Eastwood Constr. Partners, LLC v. Waxhaw Developers, LLC

CourtCourt of Appeals of North Carolina
DecidedDecember 3, 2025
Docket25-174
StatusUnpublished

This text of Eastwood Constr. Partners, LLC v. Waxhaw Developers, LLC (Eastwood Constr. Partners, LLC v. Waxhaw Developers, LLC) is published on Counsel Stack Legal Research, covering Court of Appeals of North Carolina primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Eastwood Constr. Partners, LLC v. Waxhaw Developers, LLC, (N.C. Ct. App. 2025).

Opinion

An unpublished opinion of the North Carolina Court of Appeals does not constitute controlling legal authority. Citation is disfavored, but may be permitted in accordance with the provisions of Rule 30(e)(3) of the North Carolina Rules of Appellate Procedure.

IN THE COURT OF APPEALS OF NORTH CAROLINA

No. COA 25-174

Filed 3 December 2025

Mecklenburg County, No. 21CVS000876-590

EASTWOOD CONSTRUCTION PARTNERS, LLC, f/k/a EASTWOOD CONSTRUCTION, LLC, d/b/a EASTWOOD HOMES, Plaintiff, v.

WAXHAW DEVELOPERS, LLC and WAXHAW, LLC, Defendants.

Appeal by defendants from order regarding appellate bond damages entered

29 May 2024 by Judge J. Thomas Davis and cross-appeal by plaintiff from attorney

fee order entered 20 November 2024 by Alan Z. Thornburg in Mecklenburg County

Superior Court. Heard in the Court of Appeals 26 August 2025.

Robinson, Bradshaw & Hinson, P.A. by Matthew W. Sawchak, Jazzmin M. Romero, Stephen M. Cox and Patrick H. Hill and FisherBroyles, LLP, by Deborah L. Fletcher and Christopher R. Kinkade, for defendants.

Brooks, Pierce, McLendon, Humphrey & Leonard, LLP, by Katarina K. Wong and James C. Adams, II, for plaintiff.

PER CURIAM.

This appeal is the second in this matter. The first appeal was from an order

entered 29 August 2022 by the trial court directing Defendant (a lot developer) to EASTWOOD CONSTR. PARTNERS, LLC V. WAXHAW DEVELOPERS, LLC

Opinion of the Court

specifically perform a contract to sell residential lots to Plaintiff (a homebuilder),

based on the trial court’s conclusion that the parties have an enforceable purchase

contract. Eastwood v. Waxhaw, 291 N.C. App. 519 (2023) (unpublished) (hereafter

“Eastwood I”). A more detailed background concerning the underlying dispute can

be found in Eastwood I.

This present appeal is by Defendants from an order entered by the trial court

on remand from Eastwood I directing the $495,000.00 appeal bond posted by

Defendants prior to the first appeal to be paid to Plaintiff (the “Bond Order”).

Plaintiff cross-appeals an order from the trial court denying, in part, its motion for

attorneys’ fees (the “Attorneys’ Fees Order”).

I. Analysis

A. Defendants’ Appeal

Defendants argue the trial court erred by entering the Bond Order. We

disagree for the reasoning below.

To stay the order from the appeal in Eastwood I, Defendants posted an appeal

bond in the amount of $495,000.00.

The bond was posted pursuant to Section 1-292 of our General Statutes. That

statute provides that an order directing the sale of real estate is not stayed on appeal

unless the appellant posts a bond requiring the appellant, upon affirmance of the

order on appeal, to “pay the value of the use and occupation of the property [ ] from

the time of the appeal until the delivery of possession thereof” not to exceed the bond

-2- EASTWOOD CONSTR. PARTNERS, LLC V. WAXHAW DEVELOPERS, LLC

amount. N.C.G.S. § 1-292 (emphasis added).

On remand from Eastwood I, the trial court determined the “loss of possession

and use of the property” during the first appeal exceeded the amount of the appeal

bond and, therefore, awarded the entire amount of the appeal bond ($495,000.00) to

Plaintiff.

