El Dorado Amonia, LLC v. Global Industrial, Inc.

2023 Ark. App. 455, 677 S.W.3d 812
CourtCourt of Appeals of Arkansas
DecidedOctober 18, 2023
StatusPublished

This text of 2023 Ark. App. 455 (El Dorado Amonia, LLC v. Global Industrial, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Arkansas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
El Dorado Amonia, LLC v. Global Industrial, Inc., 2023 Ark. App. 455, 677 S.W.3d 812 (Ark. Ct. App. 2023).

Opinion

Cite as 2023 Ark. App. 455 ARKANSAS COURT OF APPEALS DIVISION IV No. CV-20-692

EL DORADO AMMONIA, LLC, AND EL Opinion Delivered October 18, 2023 DORADO CHEMICAL COMPANY APPEAL FROM THE UNION APPELLANTS/CROSS-APPELLEES COUNTY CIRCUIT COURT [NO. 70CV-16-76] V. HONORABLE DAVID F. GUTHRIE, GLOBAL INDUSTRIAL, INC. JUDGE APPELLEE/CROSS-APPELLANT REVERSED AND REMANDED

RITA W. GRUBER, Judge

El Dorado Ammonia, LLC, and El Dorado Chemical Company filed an interlocutory

appeal of the April 23, 2020 “Amended Judgment I” of the Union County Circuit Court,

and Global Industrial, Inc., cross-appeals. The parties raise multiple points on appeal, but

only two of those points are dispositive: (1) whether the materialmen’s lien filed by Global

was perfected; and (2) whether the circuit court’s reference to damages for “unpaid invoices”

is a judgment that is collectible through remedies other than the materialmen’s lien. We

reverse and remand.

I. Factual and Procedural Background

A. Project History In its simplest terms, this is a case about a subcontractor attempting to get paid for

work it performed during the construction of an ammonia plant.

El Dorado Chemical Company (“EDCC”) owns a chemical plant in Union County,

Arkansas, that suffered an explosion in 2012. EDCC’s parent company created El Dorado

Ammonia (“EDA”) to own and operate an ammonia facility that would be constructed at

the plant after the explosion. For purposes of this opinion, EDCC and EDA have the same

interests and make the same arguments, so they will be referred to collectively as “El Dorado

Chemical.” Although the parent company was originally a party to this lawsuit, it was

dismissed voluntarily in 2018.

In 2013, EDA engaged Leidos Constructors, LLC (“Leidos”), to be the general

contractor on a project during which an ammonia plant in Louisiana would be dismantled,

and the salvage from that plant would be used in constructing the ammonia facility in Union

County (the “Project”). Leidos hired Global Industrial, Inc. (“Global”), to be a subcontractor

for the Project. Through three subcontracts, Leidos engaged Global in 2014 to perform both

salvage and reconstruction work during the Project. Global agreed to perform its work on a

time-and-materials basis. Through an additional subcontract, Leidos also engaged Global to

perform repair work on other parts of the chemical plant after the explosion. Global agreed

to perform this work in exchange for a lump sum. There was no contract between Global

and EDA or EDCC for any work that Global performed.

On July 1, 2015, Leidos issued a written notice of termination to Global. At the time

of termination, Global had already submitted invoices totaling $9,068,754.43. After

2 termination, Global submitted additional invoices, and the total of all unpaid invoices was

$12,426,140.68. Also after the termination, Leidos and El Dorado Chemical hired

replacement subcontractors to cure nonconforming work and to complete the Project. In

November 2015, Leidos issued a $9,977,357 back charge against Global’s outstanding

invoices. Of this amount, $4,914,850 represented costs to cure Global’s alleged

nonconforming work, and the remaining $5,062,507 was for “inefficiency and project

impact costs.”

B. Materialmen’s Lien History

On September 29, 2015, Global recorded a materialmen’s lien in the amount of

$12,426,140.68. The lien stated:

The real property which is charged with this lien is a portion of the property described on Exhibit A attached hereto and incorporated herein by this reference. Such property is commonly known as the El Dorado Chemical Plant, and such plant is located at the following address: 4500 N. West Avenue, El Dorado, AR 71730.

Exhibit A was a property description for the entirety of the property owned by EDCC at that

address, which includes hundreds of acres and many buildings. Global also included as

exhibits two overhead shots from Google Images showing the property and claimed exhibit

B-2 “is a more detailed/closer aerial photograph depicting the general location in which the

labor was furnished and materials provided.” Exhibit B-2 is an aerial photograph that

includes many structures and buildings with text added that says, “Plant area where Global

Industrial, Inc. provided labor and materials.”

