Ekotek Site PRP Committee v. Self

1 F. Supp. 2d 1282, 28 Envtl. L. Rep. (Envtl. Law Inst.) 21, 46 ERC (BNA) 1614, 1998 U.S. Dist. LEXIS 5411
CourtDistrict Court, D. Utah
DecidedMarch 18, 1998
Docket94-277L
StatusPublished
Cited by15 cases

This text of 1 F. Supp. 2d 1282 (Ekotek Site PRP Committee v. Self) is published on Counsel Stack Legal Research, covering District Court, D. Utah primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ekotek Site PRP Committee v. Self, 1 F. Supp. 2d 1282, 28 Envtl. L. Rep. (Envtl. Law Inst.) 21, 46 ERC (BNA) 1614, 1998 U.S. Dist. LEXIS 5411 (D. Utah 1998).

Opinion

MEMORANDUM AND ORDER

LUNGSTRUM, District Judge.

Plaintiff The Ekotek Site PRP Committee (the Committee) brought this contribution action against a number of defendants pursuant to the federal Comprehensive Environmental Response, Compensation and Liability Act (CERCLA), 42 U.S.C. §§ 9601-9675, to recover a portion of its past and future costs incurred in cleaning up a site contaminated by hazardous substances. After a number of settlements and dismissals, only plaintiffs claim against defendant Morrison Knudsen Corporation (MK) remained for trial. Phase I of plaintiffs litigation against MK ended -on January 24, 1997, when MK consented to judgment with respect to its liability for response costs as a generator and an owner-operator. Phase II (damages) and phase III (allocation) issues with respect to MK were tried to the court in Salt Lake City, Utah, over 10 days from January 12 to January 23, 1998. This Memorandum and Order constitutes the court’s findings of fact and conclusions of law pursuant to Fed. R.Civ.P. 52(a).

After considering all of the evidence, as well as the arguments of counsel, the court concludes that the equitable allocation of response costs to MK should reflect MK’s relatively minimal contribution to contamination at the Ekotek Site, as more fully set forth below. Accordingly, the court apportions one (1) percent of all recoverable past and future response costs incurred by plaintiff to MK. Judgment is ordered in favor of plaintiff against MK in the amount of $179,638.84 for past costs and interest on those costs. In addition, a declaratory judgment is ordered in favor of plaintiff against MK, by which MK is deemed liable for one (1) percent of all future recoverable response costs incurred by plaintiff with respect to the Ekotek Site.

FINDINGS OF FACT

Site Background

This case involves the environmental cleanup of a contaminated site, known as the Ekotek Site (the Site), located at 1628 North Chicago Street in Salt Lake City, Utah. The Site is approximately 6.6 acres in area and is divided by railroad tracks into western and eastern parts that are roughly equal in area.

MK acquired the eastern half of the Site in pieces between 1929 and 1948. In 1975, MK conveyed all interest in the eastern half to Bonus International Corporation (Bonus) and vacated the premises.

From 1953 to 1968, O.C. Allen Oil Company (O.C.Allen) owned the western half of the Site and operated a used oil refinery there. In 1968, Flinco, Inc. purchased the western *1286 half. Flinco ran the refinery until 1978, during which time the company changed its name to Bonus. In 1975, Bonus consolidated the two sides of the Site. In 1978, Ekotek, Inc., a Delaware corporation (Ekotek of Delaware), owned the Site and operated the facility. In 1981, Steven Self and Steven Miller purchased the property and incorporated under the name Ekotek, Inc., a Utah corporation (Ekotek of Utah). This company operated the re-refining facility until 1987, when the company declared bankruptcy. Pe-troChem Recycling Corporation (PetroChem) then leased the property and operated the facility until February of 1988, when the State of Utah issued notices of violation and operations ceased.

Morrison Knudsen Operations

MK is a large construction company with its principal place of business in Idaho. From the 1940s through the 1970s, MK engaged in more than 100 construction projects in the Utah area, including the Great Salt Lake Causeway project in the late 1950s, which took approximately three years to complete.

