Eimco-Bsp Service Company v. Valley Inland Pacific Constructors, Inc.

626 F.2d 669
CourtCourt of Appeals for the Ninth Circuit
DecidedSeptember 17, 1980
Docket77-3763
StatusPublished
Cited by8 cases

This text of 626 F.2d 669 (Eimco-Bsp Service Company v. Valley Inland Pacific Constructors, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Ninth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Eimco-Bsp Service Company v. Valley Inland Pacific Constructors, Inc., 626 F.2d 669 (9th Cir. 1980).

Opinions

TANG, Circuit Judge:

This is a diversity action involving a dispute between a contractor, Valley Inland Pacific Constructors, Inc. (VIPCO), and a subcontractor, Eimco-BSP Service Company (Envirotech), over the amount due Envirotech for work it performed in connection with renovation of a sewage treatment plant for the City of Vancouver, Washington. Envirotech claimed that the failure of VIPCO to object to the final account that Envirotech rendered to it constituted an account stated and thereby extinguished VIPCO’s unliquidated damage claim for breach of contract. The magistrate, sitting with consent of the parties entered judgment for Envirotech, and VIPCO appeals.

VIPCO was awarded the prime contract to convert Vancouver’s Westside Sewage Treatment Plant into a secondary treatment facility. Envirotech and VIPCO entered into a contract whereby Envirotech agreed to furnish and install the plant’s heat treatment system. The contract provided that the final payment of the 10% retained would be made to Envirotech 45 days after the work was approved by the architect and the City.

In May 1973 Envirotech learned that the heat exchanger it had installed was unacceptable to the Washington State authorities, because it did not contain an American Society of Mechanical Engineers Code. Before the city or VIPCO had learned of this problem, the city had released $120,000 to VIPCO as partial payment for the heat exchanger, a sum that VIPCO in turn had paid to Envirotech. Upon learning that the heat exchanger would be unacceptable, the city recouped its payment by withholding future payments to VIPCO. Envirotech, however, refused to return any of the payment to VIPCO.

Instead of removing the uncoded heat exchanger and installing a coded one, Envirotech appealed the decision that it needed a coded exchanger through state administrative channels. VIPCO was obligated, under its contract with the city, to dispose of sludge during the construction, and, on November 6,1973 informed Envirotech that it held Envirotech responsible for the disposal of the sludge that would accumulate, because the process portion of the plant was complete with the exception of the heat treatment system. Envirotech denied responsibility for the accumulating sludge. VIPCO met privately with city officials in December 1973 and agreed on a disposal plan for alleviating the problem. As a result, VIPCO incurred severe disposal expenses as the sludge accumulated during the delay in the operation of the heat treatment system.

[671]*671In January 1974, after receiving permission from the state of Washington, Envirotech began around the clock heat exchange operations using the uncoded system on a temporary basis until they installed a new coded heat exchange system. In March 1974 Envirotech installed the new heat exchanger and the city once again paid VIP-CO for that portion of the project.

The Envirotech-VIPCO contract provided that Envirotech would be paid the final retainage sum within 45 days of the city’s acceptance of the project. The city accepted the project in December 1974, although it did not release the final retention money until May 1975. The final retainage due Envirotech was $61,900.

In August and December 1974, Envirotech mailed VIPCO invoices for the unpaid remainder due on the contract. VIPCO did not respond to either mailing. During late 1974 and the first five months of 1975, James Young, Envirotech’s Project Manager, called Frank Fritzie, the President of VIPCO, to determine when the retainage would be released to Envirotech. According to Young, the conversations generally related to when the project retainage would be released by the city to VIPCO. On March 18, 1975, following a conversation during which Fritzie told Young that the final retention would be released to VIP-CO’s subcontractors within one week after receipt from the city, Young sent the following letter:

