Eleuterio Fuentes v. San Anastacio Development Ltd., Oscar Corona, and Mauricio Gonzalez

CourtCourt of Appeals of Texas
DecidedJuly 29, 2010
Docket13-08-00743-CV
StatusPublished

This text of Eleuterio Fuentes v. San Anastacio Development Ltd., Oscar Corona, and Mauricio Gonzalez (Eleuterio Fuentes v. San Anastacio Development Ltd., Oscar Corona, and Mauricio Gonzalez) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Eleuterio Fuentes v. San Anastacio Development Ltd., Oscar Corona, and Mauricio Gonzalez, (Tex. Ct. App. 2010).

Opinion





NUMBER 13-08-00743-CV



COURT OF APPEALS



THIRTEENTH DISTRICT OF TEXAS



CORPUS CHRISTI
- EDINBURG



ELEUTERIO FUENTES, Appellant,

v.

SAN ANASTACIO DEVELOPMENT LTD.,

OSCAR CORONA, AND MAURICIO GONZALEZ, Appellees.

On appeal from the 398th District Court

of Hidalgo County, Texas.

MEMORANDUM OPINION



Before Chief Justice Valdez and Justices Garza and Benavides

Memorandum Opinion by Chief Justice Valdez



This appeal involves a dispute regarding a construction contract in which appellees, San Anastacio Development Ltd., Oscar Corona, and Mauricio Gonzalez (collectively referred to as "San Anastacio"), contracted with appellant, Eleuterio Fuentes, to construct a water distribution system, a sanitary sewer system, storm drainage, and paving and parking lot improvements at a subdivision being developed by Fuentes. After a jury trial, judgment was rendered in favor of San Anastacio. San Anastacio was awarded $89,300 in damages and $7,000 in attorney's fees. By four issues, Fuentes contends that the trial court erred by: (1) granting judgment for San Anastacio because the jury did not make a substantial performance finding; (2) rendering judgment for Cordova and Gonzalez because "these parties did not submit a damage question"; (3) granting judgment for San Anastacio because San Anastacio "failed to meet [a] condition precedent to payment"; and (4) awarding attorney's fees. We affirm.

I. Background

On November 2, 2004, San Anastacio and Fuentes entered into a construction contract in which San Anastacio contracted to construct a water distribution system, a sanitary sewer system, storm drainage, and paving and parking lot improvements on the Adams Crossing Subdivision for $212,000. The contract provided that San Anastacio would complete the project within fifty working days of receiving a "notice to proceed" from the City of Mission, Texas. The contract provided, in part, "The Owner [Fuentes] agrees to pay the Contractor [San Anastacio] in current funds for the performance of the contract, as provided in the proposal, and to make payments on account thereof." The contract also provided that San Anastacio's payment requests were to be processed through Fuentes's agent, engineer Jaime Enriquez.

On July 1, 2005, San Anastacio filed suit against Fuentes for breach of contract for failing to make payments on the agreement, and Fuentes counterclaimed that San Anastacio failed to perform its obligations under the contract. A jury trial commenced on May 13, 2008. At trial, Gonzalez testified that he owns San Anastacio Development Ltd. and that he and Corona, another contractor, entered into a joint venture to complete the construction project at the Adams Crossing Subdivision. Corona testified that he and Gonzalez began construction on the Adams Crossing project in mid-November 2005, and believed that they could complete the project within fifty working days of receiving the "notice to proceed" by combining their workforces.

Under the terms of the contract, San Anastacio submitted invoices to Enriquez for approval. Upon receiving the invoices, Enriquez verified that the materials represented in the invoices had been installed at the Adams Crossing Subdivision and then prepared a "certificate for payment" that was submitted to Fuentes for payment. Three certificates for payment were entered into evidence. The first certificate for payment was dated December 9, 2004, and requested payment of $61,664.85. The second certificate for payment was dated December 23, 2004, reflected that no payments had been made, and requested payment of $88,086.60. The third certificate for payment was dated January 21, 2005; it reflected a $61,664.85 payment by Fuentes, presumably in response to the December 9, 2004 request, and requested payment of $54,932.31. San Anastacio contends that it continued to perform work and incur expenses after the January 21, 2005 certificate for payment was prepared.

