Eden v. State (In Re Srba Case No. 39576 Subase No. 37-00864)

429 P.3d 129
CourtIdaho Supreme Court
DecidedMarch 2, 2018
DocketDocket 44716
StatusPublished
Cited by14 cases

This text of 429 P.3d 129 (Eden v. State (In Re Srba Case No. 39576 Subase No. 37-00864)) is published on Counsel Stack Legal Research, covering Idaho Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Eden v. State (In Re Srba Case No. 39576 Subase No. 37-00864), 429 P.3d 129 (Idaho 2018).

Opinion

BEVAN, Justice

This is an appeal from the Snake River Basin Adjudication ("SRBA"). Gary and Glenna Eden (the "Edens") sought to file a late notice of claim for their Water Right No. 37-864 which was not claimed during the pendency of the SRBA and therefore was decreed disallowed. In the SRBA, the Edens alleged that the SRBA's Final Unified Decree and the Closure Order should be set aside as void because they did not receive sufficient notice of the SRBA proceedings to satisfy due process. Further, the Edens argued they were not personally served with the required notice of default pursuant to Idaho Rule of Civil Procedure 55(b)(2). Finally, the Edens claimed that unique and compelling circumstances justify relief from the final judgment under Idaho Rule of Civil Procedure 60(b)(6). The SRBA court disagreed and denied the Edens' relief on any of these grounds. The court entered judgment reflecting its conclusions. Edens timely appealed and we affirm the district court for the reasons below.

I. FACTUAL AND PROCEDURAL BACKGROUND

A. SRBA Case History and Procedures .

On June 17, 1987, pursuant to authority from Idaho's legislature in 1985 and 1986, the Director of the Idaho Department of Water Resources ("IDWR") filed a petition in the name of the State to begin the SRBA, and on November 19, 1987, the adjudication was commenced. Its purpose was to ultimately fashion a unified decree determining all water rights from the Snake River Basin water system. The decree would allow for the creation of an accurate schedule of water rights to assure the proper delivery of water in times of shortage.

At its commencement, the SRBA maintained "no reasonable method of initiating the proceeding; ... notice to potential claimants ... was provided by the existing Rules of Civil Procedure." In re SRBA Case No. 39576 , 128 Idaho 246 , 251, 912 P.2d 614 , 619 (1995) (hereinafter Basin-Wide Issue 3 ). One of the primary difficulties in a general stream adjudication like the SRBA, where thousands of claims and potential parties are involved, is that "a requirement of personal service would be too onerous, impractical and confusing in its employment, defeating any purpose for meaningful notice." Lu Ranching Co. v. United States , 138 Idaho 606 , 610, 67 P.3d 85 , 89 (2003) (citing In re Rights to the Use of Gila River , 171 Ariz. 230 , 241, 830 P.2d 442 , 453 (1992) ).

In light of these realities, "it was necessary for the Legislature to provide special procedural rules for the initiation of the SRBA." Basin-Wide Issue 3 , 128 Idaho at 251 , 912 P.2d at 619 . These rules are generally set forth in chapter 14, Title 42, Idaho Code, and include what are known as "first and second round" service procedures codified in Idaho Code section 42-1408. Additionally, this Court granted expanded powers to the district judge managing the SRBA:

[This Court] issued a Supplemental Order Granting Additional Powers to the District Judge. In that order, this Court granted the district court "the authority and power to modify the procedure for making service of pleadings, motions, notices of hearing *133 and other documents and the procedure of giving notice of hearings and trials before the court or any masters appointed by the court." In response to this order, the district court issued SRBA Administrative Order 1, [A.O.1], supplementing the applicable Rules of Civil Procedure with specialized procedures "to the extent necessary to allow for the fair and expeditious resolution of all claims or issues in the SRBA."

Id .

Pursuant to the authority granted in A.O.1 the district court adopted a procedure to provide notice which it called the Docket Sheet procedure. A.O.1 ¶ 6. The SRBA utilized this procedure by issuing monthly Docket Sheets which included a list of all orders, pleadings (except responses, pleadings or orders filed in subcases), and other documents filed with or issued by the SRBA court since the last Docket Sheet. The Docket Sheet is posted in the District Court of each county within the SRBA boundaries and made available at IDWR's central and regional offices. The Docket Sheet is also posted on the SRBA website. Interested persons also have the option of paying a nominal fee to subscribe to the Docket Sheet. Id . § 6(c) "Compliance with the Docket Sheet Procedure constitutes notice to all parties to an adjudication." Id . § 6(f)(3)(b).

As the SRBA began working toward a final, unified decree, the district court determined that it was appropriate to begin the basin closure process. Accordingly, it began informing water users that it would start closing claims in specific water basins. The court issued an Order which it called Order Establishing Deadline For Late Claim Filings in Basins 01 ... 37 ... ("Deadline Order") to inform individuals of the process. The Deadline Order was not mandated by chapter 14, Title 42, Idaho Code, but it was provided as an additional courtesy to water users.

The Deadline Order was issued in October 2012 and provided that the last date to file a Motion to File Late Claim was January 31, 2013. Pursuant to the Order, "[n]o late claims would be accepted for filing." The Deadline Order admonished potential claimants to "examine Exhibit 1 [a list of non-de minimis water rights from IDWR's water rights database, which included Water Right No. 37-864] to determine whether the listed water right numbers [were] active water rights." Id .

On August 26, 2014 the SRBA court culminated its 27-year effort and issued the Final Unified Decree for the SRBA. The Final Unified Decree decreed more than 158,600 water rights. Ann Y. Vonde et al ., Understanding the Snake River Basin Adjudication , 52 Idaho L. Rev. 53 , 56 (2016).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

State v. Stanley
Idaho Court of Appeals, 2024
Jones v. Sligar
Idaho Supreme Court, 2024
Araiza v. State
552 P.3d 626 (Idaho Supreme Court, 2024)
South Valley Ground Water v. ID Dept of Water Resources
548 P.3d 734 (Idaho Supreme Court, 2024)
Pinkham v. Plate
Idaho Supreme Court, 2023
State v. John Doe
533 P.3d 295 (Idaho Court of Appeals, 2023)
3G AG LLC v. IDWR
509 P.3d 1180 (Idaho Supreme Court, 2022)
Brockett Company LLC v. Crain
Idaho Supreme Court, 2021
Pizzuto v. State
484 P.3d 823 (Idaho Supreme Court, 2021)
Ciccarello v. Davies
456 P.3d 519 (Idaho Supreme Court, 2019)
First Security v. Belle Ranch
Idaho Supreme Court, 2019

Cite This Page — Counsel Stack

Bluebook (online)
429 P.3d 129, Counsel Stack Legal Research, https://law.counselstack.com/opinion/eden-v-state-in-re-srba-case-no-39576-subase-no-37-00864-idaho-2018.