Eckre v. Public Service Commission

247 N.W.2d 656, 1976 WL 352287
CourtNorth Dakota Supreme Court
DecidedNovember 30, 1976
DocketCiv. 9225
StatusPublished
Cited by12 cases

This text of 247 N.W.2d 656 (Eckre v. Public Service Commission) is published on Counsel Stack Legal Research, covering North Dakota Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Eckre v. Public Service Commission, 247 N.W.2d 656, 1976 WL 352287 (N.D. 1976).

Opinions

PAULSON, Judge.

This appeal is from the April 20, 1976, judgment of the district court of Burleigh County granting to the plaintiffs [hereinafter Landowners] a peremptory writ of mandamus compelling defendant Public Service Commission of the State of North Dakota [hereinafter the PSC] to withdraw, as improperly granted, the PSC’s order in the matter of the application of intervenor-defendant Dome Pipeline Corporation [hereinafter Dome] for a certificate of public convenience and necessity granted May 1, 1972, for the construction and operation of a common carrier pipeline; and which certificate was amended on August 22, 1973, and on September 10, 1974. In addition, the judgment ordered the PSC to “begin anew” in the matter of the application of Dome for such certificate and to include a proper notice and afford an opportunity to be heard to interested parties, specifically including the Landowners herein; and the judgment further ordered the PSC to make new findings of fact, conclusions of law, and orders based solely upon evidence presented to the PSC. Both the PSC and Dome appeal from the judgment and the writ of mandamus.

The facts herein are not disputed. On February 11, 1972, Dome filed an application with the PSC wherein Dome requested the authority to construct and operate a pipeline and related facilities in the State of North Dakota. On February 18, 1972, the PSC sent notice of hearing to other public utilities in the area of the proposed pipeline, and to the chairman of the board of county [661]*661commissioners of each county traversed by said pipeline. Also, on February 18, 1972, the PSC forwarded a copy of the notice of hearing in the form of a general news release to the official county newspaper of each county affected by said pipeline, but did not request such notice to be published as a legal publication in any of such newspapers. On March 16, 1972, a hearing on the application of Dome for a certificate of public convenience and necessity for the construction and operation of a common carrier pipeline was held before the PSC at Bismarck. On May 1,1972, the PSC issued a certificate of public convenience and necessity to Dome, subject, among other conditions, to the following: (1) that the applicant begin construction not later than September of 1973; and (2) that the pipeline be constructed along the basic route outlined by exhibits filed at the March 16, 1972, hearing. The initial certificate authorized Dome to construct a single 16-inch pipeline.

On July 27, 1973, Dome filed a petition with the PSC advising the PSC that Dome could not meet the requirements of PSC’s order insofar as commencing construction of the proposed pipeline before September of 1973, and indicated that the pipeline would now consist of two parallel lines, one of them 10 inches in diameter and the other one 12 inches in diameter, rather than the originally proposed single 16-inch line. Accordingly, the PSC, without notice or hearing, issued an amended order dated August 22, 1973, wherein the PSC authorized construction and operation of the common carrier pipeline in accordance with Dome’s petition of July 27, 1973, and ordered that construction begin not later than September of 1974.

On September 6, 1974, Dome filed another petition with the PSC wherein Dome requested further extension of its certificate of public convenience and necessity to permit Dome to commence construction of the proposed pipeline no later than August 31, 1975. In accordance with such request, the PSC, on September 10, 1974, issued another amended order, approving Dome’s request of September 6, 1974.

The Landowners herein were never served with notice or other process, nor did they have actual notice of the initial hearing before the PSC held on March 16, 1972; nor did the Landowners receive notice prior to the issuance of the PSC’s respective amended orders of August 22, 1973, and September 10, 1974.

The Landowners, having been contacted by representatives of Dome and having refused to negotiate the sale of their property to Dome, are all defendants in eminent domain cases now pending in the district courts of Ransom and Richland Counties.