MK operated a heavy equipment storage and maintenance facility (the yard) on the eastern portion of the Site from the late 1940s until 1975. Aerial photographs of the yard during that period generally show between 40 and 80 pieces of equipment present at the yard and an adjacent parcel at any one time, with more than 100 pieces present on two occasions. The photos also suggest that the yard was much less busy before 1958 than after.

The yard contained a number of buildings along its periphery, including warehouses, offices, storage sheds, and a paint shop. The buildings were generally situated along the southern and eastern edges of the yard. Repair and maintenance work was generally performed in the “old shop”, which contained only one or possibly two equipment bays, until approximately 1960, when the “new shop” was constructed at the north end of the yard. The new shop contained four or five equipment bays. The yard was served by a railroad spur, maintained by Union Pacific Raih’oad, that acted as the western boundary of the yard. The yard was also served by two concrete loading docks on the western side of the yard. An underground storage tank containing gasoline was located in the southeastern corner of the yard (UST # 1); another UST, which was actually a buried railroad tanker, sat in the southwestern part of the yard along the raih’oad tracks and contained virgin diesel fuel (UST # 2). In the early 1970s, MK kept some old railroad ties at the yard for use in bracing equipment during transport. The ties, which mainly lay in stacks around the railroad spur, had been treated against rotting.

Equipment usually arrived at the yard for repair on MK’s one low-boy truck; less frequently, equipment came by rail. The great majority of the equipment repaired at the yard was powered by diesel fuel. MK did not bring equipment to the yard merely for routine maintenance; minor repairs were made and oil and other fluids were changed in the field. There, waste oil would be dumped into a pit or fill area; it would then be covered or taken to a landfill. This practice was followed even at a project within one-half mile of the yard. Nor was equipment always returned to the yard between construction jobs in the area. MK brought equipment to the yard for significant repair work only, such as a major overhaul of a piece of equipment.

Only a small number of mechanics worked at the yard at any one time. Herbert Guk-eisen, the shop foreman at the yard from 1970 to 1975, testified that the number of mechanics varied from five to as many as 25 or 30 on one occasion. Harold Walker, a mechanic at the yard from 1957 to 1969, testified that there were never more than five mechanics employed at the yard at any one time. Payroll records for the period from 1961 to 1975 indicate that the number of mechanics generally ranged from three to seven, averaging the equivalent of 4.6 full-time mechanics. The records show only one week with as many as 19 mechanics at the yard at a time.

Equipment would generally be steam-cleaned upon arrival at the yard. The steam-cleaning area was located in the southeastern portion of the yard, outside the old shop. An employee would use a high-pres *1287 sure soap and water spray to dislodge dirt, rocks, and grease, which would be collected on a concrete pad and dumped off of the Site. Liquids would collect in a drain in the center of the concrete pad. No degreasing agent was used in this process.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

State v. Braesch
874 N.W.2d 874 (Nebraska Supreme Court, 2016)
CHAMPION LABORATORIES, INC. v. Metex Corp.
677 F. Supp. 2d 748 (D. New Jersey, 2010)
Clark v. Richman
339 F. Supp. 2d 631 (M.D. Pennsylvania, 2004)
USGen New England, Inc. v. Town of Rockingham
2004 VT 90 (Supreme Court of Vermont, 2004)
City of Owensboro v. Adams
136 S.W.3d 446 (Kentucky Supreme Court, 2004)
Berry v. School Dist. of City of Benton Harbor
195 F. Supp. 2d 971 (W.D. Michigan, 2002)
Karras v. Teledyne Industries, Inc.
191 F. Supp. 2d 1162 (S.D. California, 2002)
Sealy Connecticut, Inc. v. Litton Industries, Inc.
93 F. Supp. 2d 177 (D. Connecticut, 2000)
In Re Dow Corning Corp.
237 B.R. 364 (E.D. Michigan, 1999)
United States v. Davis
31 F. Supp. 2d 45 (D. Rhode Island, 1998)

Cite This Page — Counsel Stack

Bluebook (online)
1 F. Supp. 2d 1282, 28 Envtl. L. Rep. (Envtl. Law Inst.) 21, 46 ERC (BNA) 1614, 1998 U.S. Dist. LEXIS 5411, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ekotek-site-prp-committee-v-self-utd-1998.