Ecology Center, Inc. v. Russell

361 F. Supp. 2d 1310, 2005 U.S. Dist. LEXIS 8297, 2005 WL 677790
CourtDistrict Court, D. Utah
DecidedMarch 23, 2005
Docket2:03-cv-00589
StatusPublished
Cited by1 cases

This text of 361 F. Supp. 2d 1310 (Ecology Center, Inc. v. Russell) is published on Counsel Stack Legal Research, covering District Court, D. Utah primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ecology Center, Inc. v. Russell, 361 F. Supp. 2d 1310, 2005 U.S. Dist. LEXIS 8297, 2005 WL 677790 (D. Utah 2005).

Opinion

MEMORANDUM DECISION AND ORDER GRANTING DEFENDANTS’ MOTION TO DISMISS

STEWART, District Judge.

The instant case is a Petition for Review of Agency Action, brought by The Ecology Center and The Aquarius Escalante Foundation (Plaintiffs). Plaintiffs seek review of a Record of Decision (ROD) issued by the Acting Forest Supervisor of the Dixie National Forest (the DNF), an agency of the United States Department of Agriculture. The decision in question is the final approval by the DNF of the Griffin Springs Resource Management Project, (the Project) in which the DNF approved a plan to allow logging in the Griffin Springs area of the DNF. Plaintiffs seek declaratory and injunctive relief to stop the implementation of the plan, claiming that the ROD violates the National Environmental Policy Act (NEPA), the National Forest Management Act (NFMA), and the Administrative Procedures Act (APA). The case comes before the Court on Defendants’ Motion to Dismiss. In addition to the original Petition for Review and the memoranda supporting the Motion to Dismiss, the Court also considers arguments set forth in an amicus brief, submitted by the Utah Division of Forestry and several Utah counties. After the Court heard oral argument on this Motion, the Tenth Circuit case Utah Environmental Congress v. Bosworth, 372 F.3d 1219 (10th Cir.2004) was published. The Court gave counsel the opportunity to file supplemental briefs responding to the Bosworth decision.

The Court reviews the agency decision under an arbitrary and capricious standard. This entails an inquiry by the Court as to whether the agency has “considered the relevant factors, and articulated a satisfactory explanation for its action including a rational connection between the facts found and the choice made.” Penobscot Air Servs., Ltd. v. Federal Aviation Admin., 164 F.3d 713, 719 (1st Cir.1999)(internal quotations and citations omitted). Thus, if the Court finds that the agency’s decision is supported by the facts in the *1312 record, and is not contrary to law, the Court should affirm the agency’s decision.

The Court’s analysis of the instant motion is divided into three sections: a description of the Project, the objections raised by Plaintiffs to the Project and analysis of those objections, and a conclusion.

The Court will grant Defendants’ Motion to Dismiss, for the reasons hereafter stated.

I. The Project

The Project is a vegetation management proposal that encompasses an area of 11,-885 acres of aspen and spruce/fir trees on the Aquarius Plateau of the DNF. The Forest Service (FS) believes that 3,651 acres within the Project exceed maximum levels of tree density, and 2,990 acres are approaching maximum levels of tree density. According to the FS, this density causes declines in tree growth and vigor. Further, much of the aspen growth is threatened by spruce and fir trees, which have thrown off the balance between the varieties of trees. The FS claims that the Project is designed to counter both of these trends by thinning certain areas of certain kinds and ages of trees.

The logging in the Project will consist of an initial phase of clearcut harvesting, involving 112 acres. The FS will then use prescribed fire to stimulate aspen growth. Finally, commercial loggers will apply thinning to timber across 3,307 acres.

II. The Objections Raised By Plaintiffs and the Court’s Analyses Thereof

The legal framework governing this dispute is provided by NFMA and NEPA. NFMA requires the FS to develop a “land and resource management plan” (Forest Plan) for each unit of the National Forest Service. The Forest Plan for the DNF was adopted in 1986. It provides, among other things, that seven to ten percent of each drainage in the forest should be maintained as old growth. 1

Implementation of the Forest Plan occurs on a project-by-project basis. Only at the project level does the FS make a firm commitment of resources. Each project must be consistent with the Forest Plan and analyzed pursuant to NEPA.

NEPA is a procedural statute which requires federal agencies to make informed analyses of the environmental impacts of their actions. See 42 U.S.C. § 4332(2)(C). Specifically, when a federal agency proposes to undertake a “major Federal action significantly affecting the quality of the human environment,” NEPA requires the agency to prepare an Environmental Impact Statement (EIS). Id. Prior to the approval of the Project, the FS undertook both an EIS and a Supplemental EIS (SEIS). The SEIS was required so that the FS could consider new information that was presented in a report entitled, Life History and Analysis of Endangered, Threatened, Candidate, Sensitive and Management Indicator Species for the Dixie National Forest. A substantial administrative record (AR) was created by the FS in preparing the EIS and the SEIS prior to the approval of the ROD.

The Plaintiffs’ objections to the ROD for the Project are contained in Plaintiffs’ Petition For Review of Agency Action. They will be taken up in the order that they *1313 appear therein. 2

1. The Forest Service Is Required By Law To Fully Disclose and Thoroughly Analyze All Potential Adverse Environmental Impacts of Timber Harvest

Plaintiffs make unsubstantiated assertions in this objection about the failure of the FS to “demonstrate consistency of the Griffin Springs Project with the DNF Forest Plan,” the failure of the FS to take “a hard look at many critical issues” and they allege that “the FEIS for the Project is based on myriad expert conclusions that lack the kind of credible, hard quantitative data that is necessary to inform the public and the courts of the basis for these conclusions.”

With no citation to the AR or any supporting argument, the Court is unable to discern what is being objected to and for what reason. The deference provided to the agency is substantial and the burden of proof is on the Plaintiffs to prove their objections are valid. Park County Resource Council, Inc. v. U.S. Department of Agriculture, 817 F.2d 609, 621 (10th Cir.1987) overruled on other grounds, Village of Los Ranchos de Albuquerque v. Marsh, 956 F.2d 970 (10th Cir.) cert. denied, 506 U.S. 817, 113 S.Ct. 59, 121 L.Ed.2d 27 (1992). Plaintiffs have made no effort to carry their burden of proof on the specific claims made in this objection, except to the extent that the substance of these general objections are contained in the two objections discussed in sections two and three.

2.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Utah Environmental Congress v. Richmond
483 F.3d 1127 (Tenth Circuit, 2007)

Cite This Page — Counsel Stack

Bluebook (online)
361 F. Supp. 2d 1310, 2005 U.S. Dist. LEXIS 8297, 2005 WL 677790, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ecology-center-inc-v-russell-utd-2005.