Electric Reliability Council of Texas, Inc. v. May (In Re Texas Commercial Energy)

607 F.3d 153, 2010 U.S. App. LEXIS 9775, 53 Bankr. Ct. Dec. (CRR) 46, 2010 WL 1930254
CourtCourt of Appeals for the Fifth Circuit
DecidedMay 13, 2010
Docket08-40890
StatusPublished
Cited by8 cases

This text of 607 F.3d 153 (Electric Reliability Council of Texas, Inc. v. May (In Re Texas Commercial Energy)) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fifth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Electric Reliability Council of Texas, Inc. v. May (In Re Texas Commercial Energy), 607 F.3d 153, 2010 U.S. App. LEXIS 9775, 53 Bankr. Ct. Dec. (CRR) 46, 2010 WL 1930254 (5th Cir. 2010).

Opinion

EDITH H. JONES, Chief Judge:

Leo Leonard May and Texas Commercial Energy (“TCE”) sued the Electric Reliability Council of Texas (“ERCOT”) for drawing down a letter of credit in violation of a bankruptcy court order and confirmed reorganization plan that allegedly prevented ERCOT from taking that action to satisfy pre-confirmation debts. The final judgment awarded contract damages and attorneys fees to the Appellees. ERCOT now appeals, asserting that it had the right to draw down the letter of credit to pay TCE’s post-confirmation debts. We agree, and accordingly REVERSE and RENDER the judgment in favor of May. 1

I. BACKGROUND

In 2002, Texas deregulated its energy markets. Customers could choose to purchase electricity from a variety of retail electric providers. Retail electric providers purchased electricity wholesale from ERCOT, the entity that manages the electric grid and market for electricity in the state. TCE, one of the first retail electricity providers, purchased electricity from ERCOT pursuant to a contract, the Qualified Scheduling Entity Agreement (the “QSE Agreement”). Electricity cannot be stored, so TCE purchased electricity on a daily basis. Because of volatility in both the price of electricity and the quantity of electricity demanded, TCE’s daily charges could vary considerably. To address this inherent volatility, the QSE Agreement required TCE to post standby letters of credit to guarantee payment. As a new company in a newly deregulated industry, however, TCE soon began to falter. In March 2003, due to large swings in the price of electricity, TCE was about to default on approximately $30 million in un *155 paid ERCOT invoices and filed for Chapter 11 bankruptcy.

TCE continued to operate while in bankruptcy. To continue purchasing electricity from ERCOT, TCE needed to assume the QSE Agreement. See generally 11 U.S.C. § 365. After negotiations, the bankruptcy court allowed TCE to assume the QSE Agreement subject to court-ordered modifications (the “September Order”). In pertinent part, the September Order implemented the contractual modifications, stating:

ORDERED that Debtor [TCE] is hereby authorized to assume the pre-petition Qualified Scheduling Entity Agreement with ERCOT, modified as follows:
1. Defendant ERCOT is prohibited from directly or indirectly ... (i) taking any further action to collect the [unpaid invoices] ..., (ii) drawing down any Letter of Credit securing the obligation represented by those invoices, (iii) otherwise taking any action to facilitate the collection or payment of those [unpaid invoices] and/or the obligation reflected therein, or (iv) the foreclosure of any collateral securing payment of those Invoices or the obligation reflected by them except as authorized by further order of this court.

The overall effect of the September Order was to prevent ERCOT from enforcing any rights in collateral to satisfy the unpaid invoices. ERCOT was permitted to maintain letters of credit to satisfy TCE’s post-petition obligations.

