Eberle v. Connecticut Light and Power Co.

15 Conn. Super. Ct. 162, 15 Conn. Supp. 162, 1947 Conn. Super. LEXIS 76
CourtConnecticut Superior Court
DecidedJuly 14, 1947
DocketFile 14691
StatusPublished
Cited by1 cases

This text of 15 Conn. Super. Ct. 162 (Eberle v. Connecticut Light and Power Co.) is published on Counsel Stack Legal Research, covering Connecticut Superior Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Eberle v. Connecticut Light and Power Co., 15 Conn. Super. Ct. 162, 15 Conn. Supp. 162, 1947 Conn. Super. LEXIS 76 (Colo. Ct. App. 1947).

Opinion

CORNELL, J.

On or about June 9, 1941, the Federal Works Administration, in the exercise of powers conferred upon it by act of Congress contracted with defendant, John H. Eisele Company, Incorporated (hereinafter referred to as the “general contractor”) for the erection of three hundred housing units on Hamilton Avenue and vicinity in Waterbury in this state. The work was “Project Number Conn. 6041.” Included among these structures was one having six apartments, one of which apartments was designated 158 Proctor Street. The plumbing work and, of pertinency here, the gas piping within the units, was done by William L. Harmonay Company, also a corporation of the state of New York (hereinafter identified as the “sub-contractor”) under a subcontract with the general contractor. The gas supply to this, as well as to all the units was furnished by defendant, Connecticut Light & Power Co., a public utility corporation of the state of Connecticut, hereinafter referred to as the “utility.”

Only persons employed in factories engaged in defense work, and their families, were eligible to rent the several apartments contained in the project. As the work proceeded and apartments were made available, they were rented as speedily as possible. In this respect, the practice was: As a unit neared completion, the project manager notified the development manager of that fact, whereupon the latter forwarded -notices to eligible persons awaiting housing facilities that they might inspect and apply to rent, apartments in the same. On February 6, 1942, the Public Building Administration (the construction agency) and the Division of Defense Housing (the management agency) *164 entered into a written agreement whereby the former represented thait the unit which included the apartment known as 158 Proctor Street would be ready for use and occupancy on February 11, 1942 and the latter agreed to accept the same as of that date. Attached to this document was a list of various defects and omissions in the work certified by the project engineer (who was a representative of the United States government) among which was “1. Test and correct all mechanical equipment, gas, water lines, air ducts, electric wiring and fixtures.” The general contractor did not execute the document on February 6, 1942 but did so shortly after that date and before February 11, 1942, and also with the project engineer and the housing manager signed a certification to the effect that: “. . . this acceptance does not relieve the contractor of fulfillment of any of the obligations to the contract.” Such a notice had been' given to the development manager on February 2, 1942 and the latter at once advised eligible persons that the unit in question would be available for inspection as rentals ■on February 6, 1942.

Plaintiff, among about forty, responded' and after inspecting several of the units, applied for the apartment known as 158 Proctor Street. On February 6, 1942, a lease was executed between Federal Works Agency and plaintiff, dated as of that day, but to commence on March 1, 1942 and terminate on the last day of that month. It also provided that: “The tenant shall have the right to occupy the premises during the period from February 18, 1942 to the commencement of the term hereof” at the same rental as fixed for March, prorated. It was in contemplation of the parties, that the rental would thereafter continue on a month to month basis commencing wth the first day of each month. Plaintiff paid at that time the equivalent of the rental charge prorated for March, and that for the period, February 18 to February 28, together with utility services which were included in the rental charge. When plaintiff executed the lease he supposed that all fixtures were connected, that the apartment was in tenantable condition and that water, gas and electricity were in supply. Of these, however only electricity had been then connected into the house.

At the time that the lease was executed plaintiff informed the project manager, that his furniture was in Pennslyvania and would not be delivered to the house until the following Tuesday, which was February 10. He requested and the manager granted him permission to move a cot into the apartment *165 and to stay there until his family arrived and household necessities were delivered. It was the practice of the housing manager, in any event, to insist that persons leasing any of the apartments light and maintain a fire in the furnace in same one or two days 'before taking occupancy after the water was made available to insure against the pipes freezing.

On Saturday afternoon, February 7, 1942, about 5 p. m. plaintiff caused the cot to be delivered and placed in the kitchen and he slept there that night. Electricity was available for lighting, although there was a shortage of bulbs, and he was under the impression that water and gas were, also. However, on attemptnig to use the bathroom on the next morning he discovered that the fixtures there were not connected. Plaintiff worked on the following day, (Sunday, February 8) and en-route to his return to the apartment, about 5 p. m. stopped at the project office to inform the maintenance manager of than fact and that, apparently, no gas was available.

The gas supply for the house came from a main in the street laid by the defendant utility company. From this a pipe was run into a subcellar under the house and thence another to the utility room in the apartment. Three cocks controlled the flow of gas up to and including the last named point, viz., a curb cock in the street, a governor cock in the subcellar and a pet cock in the utility room which latter adjoins the kitchen and living room on the first floor and in which there was also situated a hot-air furnace, a coal bin and hot water tank. From the pet cock in the utility room one pipe connects with the hot water heater there; another runs down into the subcellar, continues horizontally for a short distance and then turns up, vertically, underneath the kitchen and after passing through the kitchen floor is connected to the gas stove in-that room, supplying fuel to it. It is found that the defendant’s general contractor’s subcontractor, which firm installed that part of the gas piping, neglected to affix a drip plug to the pipe at the point where it proceeds vertically upward from the horizontal section, to connect with the gas stove, leaving there an opening of about three-quarters of an inch through which, upon the opening of the pet cock in the utility room and the consequent admission of it to that portion of the line gas would escape.

Upon plaintiff’s complaint the maintenance manager came to plaintiff’s apartment and following the failure of an andeavor to *166 light the gas stove, went to the utility room to examine the position of the gas pet cock. At that time the curb cock and governor were open and the pet cock was closed so that while gas from the street main was admitted to the point where the pet cock was, it could not flow beyond that point unless the pet cock was opened wholly or partially. Applying a wrench to the pet cock the maintenance manager opened it to allow a full flow of gas to the kitchen stove, and then tried to light a burner therein.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Auriemme v. Bridgeport Gas Co.
144 A.2d 701 (Connecticut Superior Court, 1958)

Cite This Page — Counsel Stack

Bluebook (online)
15 Conn. Super. Ct. 162, 15 Conn. Supp. 162, 1947 Conn. Super. LEXIS 76, Counsel Stack Legal Research, https://law.counselstack.com/opinion/eberle-v-connecticut-light-and-power-co-connsuperct-1947.