On January 6,1976, the Landowners filed a petition for a writ of mandamus with the district court of Burleigh County, seeking to compel the PSC to withdraw the certificate of public convenience and necessity previously granted to Dome; to require the PSC to rehear Dome’s application, giving adequate notice to and affording opportunity for interested parties to be heard; and, thereafter, to issue new findings of fact, conclusions of law, and orders based upon evidence to be adduced at the new hearing. The PSC resisted the Landowners’ petition, and Dome, as an intervenor, joined with the PSC. The district court entered its judgment and granted the writ of mandamus dated April 20, 1976, ordering the PSC “to begin anew”. Both the PSC and Dome perfected timely appeals from the judgment and the writ of mandamus to this court.

In order to determine whether the writ of mandamus was properly issued in the instant case, this court must affirmatively find: (1) that the Burleigh County District Court had jurisdiction to hear the Landowners’ petition for a writ of mandamus; (2) that the Landowners are proper parties to challenge the granting of a certificate of public convenience and necessity to a common pipeline carrier project; (3) that a common pipeline carrier is required to obtain a certificate of public convenience prior to the construction or operation of a pipeline; (4) that there was a legal duty to give notice to the landowners within the projected pipeline right-of-way prior to the PSC [662]*662hearing on Dome’s application for a certificate of public convenience and necessity; and (5) that mandamus was an appropriate remedy to compel such notice.

I.

Both Dome and the PSC contend that, since eminent domain proceedings were initiated in the district courts of Ransom and Richland Counties prior to the commencement of this action in Burleigh County District Court, the Burleigh County District Court was without jurisdiction to hear the Landowners’ petition for a writ of mandamus. We find no merit in this contention.

Questioning the propriety of the issuance of a certificate of public convenience and necessity by the PSC would have been' improper in any district court other than in the district court of the county in which the hearing was held on Dome’s application for a certificate of public convenience and necessity. Section 49-05-12, N.D.C.C., provides that an appeal from proceedings of the PSC shall be taken in the manner prescribed by Chapter 28-32, N.D.C.C., the Administrative Agencies Practice Act. Section 28-32-15, N.D.C.C., of such Act, in pertinent part, states:

“ . . . Such appeal may be taken to the district court designated by law, and if none is designated, then to the district court of the county wherein the hearing or a part thereof was held. . . . ”

In the instant case, the hearing on Dome’s application for a certificate of public convenience and necessity was held in Burleigh County — thus the Burleigh County District Court was the only district court with jurisdiction to hear the instant case.

II.

Both the PSC and Dome question the Landowners’ standing to challenge the PSC’s issuance of a certificate of public convenience and necessity. This court has recently examined the use of the principle of standing to obstruct judicial review of administrative agency action, in Citizens State Bank of Neche v. Bank of Hamilton,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Minn-Kota Ag Products, Inc. v. N.D. Public Service Commission
2020 ND 12 (North Dakota Supreme Court, 2020)
Owego Township v. Pfingsten
2018 ND 68 (North Dakota Supreme Court, 2018)
Shark v. Northern States Power Co.
477 N.W.2d 251 (North Dakota Supreme Court, 1991)
Mini Mart, Inc. v. City of Minot
347 N.W.2d 131 (North Dakota Supreme Court, 1984)
Minnkota Power Cooperative, Inc. v. Lake Shure Properties
289 N.W.2d 230 (North Dakota Supreme Court, 1980)
Dorgan v. Mercil
269 N.W.2d 99 (North Dakota Supreme Court, 1978)
Leonard v. Medlang
264 N.W.2d 481 (North Dakota Supreme Court, 1978)
Reliance Insurance Co. v. Public Service Commission
250 N.W.2d 918 (North Dakota Supreme Court, 1977)
Eckre v. Public Service Commission
247 N.W.2d 656 (North Dakota Supreme Court, 1976)

Cite This Page — Counsel Stack

Bluebook (online)
247 N.W.2d 656, 1976 WL 352287, Counsel Stack Legal Research, https://law.counselstack.com/opinion/eckre-v-public-service-commission-nd-1976.