EDF Renewables Distributed Solutions, Inc. v. Southard

CourtDistrict Court, D. Minnesota
DecidedOctober 6, 2020
Docket0:19-cv-01588
StatusUnknown

This text of EDF Renewables Distributed Solutions, Inc. v. Southard (EDF Renewables Distributed Solutions, Inc. v. Southard) is published on Counsel Stack Legal Research, covering District Court, D. Minnesota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
EDF Renewables Distributed Solutions, Inc. v. Southard, (mnd 2020).

Opinion

UNITED STATES DISTRICT COURT DISTRICT OF MINNESOTA

EDF Renewables Distributed Solutions, Inc., File No. 19-cv-1588 (ECT/BRT)

Plaintiff,

v. OPINION AND ORDER

Morgan Southard and Dianne Southard d/b/a Oxbow Sunworks, Oxbow Solar Professionals, Inc.,

Defendants. ________________________________________________________________________ Dean B. Thomson, Thomas C. Schram, Fabyanske, Westra, Hart & Thomson, PA, Minneapolis, MN, for Plaintiff.

Steven R. Little, SRL Law, PLLC, St. Paul, MN, for Defendants.

This began as a straightforward commercial contract case. Plaintiff EDF Renewables Distributed Solutions, Inc., claims that Defendants Morgan and Dianne Southard, doing business as Oxbow Sunworks, failed to perform subcontract agreements related to solar-power construction projects and then improperly recorded mechanic’s liens on the projects through a different entity, Oxbow Solar Professionals, Inc. Compl. ¶¶ 1–2 [ECF No. 1]. After EDF filed its complaint, it deposited a bond with the Court, and Defendants agreed to seek recovery on their liens from the bond rather than from the solar projects themselves. ECF Nos. 13, 15, 18. Defendants then filed counterclaims seeking to foreclose their liens, as well as for breach of contract, promissory estoppel, unjust enrichment, and quantum meruit. Am. Counterclaim [ECF No. 17]. A drawn-out discovery dispute eventually led Magistrate Judge Becky R. Thorson to order Defendants to produce documents that EDF had requested. ECF No. 48. Magistrate Judge Thorson also ordered Defendants to pay EDF more than $19,000 in

attorney fees as a sanction for their conduct in discovery. Id.; ECF No. 60. Defendants have not complied with either order or responded with any excuse for their noncompliance. EDF has moved to dismiss Defendants’ counterclaims with prejudice and to release the bond that it previously deposited with the Court. ECF No. 56. Because the unique circumstances of this case make the last-resort sanction of dismissal appropriate, EDF’s

motion will be granted. I Beginning in the fall of 2018, EDF agreed to design and construct a “community solar garden portfolio” for a company that is not a party to this litigation. Compl. ¶ 14. To fulfill its obligations under this broader agreement, EDF entered into separate subcontract

agreements with Defendants for “electrical and mechanical construction work” at seven different solar-power-generation project sites. Compl. ¶ 16; Am. Answer ¶ 13. According to EDF, Defendants failed to pay their subcontractors and suppliers and generally to complete the agreed-upon work. Compl. ¶¶ 24–29. After EDF allegedly brought these issues to Defendants’ attention several times without resolution, it decided to assume the

remaining work on the projects in April 2019. Compl. ¶¶ 30–36. About a week later, Defendants filed and recorded mechanic’s liens against each of the seven solar-generation projects.1 Compl. ¶ 39; Am. Answer ¶ 31. EDF filed its complaint in June 2019, raising claims for breach of contract, a

Minnesota statutory violation, and a judgment declaring Defendants’ liens invalid. Compl. ¶¶ 48–80. Defendants filed an answer, ECF No. 9, and later an amended answer in which they asserted counterclaims for breach of contract, promissory estoppel, unjust enrichment, and quantum meruit, ECF No. 12. Shortly thereafter, EDF agreed to file a bond worth $242,952.63 with the Clerk of Court. ECF Nos. 13, 15, 18. In exchange, Defendants

agreed to entry of an order discharging and releasing its liens from the properties on which the solar projects were located and requiring them to assert foreclosure claims only against EDF’s bond. Id. Defendants accordingly amended their pleadings to add these foreclosure claims. ECF No. 17. The case then proceeded into discovery, which is where the problems began. On