In December 2003, the bankruptcy court approved TCE’s reorganization plan (the “TCE Plan”). The TCE Plan took into account a $14.8 million unsecured obligation owed to ERCOT (the “Plan Debt”) largely based on the unpaid invoices. ER-COT’s claim, although unsecured, was singled out from other unsecured claims because of its size, complexity, and a pending lawsuit against ERCOT and its member electricity suppliers. In addition, the TCE Plan formally incorporated the September Order. After confirmation, TCE was again obliged to guarantee electricity purchases by posting security with ERCOT pursuant to the assumed QSE Agreement. Because TCE did not have the resources to post sufficient collateral, May, TCE’s principal, provided financing. On behalf of TCE, May posted a $900,000 standby letter of credit (the “LOC”), the subject of this dispute. 2 May personally purchased the LOC from Wells Fargo Bank through an intermediary, American National Bank.

After confirmation, TCE continued to struggle. It defaulted on the Plan Debt while remaining current on its post-petition invoices for electricity purchases. ERCOT decided to use the LOC to satisfy some of the Plan Debt. It sent a letter to TCE stating that the assumed QSE Agreement gave ERCOT the right to draw down the LOC to satisfy the Plan Debt. TCE responded that, pursuant to the TCE Plan, ERCOT could only draw down the LOC to *156 satisfy post-confirmation electricity purchases. Because TCE was current on the post-confirmation invoices, TCE believed that ERCOT could not draw on the LOC.

On March 31, 2005 ERCOT presented the proper documents to Wells Fargo, and Wells Fargo paid ERCOT pursuant to the LOC. Wells Fargo sought repayment from American National Bank, which then sought repayment from May. May then commenced this litigation in the bankruptcy court. To cover his guarantee obligations to American National Bank, May executed a promissory note (the “May Note”) and paid interest during the pen-dency of this litigation. TCE became a Chapter 7 debtor shortly afterward, and its Trustee was substituted for TCE as an additional plaintiff.

May initially sought an injunction to prevent ERCOT from drawing down the LOC under Tex. Bus. & Com.Code § 5.109(a). May asserted that ERCOT was committing a material fraud against him. 3 ERCOT had already drawn down the LOC, however, so the adversary proceeding was modified to determine, inter alia, whether ERCOT was entitled to retain the $900,000. 4 May argued that ER- *157 COT violated the LOC’s underlying contract (the QSE Agreement), the TCE Plan, and the September Order. He asserted that the QSE Agreement and TCE Plan allowed ERCOT to draw down the LOC only to satisfy post-confirmation electricity purchases, not the Plan Debt. In its first ruling, the bankruptcy court held that ER-COT breached the standby LOC agreement, interpreted in light of the TCE Plan. The court awarded May $900,000 in contract damages, but did not award attorneys fees.

Both parties appealed to the district court. The district court essentially affirmed the $900,000 judgment but for its decisional basis relied on ERCOT’s violation of the September Order. 5 The court remanded to evaluate additional issues, including the Trustee’s claim.

On remand, the bankruptcy court reaffirmed its judgment based on the injunction-violation theory and awarded May contract damages of $900,000 to satisfy the May Note; $169,422.20 in interest paid during litigation; and prejudgment interest on the total award in the sum of $178,256.53. In addition, it held ERCOT in contempt for violating a court order (the TCE Plan) and awarded May attorneys fees. The district court reaffirmed the judgment. ERCOT now appeals to this court.

II. JURISDICTION

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Elec Reliability Council v. Phillips
101 F.4th 369 (Fifth Circuit, 2024)
In Re Fusion PM Holdings, Inc.
Second Circuit, 2023
Ogle v. Morgan
Fifth Circuit, 2022
Solferini v. Corradi USA
Fifth Circuit, 2021
Mandel v. Thrasher (In Re Mandel)
578 F. App'x 376 (Fifth Circuit, 2014)

Cite This Page — Counsel Stack

Bluebook (online)
607 F.3d 153, 2010 U.S. App. LEXIS 9775, 53 Bankr. Ct. Dec. (CRR) 46, 2010 WL 1930254, Counsel Stack Legal Research, https://law.counselstack.com/opinion/electric-reliability-council-of-texas-inc-v-may-in-re-texas-commercial-ca5-2010.