Eilertsen v. WEBER

255 P.2d 150, 198 Or. 1, 1953 Ore. LEXIS 203
CourtOregon Supreme Court
DecidedApril 8, 1953
StatusPublished
Cited by14 cases

This text of 255 P.2d 150 (Eilertsen v. WEBER) is published on Counsel Stack Legal Research, covering Oregon Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Eilertsen v. WEBER, 255 P.2d 150, 198 Or. 1, 1953 Ore. LEXIS 203 (Or. 1953).

Opinion

PERRY, J.

This is an action at law to recover in quantum meruit for work and labor performed. The plaintiff prevailed and the defendants appeal.

The defendants assign as error the trial court’s refusal to grant their motion for a directed verdict, their contention being that the oral promise of the de *4 fendant Yernon F. Weber to pay the sum recovered is a promise to answer for the debt, default or miscarriage of another and is within § 2-909, subsection 2, OCLA (statute of frauds) and therefore all oral evidence of the promise is incompetent; on the further ground that there was a complete failure of consideration for the promise of the defendants; and further, that the court erred in refusing to give an instruction to the effect that if the jury found that the defendant Weber’s promise was an original promise for the completion of the work, then they must segregate plaintiff’s demand, that is, the value of the work that he had already done prior to the defendants’ promise and what he earned thereafter, and, if they are unable to make a determination of the value of the work done before the promise and that following the promise, then the verdict should be for the defendants.

The defendants, some time in May or June, 1948, entered into an agreement with a Mr. Abbott to construct a building in Florence, Oregon. Plaintiff, being a plumbing and heating contractor, was given a subcontract to install the plumbing and heating in the building. The total amount due for labor and materials on the completion of the work, plus extras, was the sum of $8,857.17. The plaintiff was paid $3,000 on October 18, 1948, by the contractor, Mr. Abbott, and, on March 7, 1949, the defendant Yernon Weber paid bim $1,500. The plaintiff completed his work, and, having been paid nothing except as set out above, instituted this action for the balance which he claimed of $4,357.17.

It is the defendants’ contention that the plaintiff, as á subcontractor employed by the general contractor, performed the work and furnished the material under *5 his contract with the general contractor; that Weber’s agreement, if any, was a collateral agreement to indemnify the plaintiff; that it was not in writing, and therefore came within the statute of frauds. § 2-909, subs. 2, OCLA, supra.

The plaintiff contends that, the general contractor having failed to pay his moneys as they became due as the contract progressed and having refused to proceed further, his contracts with Abbott, the general contractor, were at an end, and that he continued with the work only because of the new promise of the defendant Vernon F. Weber, as agent for. all the defendants, to pay him for the work then completed and for the work to be done.

In determining whether the trial court erred in denying defendants’ motion for a directed verdict, this court cannot weigh the conflicting evidence but is required to consider the evidence in the record and every legitimate inference that can be drawn therefrom in a light most favorable to the plaintiff. Dudleston v. Chiravollatti, 184 Or 405, 198 P2d 858; Fish v. Southern Pacific Co., 173 Or 294, 301, 143 P2d 917, 145 P2d 991, and authorities cited therein.

The plaintiff testified that he was an experienced heating and plumbing contractor, and, further, as follows : ■

“Q. Do you know Mr. Abbott? A. Yes.
# & #
“Q. Could you tell the jury when you first became interested in this project of installing the plumbing and heating in this particular building? A. Well, it was around the 1st of August, we filed this proposal.
*6 ‘‘Q. And that proposal was filed between yon— A. And Grant Abbott. That was to do the budding in this said building. , ,
‘‘ Q. And then later on, was there another-agreement signed between you and Mr. Abbott covering the heating? A. At the time, they were in an awful hurry to get the plumbing in because they wanted to get the footings; and I went ahead and roughed in; and they wanted a proposal on the heating. And I was a little slower in getting a figure in on that.
* * * X %
“Q. Just a minute. Of course, we can’t go into what they did, Mr. Eilertsen. That was about' the 15th of October, you say, Doctor Weber said you could have the heating, too, and the estimate was signed. A. Yes, sir.
‘ ‘ Q. I will ask you if you can identify plaintiff’s Exhibit A and B, Mr. Eilertsen. State if you know what they are. A. This is the plumbing.
“Q. As prepared by you? A. Yes.
“Q. And signed by whom? A. Grant Abbott.
# * # * #
‘1Q. Now, referring to these exhibits which have not yet been entered into evidence, are you able to tell the jury exactly how this contract which you are holding was split, without the extras? A. The plumbing contract on the Weber and Dunn building, that rough-in and setting fixtures complete, was $4110; and the heating contract, total price, was $4350.
“Q. Where did the item of $397.17 extras come in? Was that subsequent to these extras? A. It was a mezzanine added, a beauty salon on the mezzanine, was a big item; and also, moving of a toilet in the apartment — Doctor Weber’s section.
# * # # *
“Q. Coming up to March 4, 1949, will you tell the jury, what was said between you and Mr. Weber or either of the defendants or both of them — and, if *7 anything, under what circumstances the conversation rose? A. Well, I came to Florence with my pickup with the idea of picking all the fixtures up and taking them hack to Newport. His promises hadn’t been fulfilled. He had promised to pay me since December.

_ Mr. Bryson: If the Court please, if he is testifying as I think he is as to promises made by our clients, the defendants—

The Court: Well, he said, ‘He’. Of course, you can bring out who he has reference to.
*****
“Q. What happened when you came down to Florence that day? A. Well, finally — finally we got to see Doctor Weber. And he was in a hurry to get his fixtures set and wondered why we weren’t setting them. And I said I couldn’t set fixtures on premises until I got paid, so he told me he would pay me personally for the work that had been done, and also what was coming after I had set the fixtures if I would please stay and set the fixtures.
Mr. Bryson: If the Court please, I renew my objection for the same reason under the statute of frauds on the promise of any of these defendants to pay Mr. Eilertsen, the plaintiff, for any part of the work he was doing for Mr. Abbott.
“Q. Do you remember the exact conversation— tell us, if you can. If you remember Doctor Weber’s words. A.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Rosewood Care Center, Inc. v. Caterpillar, Inc.
852 N.E.2d 540 (Appellate Court of Illinois, 2006)
Rosewood Care Center, Inc v. Caterpillar
Appellate Court of Illinois, 2006
Hevern v. Walter E. Heller Western, Inc.
796 P.2d 1229 (Court of Appeals of Oregon, 1990)
Otto Contracting Co. v. S. Schinella & Son, Inc.
427 A.2d 856 (Supreme Court of Connecticut, 1980)
Ford v. Allum
445 P.2d 511 (Oregon Supreme Court, 1968)
Bonneville Equipment Co. v. Tuttle
424 P.2d 231 (Oregon Supreme Court, 1967)
Copenhagen, Inc. v. KRAMER ET UX
356 P.2d 1064 (Oregon Supreme Court, 1960)
Burghardt v. Olson
354 P.2d 871 (Oregon Supreme Court, 1960)
Columbia Brick Works v. FREEMAN ET UX
353 P.2d 620 (Oregon Supreme Court, 1960)
Sugar v. Miller
315 P.2d 862 (Utah Supreme Court, 1957)
Moore v. State Finance Co.
274 P.2d 559 (Oregon Supreme Court, 1954)

Cite This Page — Counsel Stack

Bluebook (online)
255 P.2d 150, 198 Or. 1, 1953 Ore. LEXIS 203, Counsel Stack Legal Research, https://law.counselstack.com/opinion/eilertsen-v-weber-or-1953.