Edward Springer v. Ausbern Construction Co., Inc.

231 So. 3d 1065
CourtCourt of Appeals of Mississippi
DecidedAugust 2, 2016
Docket2014-CA-01190-COA
StatusPublished
Cited by4 cases

This text of 231 So. 3d 1065 (Edward Springer v. Ausbern Construction Co., Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Mississippi primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Edward Springer v. Ausbern Construction Co., Inc., 231 So. 3d 1065 (Mich. Ct. App. 2016).

Opinions

GREENLEE, J„

for the Court:

¶ 1. A Lafayette County jury awarded Ausbern Construction Company Inc. a judgment of $182,500 against county engineer Edward Springer for tortious interference with a road-construction contract. Springer appeals. We find that Springer acted within the scope of his responsibility to the County and without bad faith. Because his actions were not “without right or justifiable cause,” the element of tor-tious interference that constitutes malice was not satisfied. We also find that the claim against Springer implicates the Mississippi Tort Claims Act, and that Springer’s motion to dismiss due to lack of pre-suit notice should have been granted. We therefore reverse and render the verdict against Springer.

FACTS AND PROCEEDINGS BELOW

¶2. Ausbern won a contract bid with Chickasaw County for construction of a road. Ausbern’s bid was based on unit specifications prepared by the office of [1067]*1067Chickasaw County’s engineer, Springer. Springer’s original plans estimated that 7,689 cubic yards of 304A fill material would be required. This estimate turned out to be an error, and the project actually required 17,700 cubic yards of the unit material.

¶ 3. The project was subject to oversight from the Mississippi Office of State Aid. State Aid projects are subject to the regulations found in the “Mississippi Standard Specifications for State Aid Road and Bridge Construction” (the Green Book). Under the Green Book, the local county engineer is responsible for inspecting the contractor’s work, measuring and keeping track of the actual unit quantities placed by the contractor, preparing monthly estimates of the work actually performed by the contractor, and reporting that quantity and corresponding earned contract amounts to both the State Aid Division and the County.1

¶4. Section 105.17 of the Green Book provides a mechanism for a contractor to make a claim for adjustments from the original contract. It specifies that it “is in the public interest that the Board and the State Aid Engineer have early or prior knowledge of an existing or impending claim of any nature by the Contractor,” that “the Contractor shall notify the Engineer in writing of an intention to make such claim for additional compensation before beginning the work on which the Contractor bases the claim or for such extension of time as soon as the facts first become known on which the Contractor bases the claim for adjustment,” that “the Contractor hereby agrees that failure to provide written notice has denied the Board and the State Aid Engineer the prerogative of verifying additional time, materials, equipment, labor and making adjustment in the work which might remove or mitigate the conditions for which a claim, might be made,” and that “the Contractor further agrees that such failure on the Contractor’s part shall be a conclusive waiver of any claim, or part thereof.”

¶ 5. Ausbern did not give notice to the State Aid Office or to the county engineer, Springer, that the project required' almost three times as' much fill material as the contract called for until after the' project was completed in November 2011. Aus-bern sent Springer emails November 23, 2011, December 2, 2011, and December 22, 2011, informing him that the amount of 304A the project required was significantly more than the original estimates and asking how the overage would be addressed.2 Ausbern then contacted Joel Bridges,, the district engineer with the State Aid Division. Bridges forwarded Ausbern’s letter to Springer.

¶6, In January 2012, Ausbern filed a formal claim for payment for the overage with the State Aid Office under Green Book section 105.17. State Aid Division engineer Joel Bridges approved this claim in February 2012, finding that Springer’s original plans were in error and informing Chickasaw County and Springer that the Ausbern contract should be adjusted to show 17,700 cubic yards of 304A and that Ausbern would be paid at the contract rate of $19.50 per cubic yard. Bridges also informed the Board of Supervisors in person that the claim had been approved. The County delayed payment pending approval from Springer.3

[1068]*1068¶ 7. In February 2012, Springer sent a letter to Ausbern acknowledging -the error and offering that Ausbern should accept $8.00 a cubic yard for the overage rather than the contract unit price of $19.50. Ausbern declined to negotiate the unit price and in March 2012 sued Chickasaw County for breach of contract. Ausbern later joined Springer to the action, suing him individually for tortious interference with the contract. due. to his delay in addressing the overage and his failure to submit approval of an amended contract to the .County.4 .Ausbern did not provide pre-suit notice pursuant to the Mississippi Tort Claims Act.

¶ 8.- The court granted a directed verdict to Ausbern against the County on its liability for breach of contract. The court rejected the County’s argument that Aus-bern had waived its right to be paid for the overage by failing to comply exactly with any notice requirements of Green Book section 105.17, stating: “I don’t think that the failure to comply with the notice provisions excuses performance on, the part of the county.” The jury awarded Ausbern a judgment against the Oounty for $387,793.50. That verdict was not appealed,

¶ 9. The trial court -denied Springer’s pretrial and posttrial motions asserting that the tortious-interference claim against him implicated the Mississippi Tort Claims Act and that the suit against him should be dismissed due to lack of pre-suit notice. The jury awarded Ausbern a judgment of $182,500 against Springer for tortious interference, including damages associated with lost bonding capacity due to outstanding accounts receivable.

¶ 10. Springer appeals,

DISCUSSION

. To the extent the chancellor determined that notice was required before pursuing claims of tortious interference with either business relations or contracts, this was error.

¶ 11. ■ We review a trial court’s grant or denial of a motion for a new trial for abuse of discretion. Barviffe v. Estate of Nelson, 153 So.3d 613, 618 (¶ 22) (Miss.2014). Questions of law are reviewed de novo. Id. at (¶ 26).

I. Whether Ausbern proved the elements of tortious interference.

¶ 12. Springer argues that Aus-bern failed to prove the element of tortious interference with a contract that implicates malice. Recovery for tortious interference is permissible where a plaintiff proves (1) the acts were intentional and willful; (2) they were calculated to cause damage to the plaintiff in his lawful business; (3) they were done with the'unlawful purpose of causing damage and loss, without right or justifiable cause on the part of the defendant, which acts constitute malice; and (4) actual damage or loss resulted. Reeves v. Midcontinent Exp. Pipeline, LLC, 119 So.3d 1097, 1102 (¶ 13) (Miss.Ct.App.2013). “In this context, ‘malicious’ is defined as the intentional doing of a harmful act without legal or sound justification or excuse, in other words, the willful violation of a known right.” Collins v. Collins, 625 So.2d 786, 790 (Miss.1993).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
231 So. 3d 1065, Counsel Stack Legal Research, https://law.counselstack.com/opinion/edward-springer-v-ausbern-construction-co-inc-missctapp-2016.