Eazor Express, Inc. v. United States

483 F. Supp. 138, 1980 U.S. Dist. LEXIS 8979, 1980 A.M.C. 1939
CourtDistrict Court, E.D. New York
DecidedJanuary 15, 1980
Docket78 C 2313
StatusPublished
Cited by3 cases

This text of 483 F. Supp. 138 (Eazor Express, Inc. v. United States) is published on Counsel Stack Legal Research, covering District Court, E.D. New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Eazor Express, Inc. v. United States, 483 F. Supp. 138, 1980 U.S. Dist. LEXIS 8979, 1980 A.M.C. 1939 (E.D.N.Y. 1980).

Opinion

MEMORANDUM AND ORDER

NEAHER, District Judge.

Defendants in this damage action arising out of the dredging of a waterway adjacent to plaintiff’s property move to dismiss the complaint as barred by the applicable statute of limitations and laches. For the reasons set forth below, the motions are granted and the complaint is dismissed.

Plaintiff Eazor Express, Inc. (“Eazor”) is the owner of a trucking terminal in Brooklyn, New York, which is adjacent to New-town Creek, a navigable channel maintained by defendant United States Army Corps of Engineers (“ACE”) for the use of commercial vessels. Between April 8 and April 17, 1974, Newtown Creek was dredged to remove accumulated silt by defendant Weeks Dredging and Contracting Co., Inc. (“Weeks”) under a contract with ACE. Shortly after completion of the dredging operations, cracks began to appear in the side of the trucking terminal’s bulkhead along Newtown Creek due to subsidence of the land beneath, apparently caused by overdredging of the channel.

Plaintiff allegedly spent the next two and a half years investigating the cause of the damage, and then filed a claim for property damage with ACE in November 1976. The claim was denied on April 20, 1978, and six months later, on October 20, 1978, plaintiff filed this action.

Turning first to plaintiff’s claim against Weeks under the Extension of Admiralty Jurisdiction Act (“EAJA”), 46 U.S.C. § 740 (1948), we note that district court jurisdiction extends to claims of property damage “caused by a vessel on navigable water, notwithstanding that such damage or injury be done or consummated on land.” For purposes of determining admiralty tort jurisdiction, the Supreme Court has stated that, in addition to a maritime locality, the wrong must “bear a significant relationship to traditional maritime activity.” Executive Jet Aviation v. City of Cleveland, 409 U.S. 249, 268, 93 S.Ct. 493, 504, 34 L.Ed.2d 454 (1972). See Kelly v. United States, 531 F.2d 1144, 1146 (2 Cir. 1976). The federal courts have traditionally exercised their admiralty jurisdiction over claims for damages arising out of the operation and maintenance — including the dredging — of navigable canals and channels, Ex *140 parte Boyer, 109 U.S. 629, 3 S.Ct. 434, 27 L.Ed. 1056 (1884); Gulf Oil Corp. v. The Baltimore, 47 F.Supp. 770 (E.D.N.Y.1942), aff’d, 142 F.2d 557 (2 Cir. 1944); Otts v. I.M. Ludington’s Sons, Inc., 229 F. 538 (2 Cir. 1915); 1 Benedict, Admiralty § 145 (6th ed. 1974), and, since the passage of EAJA, the same result appears proper where, as here, the damage claimed is to plaintiff’s adjacent land. 1

As there is no specific statute of limitations for a claim for property damage brought in admiralty, the doctrine of laches applies, and the court must look to the analogous State statute of limitations for guidance in determining whether plaintiff’s claim should be barred by an inexcusable lapse of time. See Czaplicki v. The Heogh Silvercloud, 351 U.S. 525, 533-34, 76 S.Ct. 946, 100 L.Ed. 1387 (1956); Public Adm’r of County of New York v. Angela Compania Naviera S.A., 592 F.2d 58, 63 (2 Cir. 1979); Larios v. Victory Carriers, Inc., 316 F.2d 63 (2 Cir. 1963). The analogous statute of New York, the forum state here, is Civil Practice Law & Rules § 214(4) (CPLR), which provides a three-year limit for the commencement of actions to recover damages for injury to property. Plaintiff’s claim accrued at the time it was injured by the invasion of its rights — here, at the time of the dredging by Weeks which allegedly caused damage to plaintiff’s terminal — and the statute of limitations is not tolled by plaintiff’s lack of complete knowledge of the facts. Schmidt v. Merchants Despatch Trans. Co., 270 N.Y. 287, 200 N.E. 824 (1936); Medina Medical Bldg., Inc. v. Erie County Sheriff’s Dept., 55 A.D.2d 1026, 391 N.Y.S.2d 257 (4th Dept. 1977). See Kern v. Hettinger, 303 F.2d 333, 338 (2 Cir. 1962). 2

Since this action was commenced in October 1978, approximately four and a half years after the allegedly negligent dredging occurred in April 1974, it is clearly brought well beyond the limitations period of CPLR § 214(4). In these circumstances, however, courts must not resort to a mechanical application of the State statute; rather, they must consider the equities of the parties in determining whether a plaintiff’s action is barred by laches. Gardner v. Panama Railroad Co., 342 U.S. 29, 30-31, 72 S.Ct. 12, 96 L.Ed. 31; Hill v. Bruns & Co., 498 F.2d 565 (2 Cir. 1974). The approach to such a determination has been set forth by the Court of Appeals for this circuit:

“When the suit has been brought after the expiration of the state limitation period, a court applying maritime law asks why the case should be allowed to proceed .
******
“Moreover, although a plaintiff who has delayed bringing suit beyond the analogous state period has the ultimate burden of persuasion both as to the excuse for his own delay and as to lack of prejudice to the defendant, see Gilmore & Black, Admiralty (1957), 631, these two factors are not to be viewed independently. A weak excuse may suffice if there has been no prejudice .
******
“Even on this approach there may be cases where the plaintiff’s evidence as to excuse for the delay is so insubstantial that the court need not call on the defendant to come forward with evidence of prejudice.” Larios v. Victory Carriers, Inc., supra, 316 F.2d at 66-67.

*141 Applying these principles, the court concludes that plaintiff has failed to offer an explanation for its delay sufficient to excuse its commencement of this suit more than 17 months after the running of the State statute of limitations. Plaintiff cannot claim that it was not immediately a-ware of the damage to its property because, by admission of its president, cracks became apparent at the terminal site shortly after the completion of the dredging (Norton Aff., Exh. B).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Epshteyn v. United States
657 F. Supp. 255 (S.D. New York, 1987)
Kohlasch v. New York State Thruway Authority
516 F. Supp. 769 (S.D. New York, 1981)

Cite This Page — Counsel Stack

Bluebook (online)
483 F. Supp. 138, 1980 U.S. Dist. LEXIS 8979, 1980 A.M.C. 1939, Counsel Stack Legal Research, https://law.counselstack.com/opinion/eazor-express-inc-v-united-states-nyed-1980.