Eaton Commercial, L.P. v. Paradigm Hotel SA Riverwalk, LP

Court of Appeals of Texas·Decided October 5, 2016·No. 04-15-00705-CV·Published

Opinion

Fourth Court of Appeals San Antonio, Texas MEMORANDUM OPINION No. 04-15-00705-CV

EATON COMMERICAL, L.P., Appellant

v.

PARADIGM HOTEL SA RIVERWALK, LP, Appellee

From the 45th Judicial District Court, Bexar County, Texas Trial Court No. 2015CI11882 Honorable John D. Gabriel, Jr., Judge Presiding

Opinion by: Patricia O. Alvarez, Justice

Sitting: Patricia O. Alvarez, Justice Luz Elena D. Chapa, Justice Jason Pulliam, Justice

Delivered and Filed: October 5, 2016

REVERSED AND REMANDED WITH INSTRUCTIONS

Appellant Eaton Commercial, L.P. appeals the trial court’s order confirming an arbitration

award, contending the trial court erred in denying Eaton’s request to remand the award to the

arbitrator to clarify ambiguities in the award. Because we agree the arbitrator’s award is

ambiguous, we reverse the trial court’s order and remand the cause to the trial court with

instructions to remand the award to the arbitrator for clarification. 1

1 Eaton alternatively argues the trial court erred in refusing to correct the award. Because we sustain Eaton’s first issue, we do not address its alternative argument. See TEX. R. APP. P. 47.1 (providing opinions should only address issues necessary to final disposition of appeal). We note, however, “[a] court may not interpret [an arbitration] award 04-15-00705-CV

FACTUAL AND PROCEDURAL BACKGROUND

Eaton entered into a contract with Appellee Paradigm Hotel SA Riverwalk, L.P. to

construct a hotel. The contract provided for Eaton to be paid its costs plus a fee with a guaranteed

maximum price (“GMP”). The GMP in the original contract was $10,268,700.00. In May of

2013, Paradigm approved change order number 1 adding “the 9th Street Roadway Improvements”

which increased the GMP by $804,005.00 to $11,072,705.00. 2

Eventually, both parties alleged the other party breached the contract. Eaton alleged

Paradigm owed it additional amounts for change orders and other costs incurred by Eaton, and

Paradigm alleged it overpaid Eaton and incurred lost revenue as a result of Eaton’s breach of the

contract. In accordance with the contract, these disputes were submitted to arbitration.

In the arbitration proceeding, Eaton alleged the total adjusted GMP for the project was

$12,833,363.00. Eaton alleged it was owed $1,765,560.00 for seven itemized amounts which

included additional amounts for change orders and other costs and a credit for a water line. 3

Because the contract only required Paradigm to pay Eaton its costs plus a fee, Eaton also alleged

its costs and fee totaled $12,363,654.28. Subtracting the amount Paradigm paid Eaton in the

amount of $10,634,088.00 from the amount of Eaton’s alleged costs and fee, Eaton alleged it was

owed a balance of $1,729,567.00.

The arbitrator concluded Paradigm owed Eaton “an adjustment to the GMP of

$769,553.33” based on the arbitrator’s review of the seven amounts itemized by Eaton. The

in order to resolve [an] ambiguity and implement the award; instead the court must remand the award to the arbitrator with instructions to clarify the award’s particular ambiguities.” Brown v. Witco Corp., 340 F.3d 209, 216 (5th Cir. 2003). 2 One of Eaton’s exhibits reflects the GMP after change order number 1 to be $11,067,803.00. It is unclear from the record how Eaton computed this number. 3 The briefs and proposed award Eaton submitted to the arbitrator are not a model of clarity and contain numerous mathematical errors. For example, in its trial brief and in its proposed award, Eaton alleged the additional amount it was owed was $1,765,500; however, Eaton itemized seven amounts which total $1,767,959. In addition, Eaton alleged the sum of $1,729,567 and $32,480 is $1,765,560, but the two amounts actually total $1,762,047.

-2- 04-15-00705-CV

arbitrator also awarded Eaton $123,000.00 in attorney’s fees and $3,550.01 as a reimbursement

for the apportioned arbitration fees and expenses. Finally, the arbitrator awarded Eaton pre-

judgment interest at the rate of 10% accruing from May 6, 2014, the date the arbitration demand

was filed, and continuing through the date of the award, and post-award interest to accrue if

Paradigm had not paid the award within thirty days from the date of the award.

