ECIMOS, LLC v. Carrier Corporation

CourtDistrict Court, W.D. Tennessee
DecidedAugust 17, 2020
Docket2:15-cv-02726
StatusUnknown

This text of ECIMOS, LLC v. Carrier Corporation (ECIMOS, LLC v. Carrier Corporation) is published on Counsel Stack Legal Research, covering District Court, W.D. Tennessee primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
ECIMOS, LLC v. Carrier Corporation, (W.D. Tenn. 2020).

Opinion

IN THE UNITED STATES DISTRICT COURT FOR THE WESTERN DISTRICT OF TENNESSEE WESTERN DIVISION

ECIMOS, LLC, ) ) Plaintiff, ) ) Case No. 2:15-cv-2726-JPM-cgc v. ) ) CARRIER CORPORATION, ) ) Defendant. )

ORDER DENYING CARRIER’S MOTION FOR EXTENSION OF TIME AND ORDER REDUCING PENALTIES

Before the Court is Carrier’s Motion for Extension of Time or, in the Alternative, Motion to Reduce Penalties, filed on August 13, 2020. (ECF No. 601.) Carrier moves the Court for an extension of time to complete the rollout of the non-infringing run-test software and database, asserting that: (1) it has acted diligently to install the non-infringing run-test software and database; (2) it has experienced delays that could not have been fully appreciated at the time when it provided its two-week rollout plan to the Court; (3) delays caused by the COVID-19 Pandemic have impeded Carrier’s ability to complete rollout within the Court’s two-week schedule; and (4) not granting the extension would harm innocent third parties. (See id. at PageID 13720–25.) Second, Carrier argues that the Court’s escalating penalty structure, starting at $500,000 and increasing by $250,000 each week, is an improper valuation of ECIMOS’s licensing fee for Carrier’s continued use of ECIMOS’s intellectual property, and that the penalty violates both the Due Process and the Excessive Fines Clauses of the United States Constitution. (See id. at PageID 13725–31.) Carrier recommends that if the Court is inclined to reduce the sanction, it should reduce the award to $25,000 per week, totaling $100,000 per month. (Id. at PageID 13731.)

ECIMOS filed its Expedited Response on August 13, 2020. (ECF No. 606.) ECIMOS rejects Carrier’s proposal and asserts that the Court’s Order is appropriate and properly penalizes Carrier for its continued delays. (See generally id.)

The Court held a hearing on the Motion on August 14, 2020 at 9:30 a.m. Present were counsel for ECIMOS and Carrier, as well as the Special Master Nik Baer. The Court heard a status update1 on the rollout from the Special Master and testimony from Lisa Oliver, Carrier’s rollout project manager, and William Jeffrey Carr, ECIMOS’s technical expert. For the reasons provided at the hearing and for the reasons set forth below, the Court

DENIES IN PART and GRANTS IN PART Carrier’s Motion. August 17, 2020 will remain the deadline for completion of the rollout of the non-infringing run test software and database at Carrier’s Collierville, Tennessee plant. The Court will modify the Order on Rollout Plan (ECF No. 588) to direct the payment of the potential penalty to the Court and to reduce the amount of the sanction to $250,000 per week with no escalating penalty structure.

I. Background On November 26, 2018, the Court entered the Judgment and Permanent Injunction in this case. (Judgment and Permanent Injunction, ECF No. 400.) Carrier was enjoined from using ECIMOS’s RES run-test software and database in its Collierville, Tennessee plant, but the Court stayed enforcement of the injunction until Carrier was able to develop a replacement

1 The Special Master’s August 13, 2020 Report has been docketed and can be found at ECF No. 605. non-infringing run-test software and database. (Id. at PageID 11050–51.) Carrier was ordered to pay ECIMOS a $50 per run-test station monthly fee each month the RES run-test software and database were still in use at Carrier’s Collierville plant. (Id.)