On appeal, Defendants argue Plaintiff failed to prove the value of the use and

occupation of the land during the appeal was the amount of the appeal bond.

Plaintiff, though, argues it did meet its burden and, therefore, the order of the trial

court awarding it $495,000.00 should be affirmed.

We note the language of the bond in this case does not track the language in

G.S. 1-292 but rather states that Defendants shall pay “all costs and damages that

shall be adjusted against [Defendants] on appeal, and shall also satisfy and perform

the judgment or order appealed from in case it shall be affirmed . . . [.]” Neither party

makes any argument that the measure of damages used in the bond differs from that

in G.S. 1-292 or that the trial court erred by using the measure of damages as set

forth in G.S. 1-292. Accordingly, we do not address that issue.

A successful appellee is not entitled to the amount of the bond automatically;

rather, the appellee must show its damages because of the delay caused by the appeal

and may recover up to the amount of the bond. See First National Bank v. Hicks, 207

N.C. 157, 159 (1934); In re Simon, 36 N.C. App. 51, 56–57 (1978).

In determining the damages under a bond, the trial court is to consider the loss

-3- EASTWOOD CONSTR. PARTNERS, LLC V. WAXHAW DEVELOPERS, LLC

from the perspective of the appellee, and not the appellant. See Currituck v.

Hollowell, 170 N.C. App. 399, 404 (2005).

In its order, the trial court made findings supported by the evidence that

Plaintiff’s damages, from the perspective of Plaintiff, exceeded over $495,000.00,

based on the increase in construction and borrowing costs in 2023 alone. These

findings were supported by the evidence. Accordingly, we affirm the order of the trial

court.

B. Plaintiff’s Cross-Appeal

Plaintiff argues the trial court abused its discretion by failing to find Plaintiff

was entitled to attorneys’ fees and expenses under G.S. 1D-45 and G.S. 6-21.6.

We review a trial court’s order denying attorneys’ fees under both G.S. 1D-45

and G.S. 6-21.6 for abuse of discretion. Rhyne v. K-Mart, 149 N.C. App. 672, 690

(2002).

General Statute 1D-45 allows for attorneys’ fees “resulting from the defense

against [a] punitive damages claim” when the party asserting the claim “knows or

should have known” the claim was “frivolous or malicious.” N.C.G.S. § 1D-45.

Here, Plaintiff made no argument at the trial court that Defendants’ punitive

damage claim was “malicious.” Therefore, we consider any argument on appeal on

this issue waived. And though Defendants were not successful on their claims, we

cannot say the trial court abused its discretion in determining Defendants’ claims,

based on slander of title, were not frivolous.

-4- EASTWOOD CONSTR. PARTNERS, LLC V. WAXHAW DEVELOPERS, LLC

General Statute 6-21.6 provides a trial court “may” in its discretion award

reasonable attorneys’ fees “in accordance with the terms of [a] business contract.”

The agreement which is the subject of this litigation does not contain an

attorneys’ fees provision. Plaintiff, though, contends the attorneys’ fees provision in

the deed of trust controls. Assuming the provision applies, we cannot say the trial

court abused its discretion in not awarding attorneys’ fees in this case.

Accordingly, we affirm the trial court’s order on Plaintiff’s motion for attorneys’

fees and costs.

AFFIRMED.

Panel consisting of Chief Judge DILLON and Judges STROUD and GORE.

Report per Rule 30(e).

-5-

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Rhyne v. K-Mart Corp.
562 S.E.2d 82 (Court of Appeals of North Carolina, 2002)
Currituck Associates-Residential Partnership v. Hollowell
612 S.E.2d 386 (Court of Appeals of North Carolina, 2005)
In Re the Deed of Trust of Simon
243 S.E.2d 163 (Court of Appeals of North Carolina, 1978)
First National Bank of Henderson v. Hicks
176 S.E. 249 (Supreme Court of North Carolina, 1934)