October 2, 2019, Magistrate Judge Thorson issued a Pre-Trial Scheduling Order under which the parties were to complete fact discovery by June 1, 2020. ECF No. 20 at 3. EDF served a request for production of documents on Defendants on October 23, which included requests for Defendants’ “complete project file for the Projects,” documents relied on by

1 The Parties dispute exactly who were parties to the subcontract agreements. EDF says that it entered into the subcontracts with the Southards, who were doing business under the “commercial assumed name” of Oxbow Sunworks, and that it never had a contractual relationship with Oxbow Solar Professionals—the entity that filed the liens. Pl.’s Mem. in Supp. at 2 n.1 [ECF No. 58]; Compl. ¶¶ 2, 39–41. Defendants claim that Oxbow Solar Professionals was a party to the subcontracts but that the Southards themselves never were. Am. Answer ¶ 13. There is no need to resolve this dispute for purposes of the present motion, so Defendants will be referred to collectively. any experts expected to testify, “cost estimates,” payment records, and other financial information. ECF No. 54-11. Defendants responded to the request in writing on November 25 and indicated that the documents themselves would follow, but no documents arrived.

ECF Nos. 54-12; 54-13. The resulting delay led the parties to request an extension of the deadline to amend pleadings, which Magistrate Judge Thorson granted. ECF Nos. 26, 28. Defendants did eventually produce over 1,600 pages of documents on December 27, but there was a problem. The production contained many duplicates and irrelevant materials, and it omitted “financial [and] cost records, [and] records of Defendants’

payments to their subcontractors and vendors” for the solar projects, which were necessary to evaluate Defendants’ counterclaims. Decl. of Thomas C. Schram ¶¶ 17–19 [ECF No. 54]. On January 9, 2020, EDF’s counsel asked Defendants’ counsel if more documents were on the way, but he received no response for nearly two months. ECF No. 54-16; Pl.’s Mem. in Supp. at 4–5.

A response came when the Parties held a meeting on March 6. At the meeting, Defendants claimed that they possessed “numerous additional documents” and that an expert witness was using these documents to prepare a damages claim worth more than $1,000,000. Schram Decl. ¶ 24. Defendants indicated that they would produce the remaining documents “on a rolling basis” by April 10. ECF No. 54-21. Based on this

proposal, the Parties’ stipulated to extend the discovery deadline to August 3, and Magistrate Judge Thorson ordered the extension. ECF Nos. 31, 32. April 10 came and went with no more document productions, prompting EDF to seek the Court’s intervention. ECF No. 54-25. At a status conference on May 6, Defendants’ new counsel2 blamed the delay on a dispute with a third party that had allegedly gained control of the records in question. Schram Decl. ¶ 32. On May 18, Defendants told EDF that they had made no progress and had “nothing more to produce.”

ECF No. 54-28. But two days later, at another status conference before Magistrate Judge Thorson, Defendants reported that they now had the records “and would produce them in the immediate future.” Schram Decl. ¶ 33. If Defendants did not follow through on this promise, Magistrate Judge Thorson warned at this second conference, they would face adverse consequences. Id.

When EDF had received no additional documents by June 3, it filed a motion to compel and for sanctions. ECF No. 39. The next day, June 4, Defendants produced nearly 1,200 more pages, but this production included only four new documents (the rest were duplicates of previously produced records), and Defendants once again omitted the “financial, cost, and payment records” that EDF sought. Schram Decl. ¶ 36. This was the

last that anyone has heard from Defendants in this case.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
EDF Renewables Distributed Solutions, Inc. v. Southard, Counsel Stack Legal Research, https://law.counselstack.com/opinion/edf-renewables-distributed-solutions-inc-v-southard-mnd-2020.