Columbia Brick Works v. FREEMAN ET UX

353 P.2d 620, 223 Or. 109, 1960 Ore. LEXIS 532
CourtOregon Supreme Court
DecidedJuly 6, 1960
StatusPublished
Cited by3 cases

This text of 353 P.2d 620 (Columbia Brick Works v. FREEMAN ET UX) is published on Counsel Stack Legal Research, covering Oregon Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Columbia Brick Works v. FREEMAN ET UX, 353 P.2d 620, 223 Or. 109, 1960 Ore. LEXIS 532 (Or. 1960).

Opinion

O’CONNELL, J.

This is an action to recover the value of building materials furnished by the plaintiff to William D. Kay-ton, allegedly upon the promise of the defendant, Joseph J. Freeman, acting on behalf of himself and his wife Shirley Freeman, to pay for such materials.

The case was tried without a jury. A judgment was entered against both defendants. The trial court found that the defendants unqualifiedly agreed to pay for the materials delivered to Kayton. The sole question before us is whether there was sufficient evidence to support the trial court’s conclusion. We are of the opinion that the evidence is sufficient to support the judgment.

The defendants rely upon ORS 41.580, which provides in effect that “an agreement to answer for the debt, default or miscarriage of another” is void unless it is evidenced by a writing.

The testimony of one of the plaintiff’s agents, if believed, would establish the fact that defendant, Joseph Freeman, orally promised to pay for the materials delivered to Kayton, and that the promise was made not as a guarantor but as a principal obligor, the plaintiff relying exclusively upon defendant’s credit. On the basis of defendant’s promise the plaintiff made further deliveries of materials used in the improvement of the property in which defendants had an interest. This was a direct benefit to the defendants. Such an agreement is not within the statute of frauds. *111 Mackey v. Smith et al., 21 Or 598, 28 P 974 (1892); Harrison v. Birrell, 58 Or 410, 115 P 141 (1911). See also, Eilertsen v. Weber, 198 Or 1, 255 P2d 150 (1953); Bryant v. Panter, 91 Or 686, 178 P 989 (1919).

Error is assigned for the trial court’s failure to make certain findings of fact requested by the defendants. The trial judge made findings upon all of the material issues in the case. The requested findings would have added only a conclusion of law and a detailed recitation of evidence already covered by the court’s statement of the ultimate facts. Silver Falls Co. v. Eastern & Western Lbr. Co., 149 Or 126, 40 P2d 703 (1935); Fitzpatrick v. Sletten, 117 Or 173, 242 P 1114 (1926); Maeder Steel Products Co. v. Zanello, 109 Or 562, 220 P 155 (1923); Oregon Home Builders v. Montgomery Inv. Co., 94 Or 349, 184 P 487 (1919).

The judgment is affirmed.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Romney Produce Company v. Edwards
451 P.2d 338 (Court of Appeals of Arizona, 1969)
Boothe v. Bennett
436 P.2d 746 (Oregon Supreme Court, 1968)
Copenhagen, Inc. v. KRAMER ET UX
356 P.2d 1064 (Oregon Supreme Court, 1960)

Cite This Page — Counsel Stack

Bluebook (online)
353 P.2d 620, 223 Or. 109, 1960 Ore. LEXIS 532, Counsel Stack Legal Research, https://law.counselstack.com/opinion/columbia-brick-works-v-freeman-et-ux-or-1960.