niagara Mohawk Power Corp., Counsel Stack Legal Research, https://law.counselstack.com/opinion/elg-utica-alloys-inc-v-niagara-mohawk-power-corp-ca2-2025.