Fuentes testified that the contract did not require that he make any payment to San Anastacio before the completion of the Adams Crossing Project. However, Fuentes confirmed that he satisfied payment under the first certificate for payment but none thereafter. Fuentes testified that he ceased making payments because he learned that San Anastacio had failed to pay various subcontractors who had worked on the Adams Crossing project. Fuentes also testified that, after he paid the first certificate of payment, San Anastacio had twenty-one working days left under the contract to complete the project but performed little work. Fuentes stated that, after the fifty working days under the contract expired, he allowed San Anastacio to continue working on the project for two additional months before terminating the contract in March 2005. After terminating his contract with San Anastacio, Fuentes contracted with another construction company to complete the project for approximately $70,000.

Fuentes's testimony was hotly disputed by Corona and Gonzalez. According to Corona and Gonzalez, when the parties contracted with Fuentes, they were told to turn in their requests for payment on the 25th of each month and that they would be paid on the 10th of the following month. Moreover, Enriquez opined that a provision found within the contract required Fuentes to make payments as the work progressed in accordance with the work reflected in the certificates of payment. Corona admitted that San Anastacio was unable to complete the Adams Crossing project but insisted that its failure to complete the project resulted from Fuentes's failure to make the requested payments. Corona testified that Fuentes owes San Anastacio $37,000 for work performed under Corona's portion of the San Anastacio joint venture. Additionally, Gonzalez testified that Fuentes owes San Anastacio a total of $89,300 for work performed under the contract. Gonzalez stated that the $89,300 is comprised of $37,000 for work performed under Corona's portion of the joint venture, as well as $52,000 for work performed under Gonzalez's portion.

The jury found that both San Anastacio and Fuentes failed to comply with the November 2, 2004 contract. The jury awarded $89,300 to San Anastacio after it determined that Fuentes was the first to breach the contract and that his breach was not excused. The trial court entered a final judgment providing that San Anastacio evelopment Ltd., Oscar Corona, and Mauricio Gonzalez recover $89,300 in actual damages, pre- and post-judgment interest, attorney's fees, and court costs. Fuentes filed a "Motion for Judgment Notwithstanding the Verdict" and a "Motion for New Trial or in the Alternative Motion to Modify Final Judgment"; however, the trial court denied these motions. This appeal ensued.

II. Substantial Performance

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Mustang Pipeline Co. v. Driver Pipeline Co.
134 S.W.3d 195 (Texas Supreme Court, 2004)
Jones v. Kelley
614 S.W.2d 95 (Texas Supreme Court, 1981)
State Department of Highways & Public Transportation v. Payne
838 S.W.2d 235 (Texas Supreme Court, 1992)
Tips v. Hartland Developers, Inc.
961 S.W.2d 618 (Court of Appeals of Texas, 1998)
Lake LBJ Municipal Utility District v. Coulson
692 S.W.2d 897 (Court of Appeals of Texas, 1985)
Coulson v. Lake L.B.J. Municipal Utility District
734 S.W.2d 649 (Texas Supreme Court, 1987)
Mead v. Johnson Group, Inc.
615 S.W.2d 685 (Texas Supreme Court, 1981)
Vance v. My Apartment Steak House of San Antonio, Inc.
677 S.W.2d 480 (Texas Supreme Court, 1984)
In the Interest of B.L.D.
113 S.W.3d 340 (Texas Supreme Court, 2003)

Cite This Page — Counsel Stack

Bluebook (online)
Eleuterio Fuentes v. San Anastacio Development Ltd., Oscar Corona, and Mauricio Gonzalez, Counsel Stack Legal Research, https://law.counselstack.com/opinion/eleuterio-fuentes-v-san-anastacio-development-ltd--texapp-2010.