The process of developing the new run-test software and database has been ongoing since the judgment was entered in November 2018. Development of the DSA software was completed in February 2020. (See Special Master’s Sixteenth Report, ECF 547 at PageID 12654 (discussing completion of families 1 through 14 of requirements).) Carrier was to submit a proposed rollout plan on March 12, 2020. (Order Setting Schedule, ECF No. 548 at PageID 12704.) A status conference to review Carrier’s proposed rollout plan was set for

April 2, 2020. (Id.) The COVID-19 pandemic prompted a change to the testing and rollout schedules. (See Setting Letter, ECF No. 555.) The Court held a status conference on May 5, 2020 to review the testing schedule proposed by Carrier. (See May 5, 2020 Min., ECF No. 563.) During the conference, Carrier requested that the Court allow DSA to continue the

development of new families of requirements, despite the completion of the development of families of requirements for the non-infringing run-test software and database. (See Order Following Conference, ECF No. 567.) ECIMOS objected to the development of additional requirements during the testing phase of the litigation. (Id.) The Court overruled ECIMOS’s objections and granted Carrier’s request for additional time to complete testing and the development of these new requirements.2 (Id.) Based on the presentation of the Parties, the Court adopted a schedule requiring Carrier to begin testing by no later than June 22, 2020 and

2 Carrier’s original proposed testing schedule anticipated that the testing of the new run-test software and database would begin on April 6, 2020 and would be completed by May 8, 2020. (Special Master’s Seventeenth Report, ECF No. 554 at PageID 12835.) to complete all testing by no later than July 27, 2020. (Id. at PageID 13668.) In accordance with the schedule, the deadline for development of new families of requirements was to coincide with the end of testing, that is, no later than July 27, 2020. (Id.)

Carrier did not complete the testing of the new non-infringing run-test software and databased and the development of new requirements by the July 27, 2020 deadline. (See Special Master’s Twenty-First Report, ECF No. 585 at PageID 13549–51; see also Order Following August 3, 2020 Conference, ECF No. 592 at PageID 13683.) A deadline of August 17, 2020 was then established for Carrier to come into full compliance with the November 26, 2018 Permanent Injunction. (Order Setting Deadline, ECF No. 586.) On July 29, 2020, an

Order on Rollout Plan for the Non-Infringing Run-Test Software and Database was entered adopting the two-week rollout time frame proposed by Carrier but providing for a line-by-line rollout rather than a station-by-station rollout. (ECF No. 588.) Specifically, rollout was to begin on August 3, 2020 and to be completed by no later than August 17, 2020. (Order on Rollout Plan, ECF No. 588 at PageID 13671.) Carrier’s failure to complete rollout by the August 17, 2020 deadline would lead to the imposition of a $500,000 weekly penalty, which would increase by $250,000 each additional week that Carrier failed to comply with the permanent injunction. (Id. at PageID 13673.)

The Court held a hearing on August 3, 2020 to review Carrier’s plan to meet the Court’s rollout schedule. (Min., ECF No. 591.) Carrier requested an additional exception to the Court’s Order that adopted the requirement that the development of new requirements be completed by no later than the July 27, 2020 deadline. (Id.) The Court granted a limited exception and allowed DSA to continue the development of the Opto-22 Snap and IO configuration requirements necessary for Carrier to operate production lines 6, 7, and 8 of its Collierville plant, despite the lack of diligence shown by Carrier during the testing and development phase of the new DSA database and software. (ECF No. 592 at PageID 13684.) Carrier also was required to pay ECIMOS a $50,000 licensing fee for its continued use of ECIMOS’s intellectual property. (Id.)

II. Discussion

A. Carrier’s Request for an Extension of Time An extension of time is not appropriate in this case. As the Court stated during the hearing, Carrier has failed to marshal the resources necessary to complete the development, testing, and rollout of the non-infringing run-test software and database.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Ex Parte Robinson
86 U.S. 505 (Supreme Court, 1874)
Gompers v. Bucks Stove & Range Co.
221 U.S. 418 (Supreme Court, 1911)
United States v. United Mine Workers of America
330 U.S. 258 (Supreme Court, 1947)
Austin v. United States
509 U.S. 602 (Supreme Court, 1993)
International Union, United Mine Workers v. Bagwell
512 U.S. 821 (Supreme Court, 1994)
United States v. Bajakajian
524 U.S. 321 (Supreme Court, 1998)
State Farm Mutual Automobile Insurance v. Campbell
538 U.S. 408 (Supreme Court, 2003)
David Hopper v. Phil Plummer
887 F.3d 744 (Sixth Circuit, 2018)
United States v. Tennessee
925 F. Supp. 1292 (W.D. Tennessee, 1995)
Roe v. Operation Rescue
919 F.2d 857 (Third Circuit, 1990)
Glover v. Johnson
934 F.2d 703 (Sixth Circuit, 1991)

Cite This Page — Counsel Stack

Bluebook (online)
ECIMOS, LLC v. Carrier Corporation, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ecimos-llc-v-carrier-corporation-tnwd-2020.