Ecosystem Investment Partners v. United States

130 Fed. Cl. 537, 2017 U.S. Claims LEXIS 62, 2017 WL 475706
CourtUnited States Court of Federal Claims
DecidedJanuary 25, 2017
Docket16-1549C
StatusPublished

This text of 130 Fed. Cl. 537 (Ecosystem Investment Partners v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ecosystem Investment Partners v. United States, 130 Fed. Cl. 537, 2017 U.S. Claims LEXIS 62, 2017 WL 475706 (uscfc 2017).

Opinion

Bid protest; Standing; Waiver; 28 U.S.C. § 1491(b)(1); Interested Party; Prospective Bidder.

Eric G. Bruggink, Senior Judge

OPINION

Plaintiff, Ecosystem Investment Partners (“EIP”), protests the United States Army Corps of Engineers’ (the “Corps”) award of a contract to intervenor, Crosby Dredging, LLC (“Crosby Dredging”), for the provision of dredging and construction services as part of a compensatory environmental mitigation plan to offset other work the Corps was doing to safeguard against possible future storm damage. EIP was not a bidder in connection with this dredging solicitation, but it operated an environmental mitigation credit bank, which it argues should have been selected as part of an earlier environmental administrative action to accomplish the necessary mitigation effects. In other words, plaintiff has no critique to offer of the current dredge and fill solicitation other than its argument that the solicitation would have been unnecessary if the Corps had correctly assessed its environmental options earlier. The case raises the novel question of whether a challenge to the Corps’ actions in connection with developing a plan to mitigate its own environmental impacts can be heard as a bid protest.

On December 9, 2016, defendant moved to dismiss the complaint for lack of subject-matter jurisdiction or, in the alternative, to dismiss the complaint in part for failure to state a claim. 2 Oral argument was held on January 6, 2017. As we announced at the conclusion of oral argument, we find that plaintiff was not an “interested party” within the meaning of 28 U.S.C. § 1491(b)(1) (2012), and, in any event, waived its right to challenge the terms of the solicitation by not filing a protest prior to bid opening. In addition, we conclude that plaintiffs real dispute here does not raise a matter “in connection with a procurement or a proposed procurement” and thus we lack subject-matter jurisdiction for a third reason. We therefore grant defendant’s motion to dismiss for lack of subject-matter jurisdiction.

BACKGROUND

In response to the damage caused by Hurricanes Katrina and Rita in 2006, the Corps set out to build a flood risk reduction system surrounding the New Orleans metropolitan area known as the Hurricane and Storm Damage Risk Reduction System (“HSDRRS”). During construction of the $14.5 billion project, various wetland habitats, including wildlife refuges in the area, were damaged. The Clean Water Act (“CWA”) and the Water Resources Development Act of 1986 (“WRDA”), as amended, require that the Corps, as would any private party, act to mitigate such damage by implementing a plan to offset environmental impacts. Specifically, the Corps is required to ensure that impacts to a particular habitat are mitigated through measures to preserve that same type of habitat.

Required habitat mitigation can be accomplished through different means, including mitigation banking (buying credits from an authorized “bank”), contracting with an “in- *539 lieu” fee provider (explained below), or through a Corps-constructed restoration project. In the case of mitigation banking, the credit provider places a permanent encumbrance on its land in exchange for a certain amount of credits, which it can then sell to private developers, or, in this case, to the Corps itself. A second option, not relevant in this case, is the use of in-lieu fee providers, where the credit provider is given provisional' credits that it can market. Once it completes a transaction, the in-lieu fee provider then has the responsibility of securing land and placing a conservation easement on that land, See generally Pioneer Reserve, LLC v. United States, 128 Fed.Cl. 483 (2016). A third option for the Corps here was that it could design and implement its own restoration project. The mitigation plan adopted by the Corps in this case included both the purchase of mitigation credits and Corps-constructed restoration projects.