Eaton filed a motion to clarify the award, asserting the award did not specify the final

contract amount Eaton was due because the award did not state the amount of the GMP to which

the $769,553.33 adjustment was to be added. Eaton attached an award summary to its motion,

asserting the final GMP amount was $11,837,356.33, which was the total of the original GMP

stated in the contract, the adjustment to the GMP from change order number 1, and the additional

$769,553.33 adjustment to the GMP stated in the arbitrator’s award. 4 The arbitrator initially

denied the motion; however, after receiving additional filings from both parties, the arbitrator

issued a second order stating the arbitrator believed she was “without authority to issue a ruling or

take any other action until a court of competent jurisdiction issues further orders.”

Eaton then filed a petition asking the trial court to interpret the award, remand the award

for further proceedings, or confirm the award in the amount of $1,463,331.68. Paradigm filed a

motion to confirm the award for the specific amounts listed by the arbitrator. The trial court denied

Eaton’s petition and granted Paradigm’s motion confirming the award. The trial court’s order

states:

1) That the Final Award issued on June 15, 2015 is confirmed; and 2) Pursuant to that Award, Paradigm Hotel SA Riverwalk, LP is to pay Eaton Commercial, LP $769,533.33 for its claims, $123,0000 in attorney’s fees, $3,550.01 in administrative costs, as well as 10% prejudgment interest running from May 6, 2014 (date of the [sic] Eaton’s filing of the arbitration

4 As previously noted, this figure is based on Eaton’s calculation that the GMP after change order number 1 was $11,067,803, and the record is not clear how this amount was calculated because the total of the original GMP in the contract of $10,268,700 and the $804,005.00 added to the GMP in change order number 1 is $11,072,705.00.

-3- 04-15-00705-CV

demand) to June 15, 2015 (date of issuance of the Final Award), post award interest at the rate of 10% per annum shall begin to accrue thirty (30) days from the date of the Final Award.

Eaton appeals.

STANDARD OF REVIEW

We review a trial court’s decision to confirm an arbitration award de novo in order to

protect the great deference accorded to arbitration awards. Stage Stores, Inc. v. Gunnerson, 477

S.W.3d 848, 855 (Tex. App.—Houston [1st Dist.] 2015, no pet.); SSP Holdings Ltd. P’ship v.

Lopez, 432 S.W.3d 487, 492 (Tex. App.—San Antonio 2014, pet. denied). “In a de novo review,

the trial court’s decision is given no deference.” Lopez, 432 S.W.3d at 493.

PROPER TRIAL COURT ACTION WHEN ARBITRATION AWARD IS AMBIGUOUS

If an arbitration award is ambiguous, it cannot be enforced. Brown, 340 F.3d at 216;

Gunnerson, 477 S.W.3d at 855. If a trial court determines an arbitration award is unclear or

ambiguous in the process of deciding whether the award should be confirmed or vacated, the trial

court may not interpret the award to resolve the ambiguity but must remand the award to the

arbitrator for clarification. Murchison Capital Partners, L.P. v.

Free access — add to your briefcase to read the full text and ask questions with AI

Eaton Commercial, L.P. v. Paradigm Hotel SA Riverwalk, LP, (Tex. Ct. App. 2016).

Eaton Commercial, L.P. v. Paradigm Hotel SA Riverwalk, LP (Eaton Commercial, L.P. v. Paradigm Hotel SA Riverwalk, LP) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Brown v. Witco Corporation
340 F.3d 209 (Fifth Circuit, 2003)
East Texas Salt Water Disposal Co. v. Werline
307 S.W.3d 267 (Texas Supreme Court, 2010)
GJR Management Holdings, L.P. v. Jack Raus, Ltd.
126 S.W.3d 257 (Court of Appeals of Texas, 2003)
Riha v. Smulcer
843 S.W.2d 289 (Court of Appeals of Texas, 1992)
Weinberg v. Silber
140 F. Supp. 2d 712 (N.D. Texas, 2001)
Stage Stores, Inc. v. Jon Gunnerson
477 S.W.3d 848 (Court of Appeals of Texas, 2015)
SSP Holdings Ltd. Partnership v. Lopez
432 S.W.3d 487 (Court of Appeals of Texas, 2014)
M & C Corp. v. Erwin Behr GMBH & Co.
143 F.3d 1033 (Sixth Circuit, 1998)