3 After the original materialmen’s lien was filed, Leidos paid Global for the difference

between the amount invoiced and the amount of the back charge. Global then amended its

materialmen’s lien on February 23, 2016. The first amended lien was in the amount of

$8,772,815.69. The amended lien did not describe the property on which work was

performed with any further specificity. On February 26, 2016, Global filed a lis pendens that

covered all property owned by EDCC in Union County. More than a year later, on May 30,

2017, Global filed its second amended materialmen’s lien that included a metes and bounds

description of precisely where on EDCC’s property Global had performed work. On

November 14, 2018, during trial, Global filed an amended lis pendens to include only the

property identified in the second amended materialmen’s lien and released the remaining

previously identified portion of EDCC’s property from the lien claim.

C. Procedural History

Global filed its complaint against Leidos, EDA, EDCC, and other defendants on

February 26, 2016, alleging breach of contract, foreclosure, and negligence. On December

28, 2017, Global filed its second amended complaint against Leidos, EDA, EDCC, and

others. This is the operative complaint in the lawsuit. On January 12, 2018, Leidos filed a

counterclaim against Global for breach of contract. At various points during the litigation,

other parties filed claims, counterclaims, cross-claims, and third-party claims.

On September 24, 2018, the circuit court entered an order bifurcating all cross-

claims, Leidos’s counter cross-claims against EDA and EDCC, Leidos’s counter cross-claims

against EDCC’s parent company, and the third-party claims. In other words, all claims by

4 and directly against Global were to be tried in “Phase I,” while all other matters would be

heard in “Phase II.” In its bifurcation order, the circuit court also stated that the parties were

“free to assert at trial any and all defenses that relate to the claims by Global and the

counterclaim by Leidos against Global.”

Phase I was a four-week bench trial from October 22 through November 14, 2018,

during which Global’s five surviving causes of action were litigated: (1) breach of contract

against Leidos; (2) breach of contract against EDA; (3) lien foreclosure against Leidos; (4)

lien foreclosure against EDCC; and (5) lien foreclosure against EDA, as well as the

counterclaims asserted by Leidos against Global. During trial, Global presented evidence of

unpaid invoices totaling $9,068,754.43. Leidos presented evidence of $10,080,849 in charge

backs. At the end of trial, Global moved to conform the pleadings to the evidence, which

added claims for intentional interference with a contract against EDA and EDCC.

On March 12, 2020, the circuit court entered Judgment I, disposing of all claims and

counterclaims tried in Phase I. In that order, the circuit court awarded judgment to Global

against EDA “on its derivative action for debt on [certain subcontracts] for the sum of

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Arkhola Sand & Gravel Co. v. Hutchinson
726 S.W.2d 674 (Supreme Court of Arkansas, 1987)
Wiggins v. SEARCY FEDERAL SAVINGS & LOAN ASS'N
486 S.W.2d 900 (Supreme Court of Arkansas, 1972)
Christy v. Nabholz Supply Co., Inc.
546 S.W.2d 425 (Supreme Court of Arkansas, 1977)
Servewell Plumbing, LLC v. Summit Contractors, Inc.
210 S.W.3d 101 (Supreme Court of Arkansas, 2005)
Burks v. Sims
321 S.W.2d 767 (Supreme Court of Arkansas, 1959)
Florida Oil Investment Group, LLC v. Goodwin & Goodwin, Inc.
2015 Ark. App. 209 (Court of Appeals of Arkansas, 2015)
Arkansas Foundry Co. v. American Portland Cement Co.
75 S.W.2d 387 (Supreme Court of Arkansas, 1934)
Whitener v. Purifoy
5 S.W.2d 724 (Supreme Court of Arkansas, 1928)
Rust v. Kelley Brothers' Lumber Co.
21 S.W.2d 973 (Supreme Court of Arkansas, 1929)
Dowty v. Riggs
2010 Ark. 465 (Supreme Court of Arkansas, 2010)
JMAC Farms, LLC v. G & C Generator, LLC
2017 Ark. App. 658 (Court of Appeals of Arkansas, 2017)
Anderson v. Seamans
49 Ark. 475 (Supreme Court of Arkansas, 1887)
Pfeiffer Stone Co. v. Brogdon
188 S.W. 1187 (Supreme Court of Arkansas, 1916)
Arkmo Lumber Co. v. Cantrell
252 S.W. 901 (Supreme Court of Arkansas, 1923)

Cite This Page — Counsel Stack

Bluebook (online)
2023 Ark. App. 455, 677 S.W.3d 812, Counsel Stack Legal Research, https://law.counselstack.com/opinion/el-dorado-amonia-llc-v-global-industrial-inc-arkctapp-2023.