Edgewater Construction Group, Inc.

United States Bankruptcy Court, S.D. Florida.·Decided November 15, 2024·No. 23-12217·Unknown

Opinion

Tagged opinion PRR, op Jf “A sg Yhagl”'¢ a SI RAINS □□ ORDERED in the Southern District of Florida on November 15, 2024.

fruuf YN

Laurel M. Isicoff, Judge United States Bankruptcy Court

IN THE UNITED STATES BANKRUPTCY COURT SOUTHERN DISTRICT OF FLORIDA MIAMI DIVISION IN RE: Case No. 23-12217-BKC-LMI EDGEWATER CONSTRUCTION Chapter 11 GROUP, INC. Subchapter V Debtor.

ORDER ON DAMAGES THIS MATTER came before the Court on May 21 and 22, 2024 for trial (the “Trial”) on (1) the damages phase of the Order on Debtor’s Emergency Motion for an Order Enforcing the Automatic Stay; Setting Further Hearing on Request for Sanctions for Intentional and Willful Violation of the Automatic Stay; and Setting Further Hearing on Request for Turnover (the “Stay Violation Order”) (ECF #242); and (2) Reorganized Debtor’s Objection to Balfour’s Proof of Claim 27-3 (the “Claim

Objection”) (ECF #516). The Court has considered the Stay Violation Order, the Claim Objection, the response to the Claim Objection, the parties’ arguments, and the evidence presented at Trial in rendering the following ruling.1

PROCEDURAL AND FACTUAL BACKGROUND In October of 2021 BALFOUR BEATTY CONSTRUCTION, LLC (“Balfour,” “Balfour Beatty,” or “Contractor”) and EDGEWATER CONSTRUCTION GROUP, INC. (“Edgewater” or “Debtor” or “Reorganized Debtor” or “Subcontractor”) executed a Long Form Subcontract under which Edgewater was to perform stucco services on what has been called the RD East Las Olas Project (the “RD Project”). In January of 2022 Balfour Beatty and Edgewater entered into an almost identical Long Form Subcontract to perform stucco services on what has

been called the 2000 Biscayne Project (the “2000 Project”).2 At some point after Edgewater executed the Contracts, Edgewater began to experience financial difficulties at the many projects in which it was performing stucco subcontracting work, including the Projects. On March 20, 2023, Edgewater’s field crew assigned to the RD Project stopped working and left the jobsite altogether based on Edgewater’s failure to pay their wages. On March 21, 2023, Balfour Beatty emailed Edgewater as follows: Edgewater's field crew assigned to RD Las Olas stopped working and left the jobsite today. As a result of this action, this email is a delay

1 The findings of fact and conclusions of law set forth herein constitute the Court’s findings of fact and conclusions of law pursuant to Rule 7052 of the Federal Rules of Bankruptcy Procedure (“Fed. R. Bankr. P.”). To the extent any of the following findings of fact are determined to be conclusions of law, they are adopted, and shall be construed and deemed, as conclusions of law. To the extent any of the following conclusions of law are determined to be findings of fact, they are adopted, and shall be construed and deemed, as findings of fact. 2 The two contracts will be referred to collectively as the “Contracts” and the two projects will be referred to collectively as the “Projects”. notice because production on site cannot stop. Edgewater's decision to pull out all their personnel from the site without notice will delay the completion date of the project. Cost and schedule impact may result due to this decision which may also affect other trades.

Your written explanation and correction plan must be submitted via e-mail to all copied in this email by COB today. We ask that you take appropriate measures to address this issue promptly.

On March 22, 2023, Balfour Beatty sent a second email to Edgewater demanding that the situation be corrected. Edgewater did not respond to either email. However, on March 22, 2023, Edgewater filed for protection under Subchapter V of Chapter 11 of the Bankruptcy Code (the “Petition Date”). At the time Edgewater filed bankruptcy, the RD Project was well underway, but the only work Edgewater had done on the 2000 Project was the preparation of mockups of different stucco applications for the owner’s review. What happened after that, leading up to the entry of the Stay Violation Order, is detailed in that order. There is no need for the Court to repeat those findings in this order. The Stay Violation Order held that Balfour Beatty had willfully violated the automatic stay by issuing the Default Letters3 and by wrongfully retaining Edgewater’s scaffolding and stucco materials left at the Projects (collectively the “Stay Violations”). The Stay Violation Order directed the parties to confer regarding establishing trial procedures to adjudicate Edgewater’s request for damages arising from the Stay Violations, which requests included (1) loss of