“Dear Mr. Fritzie:
I was happy to learn this afternoon in talking with you that the final Tax Audit by the State of Washington will begin on Thursday, March 20.
In talking with the City (Mr. Eric Oien) and yourself, it is my understanding that the City will release the retention monies to V.I.P. as soon as the State Tax Audit is complete.
Further, per our discussions, V.I.P. will release all billed retention monies ($61,-900) to Envirotech within one week after receipt of funds from the City.
Please advise if any of the above is not in accordance with our conversation.
Very truly yours,
EIMCO BSP Division
ENVIROTECH CORPORATION
/s/ James Young
Project Manager’’

VIPCO made no immediate response to this letter. During the next two months, another Envirotech representative, William Reilly, called Fritzie to seek release of the funds. Fritzie did not recall any discussions about VIPCO claiming back charges resulting from the sludge removal.

In early June 1975, during a telephone conversation between Young and Fritzie, Envirotech learned for the first time that VIPCO intended to offset the costs of sludge removal from the final retainage due Envirotech. Accordingly, VIPCO tendered a check later that month to Envirotech for $1,191.70. Envirotech rejected this tender and another check for even less than this amount, and filed this complaint to recover the retainage. VIPCO counterclaimed for damages incurred from Envirotech’s breach of its contract to provide an acceptable heat exchanger system.

Envirotech pleaded two causes of action, one based on the original contract, the other on an account stated. The magistrate found that the failure of VIPCO to object to the account tendered in the March 18 letter within a reasonable time constituted an account stated in the amount of $61,900. He disallowed an offset to VIPCO, finding it “fundamentally inconsistent with the nature of the account stated.”

The sole issue on appeal is the correctness of the magistrate’s conclusion that there was an account stated between the parties which constituted a final adjustment of their dealings. We conclude that the magistrate erred in his understanding of the law of “account stated” and remand for further proceedings.

An account stated is an agreement between persons having previous monetary transactions that fixes the amount due in respect to such transactions and promises payment. E. g., Steinmetz v. Grennon, 106 Or. 625, 634, 212 P. 532, 535 (1923); Halvor[672]*672son v. Blue Mountain Prune Growers, 188 Or. 661, 214 P.2d 986 (1950). As such, an account stated is itself an independent contract that is enforceable without regard to the underlying transactions on which it is based. Meridianal Co. v. Moeck, 121 Or. 133, 253 P. 525 (1927). After a party has tendered an account, the promise to pay the stated amount may be expressed, or implied from the actions of the party when their conduct justifies the inference that they have agreed. Steinmetz, 106 Or. at 634, 212 P. 532. Unless a debtor objects within a reasonable time to a tendered account, the inference of an agreement may be drawn and the account considered as stated. Carlon v. First National Bank, 80 Or. 539, 547-48, 157 P. 809 (1916).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Sandra L. Ferguson, Et Ano., V. Brian J. Waid, Et Ano.
Court of Appeals of Washington, 2021
Kennedy v. Caruso
D. Connecticut, 2020
Tiger Steel Engineering, LLC v. Symbion Power, LLC
195 A.3d 793 (District of Columbia Court of Appeals, 2018)
Citibank v. Hull
26 Pa. D. & C.5th 188 (Clinton County Court of Common Pleas, 2012)
Fisher Sand & Gravel Co. v. Neal A Sweebe, Inc.
810 N.W.2d 277 (Michigan Court of Appeals, 2011)
MOORMAN MANUFACTURING CO. OF CALIFORNIA, INC. v. Hall
830 P.2d 606 (Court of Appeals of Oregon, 1992)
MERRILL-STEVENS DRY DOCK COMPANY v. Corniche Express
400 So. 2d 1286 (District Court of Appeal of Florida, 1981)

Cite This Page — Counsel Stack

Bluebook (online)
626 F.2d 669, Counsel Stack Legal Research, https://law.counselstack.com/opinion/eimco-bsp-service-company-v-valley-inland-pacific-constructors-inc-ca9-1980.