ECC International LLC

Armed Services Board of Contract Appeals·Decided February 20, 2015·No. ASBCA No. 58856·Published

Opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS

Appeals of -- ) ) ECC International LLC ) ASBCA No. 58856 ) Under Contract No. W912DQ-11-C-4009 )

APPEARANCE FOR THE APPELLANT: R. Dale Holmes, Esq. Amy M. Kirby, Esq. Cohen Seglias Pallas Greenhall & Furman PC Philadelphia, PA

APPEARANCES FOR THE GOVERNMENT: Thomas H. Gourlay, Jr., Esq. Engineer Chief Trial Attorney Daniel B. McConnell, Esq. Geoffrey A. Mueller, Esq. Regina L. Schowalter, Esq. Engineer Trial Attorneys U.S. Army Engineer District, Middle East Winchester, VA

OPINION BY ADMINISTRATIVE JUDGE O'SULLIVAN ON CROSS-MOTIONS FOR SUMMARY JUDGMENT

This appeal arises from a dispute between the parties over whether the contract required appellant to construct a vehicle refueling point (VRP) as part of the construction of a Military Police School at Camp Shaheen, Afghanistan. The government has moved for summary judgment on this issue. Appellant opposes the government's motion and has cross-moved for summary judgment. For the reasons stated below, we deny both parties' motions.

STATEMENT OF FACTS (SOF) FOR PURPOSES OF THE MOTIONS

1. On 24 February 2011, the U.S. Army Corps of Engineers issued Solicitation No. W912DQ-l l-R-4014 for the design and construction of the Afghan National Army Military Police and Personal Security Training School (MP School) and the Signal Training School (Signal School) at Camp Shaheen, Balkh Province, 1 Afghanistan (Government's Statement of Undisputed Facts (gov't stmt.) ii 1.)

2. The solicitation contemplated a firm-fixed-price contract with four contract line item numbers (CLINs): one for design and construction of the MP School, one for design and construction of the Signal School, and two for Defense Base Act insurance applicable to each project (gov't stmt. ii 2).

3. CLIN 0001, for the MP School, states:

The contractor shall provide all Manpower, Materials, Equipment, and Coordination to the Design/Construction of Military Police and Personal Security Training School in accordance to the attached specifications. [See] PRICE 2 PROPOSAL SCHEDULE Military School. r l

CLIN 0001 provided a single line for insertion of a lump sum firm fixed price for the entire MP School project. (R4, tab 4 at 39)

4. The solicitation included a price proposal schedule for the MP School and a price proposal schedule for the Signal School. The price proposal schedule for the MP School was broken out by subCLINs (OOOlAl, 0001B2, etc.) that called out most, but not all, of the items of work contained in the specifications referenced in CLIN 0001. (Gov't stmt. ilil 3, 7; R4, tab 4 at 41-42)

5. The price proposal schedules contained the following statement at the top of the first page: "This Price Proposal Schedule is information supplemental to the CLIN and is not part of the contract" (R4, tab 4 at 41 ). The price proposal schedules also contained the following "PROPOSAL SCHEDULE NOTES" on the second page, following the list of bid items:

1 The government has filed a statement of undisputed facts in connection with its motion. Appellant has indicated where it agrees and where it does not agree with the government's statement. Along with its opposition, appellant has also filed a statement of undisputed facts, to which the government has not responded. References in this opinion to either document will be to those paragraphs that are not disputed. 2 By reference to CLIN 0003 for the Signal School, the word "See" was probably intended to precede the words "PRICE PROPOSAL SCHEDULE" in CLIN 0001, but was inadvertently omitted.

2 1. Offeror shall submit prices on all items. Scope of work on each items [sic] are [sic] described in Section 01010 and 01015 [the specifications].

2. Only the contract for the entire schedule will be awarded under this solicitation. This project will be awarded as a lump sum contract. This Proposal Schedule is an accounting tool for allocating funds to applicable budget.

(R4, tab 4 at 42)

6. The VRP was called out by the specifications and drawings to be constructed as part of the MP School. MP School specification section 01010, paragraph 4.12.3, Site Adapt Facilities, provided that "The contractor shall construct the Site Adapt Facilities listed below in conformance with the standard design drawings provided." The VRP was one of the site adapt facilities so listed, under Site Identifier Number 109. (Gov't stmt. iii! 9-11)

7. MP School specification section 01010, paragraph 4.12.12, Vehicle Re-Fueling Point, stated:

The Contractor shall construct a vehicle re-fueling point as shown in the fuel point standard drawings and as specified in Section 01015. It shall be located as shown in the plans. The Contractor shall provide a full supply of fuel to the tanks at the time of turnover to the Government. Vehicle Re-Fueling Point shall have a metal roof covering.

(Gov't stmt. ii 12)

8. Additional sections of the MP School specification provided requirements for the plumbing system and storage tanks related to the VRP; the contract also contained 18 drawings providing siting and construction information for the VRP (gov't stmt. i!i! 13-15).

9. Contract No. W912DQ-11-C-4009 (the contract) was awarded to ECC International LLC (ECCI) on 8 April 2011 in the total amount of $27,613,870.20. The price included $16,870,811.69 for the MP School and $10,583,106.11 for the Signal School. (Gov't stmt. iii! 16, 17)

3 10. ECCI submitted its 65% design for the MP School, which included the VRP, on 30 July 2011. On 3 February 2012, ECCI submitted its 100% design, which also included the VRP. (Gov't stmt. iii! 23-26) At some point, the ECCI program manager became aware that its design engineers were including the VRP in ECCI's submitted designs (app. mot., attach., affidavit of Scott Hayward (Hayward aff.) i! 16). He immediately directed that the Corps of Engineers be informed that ECCI did not consider the VRP to be part of the awarded contract work since it was not listed on the price proposal schedule for the MP School (id. i! 17).

11. The record is unclear on when the Corps was first informed of ECCI's position on the VRP. The first written notice in the record before the Board is a letter dated 10 September 2012 from ECCI to the Corps, stating:

This letter is to notify USACE that neither the detailed price schedule nor ECCI's price proposal included a Vehicle Refueling Point (VRP) for MP/Signal School. The detailed schedule listed all required buildings, utilities and site civil work required for the project, but failed to include a line item for the VRP that is described within the statement of work and drawings accompanying the solicitation. However, since there was no line item for the VRP and there is no other line item the VRP could be associated with; ECCI did not include any costs for this facility in our proposal.

ECCI concluded by saying it would need a contract modification to construct the VRP. (R4, tab 29)

12. The Corps did not agree. By letter dated 27 September 2012, the contracting officer responded that the requirement for the VRP was clearly identified in multiple locations in the contract drawings and specifications, and the fact that it was not listed separately in the price proposal schedule was irrelevant (R4, tab 30). The contracting officer stated that "It is neither expected nor required of the Government to list each and every feature of work as a separate line item in the price schedule of the RFP.... It is solely up to the contractor to decide how to incorporate the costs of the contract requirements into the contractor's price proposal." Thus, the government would not be issuing a contract modification for the VRP, and would insist that ECCI construct it. ECCI was invited to submit a claim if it disagreed. (Id.)

13.

Free access — add to your briefcase to read the full text and ask questions with AI

ECC International LLC, (asbca 2015).