3 All terms not defined herein shall have the meaning set forth in the Stay Violation Order. profits; (2) the inability to monetize its scaffolding as a result of Balfour Beatty’s wrongful retention; (3) the additional cost of Edgewater retaining personnel on the belief it would continue to work under the Contracts; (4) the inability to

contain and resolve claims against the estate due to Balfour Beatty’s unilateral decision to pay certain suppliers and subcontractors; (5) legal fees and costs; (6) lost opportunity costs related to the distractions of Edgewater’s personnel dealing with the Stay Violations; and (7) punitive damages.4 In addition to the damages phase of the Stay Violation Order, by agreement, the parties agreed to try the Claim Objection, as well as Edgewater’s request for turnover of unpaid draw requests, which draw requests will be described in more detail later in this opinion. The parties also tried by consent

the issue of damages arising from the disappearance of at least half of the scaffolding that had been delivered to the Projects from the time the bankruptcy case was filed to the time the remaining scaffolding was sold by Edgewater to the subcontractor who replaced it on the Projects – James J. Brooks, Inc. d/b/a Advanced Stucco (“Advanced”), which relate, not only to the wrongful retention of the scaffolding, but, as more detailed below, also to the appropriateness and amount of the punitive damages.

4 Prior to Trial the Court granted Balfour Beatty’s Motion for Partial Summary Judgment (ECF #311) holding that Edgewater was not entitled to lost profits as a matter of law. See Oral Ruling on Motion for Partial Summary Judgment (ECF #544); Order Granting Balfour Beatty Construction, LLC's Motion for Partial Summary Judgment (ECF #622). Edgewater did not put on any proof at Trial regarding retention cost of personnel or lost opportunity costs. The issues relating to Balfour Beatty’s unilateral payment to subcontractors and suppliers was addressed by the Court in its Memorandum Opinion on Order Denying Application for Administrative Claim (ECF #519). FINDINGS OF FACT AND CONCLUSIONS OF LAW A. Actual Damages for the Stay Violations As the Court noted in the Stay Violation Order “[i]f a party willfully violates

the automatic stay a debtor who is injured by the willful violation is entitled to recover his or her actual damages including costs and attorneys' fees, and if appropriate, may also recover punitive damages.” In re Lyubarsky, 615 B.R. 924, 929 (Bankr. S.D. Fla. 2020). The actual damages for which evidence was presented at Trial by Edgewater are for the use of the scaffolding while it was being wrongfully retained by Balfour Beatty, the replacement value of the scaffolding that disappeared from the Projects, the value of the stucco material wrongfully retained, and attorneys’ fees incurred in connection with the Stay

Free access — add to your briefcase to read the full text and ask questions with AI

Edgewater Construction Group, Inc., (Fla. 2024).

Edgewater Construction Group, Inc. (Edgewater Construction Group, Inc.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Small Business Administration v. Echevarria
864 F. Supp. 1254 (S.D. Florida, 1994)
Banderas v. Doman (In Re Banderas)
236 B.R. 841 (M.D. Florida, 1999)
In Re SunCruz Casinos LLC
342 B.R. 370 (S.D. Florida, 2006)
Roche v. Pep Boys, Inc. (In Re Roche)
361 B.R. 615 (N.D. Georgia, 2005)
In RE McKAY
420 B.R. 871 (M.D. Florida, 2009)
In Re Beverage Canners International Corp.
255 B.R. 89 (S.D. Florida, 2000)
Mary Beth Mantiply v. Patricia Nelson Horne
876 F.3d 1076 (Eleventh Circuit, 2017)
In re Harrison
599 B.R. 173 (N.D. Florida, 2019)
Parker v. Credit Central South, Inc.
634 F. App'x 770 (Eleventh Circuit, 2015)
Taxinet Corp. v. Santiago Leon
114 F.4th 1212 (Eleventh Circuit, 2024)