One factor limiting the Corps’ options was a policy of the United States Fish and Wildlife Service to the effect that, when the impacts occur on national wildlife refuge property, mitigation also must take place on refuge property. See Final Policy on the National Wildlife Refuge System and Compensatory Mitigation under the Section 10/404 Program, 64 Fed. Reg. 49229 (September 10, 1999). As a practical matter, this policy had the effect of removing the option of purchasing private mitigation banking credits in order to mitigate for environmental impacts occurring on national wildlife refuge property.

The Corps’ initial proposed mitigation plan was described and evaluated in Programmatic Individual Environmental Report # 36 (“PIER # 36”), which was prepared in accordance with the National Environmental Policy Act, 42 U.S.C. §§ 4321-4370h (2012). PIER # 36’s stated purpose was to compensate for habitat losses caused by the construction of HSDRRS. It addressed six types of habitats: swamp, bottomland hardwood (“BLH”) — dry, BLH — wet, fresh marsh, intermediate marsh, and brackish marsh. PIER # 36 proposed to meet nearly 40% of its total mitigation needs through the purchase of mitigation credits for the swamp and BLH wet/dry habitat impacts. In relevant part, the plan also proposed that the Bayou Sauvage Marsh Restoration project would provide all the necessary mitigation for both on- and off-refuge brackish marsh impacts. This plan meant that EIP would not be able to sell the brackish marsh mitigation credits generated by its Chef Menteur' Pass Mitigation Bank (“Chef Bank”) in connection with the mitigation plan. PIER # 36 was released for public review and comment from August 12, 2013 to September 25, 2013. During this time, EIP made a number of comments, including a recommendation that PIER #36 recognize its Chef Bank “as a source of brackish marsh mitigation available for HSDRRS use either as the preferred alternative (subject to credit availability and price at time of solicitation) or at least as a source of alternative mitigation if the corps-constructed alternatives prove to be unfeasible or overly expenses.” AR 1509.

On October 20, 2015, the Corps issued the Individual Environmental Report Prepared to Supplement: Programmatic Individual Environmental Report (PIER) 36 Bayou Sauvage, Turtle Bayou & New Zydeco Ridge Restoration Project Saint Tammany & Orleans Parishes, Louisiana PIER 36, Supplement 1 (“SIER 1”). SIER 1 explained that, due to increased cost estimates, the Bayou Sauvage Marsh Restoration project was no longer considered feasible. The Corps decided to move the location of these restoration features within the same area in order to lower the cost of the project. SIER 1 stated that “[t]his relocation brought the cost of the project back down such that the exploration of other options to mitigate the requirement was unnecessary.” AR 1924.

The new Bayou Sauyage Floodside Brackish Marsh project, however, only met roughly 81% of the Corps’ brackish marsh mitigation needs.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Weeks Marine, Inc. v. United States
575 F.3d 1352 (Federal Circuit, 2009)
Distributed Solutions, Inc. v. United States
539 F.3d 1340 (Federal Circuit, 2008)
Blue & Gold Fleet, L.P. v. United States
492 F.3d 1308 (Federal Circuit, 2007)
Rex Service Corp. v. United States
448 F.3d 1305 (Federal Circuit, 2006)
Ramcor Services Group, Inc. v. United States
185 F.3d 1286 (Federal Circuit, 1999)
Vfa, Inc. v. United States
118 Fed. Cl. 735 (Federal Claims, 2014)
Bannum, Inc. v. United States
779 F.3d 1376 (Federal Circuit, 2015)
Pioneer Reserve, LLC v. United States
128 Fed. Cl. 483 (Federal Claims, 2016)
CCL, Inc. v. United States
42 Cont. Cas. Fed. 77,237 (Federal Claims, 1997)
Labat-Anderson, Inc. v. United States
65 Fed. Cl. 570 (Federal Claims, 2005)

Cite This Page — Counsel Stack

Bluebook (online)
130 Fed. Cl. 537, 2017 U.S. Claims LEXIS 62, 2017 WL 475706, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ecosystem-investment-partners-v-united-states-uscfc-2017.