ECC International Constructors, LLC

Armed Services Board of Contract Appeals·Decided November 9, 2021·No. ASBCA No. 59643·Published

Opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS Appeal of - ) ) ECC International Constructors, LLC ) ASBCA No. 59643 ) Under Contract No. W912ER-10-C-0054 )

APPEARANCES FOR THE APPELLANT: R. Dale Holmes, Esq. Michael H. Payne, Esq. Cohen Seglias Pallas Greenhall & Furman PC Philadelphia, PA

APPEARANCES FOR THE GOVERNMENT: Michael P. Goodman, Esq. Engineer Chief Trial Attorney Sarah L. Hinkle, Esq. Geoffrey A. Mueller, Esq. Kathryn G. Morris, Esq. Matthew Tilghman, Esq. Engineer Trial Attorneys U.S. Army Engineer District, Middle East Winchester, VA

OPINION BY ADMINISTRATIVE JUDGE MCILMAIL ON THE GOVERNMENT’S PARTIAL MOTION TO DISMISS FOR LACK OF JURISDICTION

The government moves for the dismissal of parts of the appeal for lack of jurisdiction, saying that appellant, ECC International Constructors, LLC (ECCI), did not provide sums certain for what the government (U.S. Army Corps of Engineers or USACE) says are separate claims.

STATEMENT OF FACTS FOR PURPOSES OF THE MOTION

In September 2010, the parties contracted for ECCI to design and construct a military compound in Afghanistan (R4, tab 5 at 2, 179 § 1.1). On May 2, 2014, ECCI submitted to the contracting officer a demand for $3,767,856.32 “for the design, procurement, logistics and construction cost impacts directly attributable to the extra work caused and directed by the Government during execution of the project,” more specifically: (1) design costs; (2) material procurement, shipping and labor costs associated with communications systems; (3) material procurement, shipping and labor costs associated with electrical systems; (4) material procurement, shipping and labor costs associated with heating ventilation and air conditioning (HVAC) systems; and (5) miscellaneous extra work (R4, tab 75 at 6). The submission further breaks the $3,767,856.32 demand amount into 23 direct cost items totaling $3,212,831.76, before adding general and administrative costs, fee, and bond, to arrive at the claimed total amount of $3,767,856.32 (R4, tab 75 at 55, 77-78). The government challenges the Board’s jurisdiction to entertain nine of those direct cost items: (1) Additional Outlets and Changed Configurations; (2) Additional and Changed Flexible Metal Conduit; (3) Legrand Raised Floor Communications Outlets; (4) 144 Port Fiber Optic Combination Units; (5) Trunk and Splice OSP Configuration, (6) Changed Direction Regarding Design and Provision of Uninterruptible Power Supply (UPS) System; (7) UL/R410 HVAC and Change to Accommodate Schedule; (8) Server Cabinets and Relay Racks; and (9) Additional Ladder Rack and Cable Tray (gov’t mot. at 4-5).

1. Additional Voice/Data and Printer Outlets and Changes to Configuration of Non-Office Outlets

In its submission to the contracting officer, ECCI makes a single request for $989,042.80 for (at least): (1) the government’s alleged “direction to ‘round up’ the number of outlets in each space determined by dividing the floor area of a particular office by the [contract] outlet density when the calculation resulted in less than a whole number”; (2) the government’s alleged direction to provide “two voice and two data connectors” every 4.5 square meters of floor area in certain office spaces; (3) the government’s alleged direction “to provide a standard ‘Office’ wall outlet with two voice and two data outlets in a six-plex plate in all non-office spaces”; (4) the government’s alleged direction that “raised access floor areas in the [Tactical Operations Center (TOC)] be equipped with one Secure, one Above Secret and one Non-Secure raised floor box per 4.6 square meters of raised floor area”; and (5) the government’s alleged direction that ECCI provide additional non-Secure and Secure printer outlets (R4, tab 75 at 15-18).

a. Rounding Up

With respect to “rounding up,” ECCI in its submission to the contracting officer states:

The communications systems design reviewer directed that all room outlet calculations need to be reviewed to “ensure the number meets the requirements of [the contract].” A follow up review conference revealed that the reviewer was insisting on implementation of his interpretation of the contract requirements regarding the number of outlets required in each building. Essentially, he was directing that the outlets density provisions in [the contract] be implemented with complete disregard of other applicable contract provisions or conditions. This included his direction to “round up” the number of outlets in each space determined by dividing the

2 floor area of a particular office by [the contract] outlet density when the calculation resulted in less than a whole number.

(R4, tab 75 at 15)

b. Two Voice and Two Data Connectors Every 4.5 Square Meters

With respect to two voice and two data connectors every 4.5 square meters of floor area in certain office spaces, ECCI states:

The I3A (Department of the Army, Technical Criteria for the Installation Information Infrastructure Architecture), Paragraph 2.3.5.2, QUARTERS requires an outlet with just one connector compared to the two connectors in ECCI’s original design and the four connectors directed by the Government. The I3A states,

“For U.S. Army barracks projects, provide one 8-pin modular (RJ45 type) connector in a single gang outlet faceplate, labeled voice use, and one CATV outlet per sleeping/living area.”

So the communications system design reviewer’s direction . . . results in four times the cable and keystone modules required by the I3A and two times the number proposed in ECCI’s design.

...

So while the Government was directing ECCI install a barracks communications system costing more than four times the Army’s normal barracks communication system, there was apparently no requirement at all. The Government also directed the same outlet configuration for sleeping rooms in other buildings . . . .

Similarly, for non-barracks, non-office spaces, the I3A only requires one voice and one data connector. And finally, the I3A only requires one outlet with one each voice and one data connector every 7.5 square meters of floor area in Headquarters, Administrative and Office spaces as compared to the 4.5 square meters and two voice and two data

3 connectors the communications system design reviewer directed.

(R4, tab 75 at 16-17 (italics in original))

c. Additional Non-Secure and Secure Printer Outlets

With respect to the government’s alleged direction that ECCI provide additional non-Secure and Secure printer outlets, ECCI states:

[T]he Government communications design reviewer directed ECCI to provide a standard “Office” wall outlet with two voice and two data outlets in a six-plex plate in all non-office spaces. However, the barracks rooms, sleeping rooms in other buildings, maintenance spaces, game rooms, etc. throughout the project are not offices, and the contract is silent regarding the outlet configuration for non-office spaces except for those with raised computer flooring.

(R4, tab 75 at 16)

d. Raised Access Floor Areas in the TOC Be Equipped with One Secure, One Above Secret and one Non-Secure Raised Floor Box Per 4.6 Square Meters

With respect to the government’s alleged direction that “raised access floor areas in the TOC be equipped with one Secure, one Above Secret and one Non-Secure raised floor box per 4.6 square meters of raised floor area,” ECCI states:

The communications system design reviewer also directed that raised access floor areas in the TOC be equipped with one Secure, on Above Secret and one Non-Secure raised floor box per 4.6 square meters of raised floor area, equating to 30 outlet groups in each of the four TOC open work areas, which have a calculated . . . occupancy of 15.

Free access — add to your briefcase to read the full text and ask questions with AI

ECC International Constructors, LLC, (asbca 2021).

ECC International Constructors, LLC (ECC International Constructors, LLC) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

§ 7101-7109
41 U.S.C. § 7101-7109
§ 7101
41 U.S.C. § 7101