Eastern Exterior Wall Systems, Inc. v. Gilbane Building Company

CourtDistrict Court, N.D. New York
DecidedOctober 24, 2023
Docket6:22-cv-01318
StatusUnknown

This text of Eastern Exterior Wall Systems, Inc. v. Gilbane Building Company (Eastern Exterior Wall Systems, Inc. v. Gilbane Building Company) is published on Counsel Stack Legal Research, covering District Court, N.D. New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Eastern Exterior Wall Systems, Inc. v. Gilbane Building Company, (N.D.N.Y. 2023).

Opinion

UNITED STATES DISTRICT COURT NORTHERN DISTRICT OF NEW YORK _____________________________________________ EASTERN EXTERIOR WALL SYSTEMS, INC., Plaintiff, 6:22-CV-1318 v. (GTS) GILBANE BUILDING COMPANY, f/k/a Gilbane Construction Company, Defendant. _____________________________________________ APPEARANCES: OF COUNSEL: ADAMS LeCLAIR LLP DANIEL P. ADAMS, ESQ. Counsel for Plaintiff 28 East Main Street, Suite 1500 Rochester, NY 14614 ERNSTROM & DRESTE, LLP JOHN W. DRESTE, ESQ. Counsel for Defendant 925 Clinton Square Rochester, NY 14604 GLENN T. SUDDABY, United States District Judge DECISION and ORDER Currently before the Court, in this arbitration action filed by Eastern Exterior Wall Systems, Inc. (“Petitioner”) against Gilbane Building Company (“Respondent”) are (1) Petitioner’s Petition to Compel Arbitration, and (2) Respondent’s cross-motion to dismiss Petitioner’s Petition for failure to state a claim under Fed. R. Civ. P. 12(b)(6). (Dkt. Nos. 1, 6.) For the reasons set forth below, Respondent’s cross-motion is granted, and Petitioner’s Petition is denied and dismissed. I. RELEVANT BACKGROUND A. Underlying Dispute and Relevant Procedural History The dispute arises from events occurring on a construction project in Utica, New York, commonly referred to as Mohawk Valley Health System-New Downtown Hospital on Lafayette Street (the “Project”). Respondent was the Project’s construction manager, and Petitioner was

Respondent’s subcontractor, charged with furnishing and installing the wall panels that made up the façade of the new hospital. After incurring uncontemplated costs in erecting the wall panels, Petitioner demanded that Respondent pay those costs, because (allegedly) they were due to faulty control lines that were provided by Respondent (and from which Petitioner laid out its work). Respondent disagreed. The parties’ attempted mediation of their dispute failed. On November 16, 2022, Petitioner served a demand for arbitration on Respondent, in accordance with two parties’ subcontract (“Trade Contract Agreement”). On November 21, 2022, Respondent rejected the arbitration demand. On December 8, 2022, Petitioner filed its Petition in this Court, seeking an order to compel binding arbitration with the American

Arbitration Association, pursuant to the Federal Arbitration Act, 9 U.S.C. § 4, arguing that arbitration is required under with Article 5 of the General Conditions of Respondent’s contract with the owner of the Project (“the Prime Contract”). On January 5, 2023, Respondent cross- moved to dismiss Petitioner’s Petition for failure to state a claim. B. Summary of Parties’ Arguments 1. Petitioner’s Memorandum of Law in Chief Generally, in its memorandum of law in chief, Petitioner asserts two arguments. (Dkt. No. 1, Attach. 2.) First, Petitioner argues that the Court should issue an Order compelling arbitration of its claim, because Second Circuit precedent favors arbitration under the 2 circumstances. (Id. at 7-11.)1 More specifically, Petitioner essentially asserts the following seven-part syllogism: (1) the parties agree that Petitioner’s claim against Respondent is governed by the dispute resolution procedure set forth in Article 9 of the Prime Contract, specifically Article 9.1, which provides that “[a]ny Claim between the Owner and Construction Manager shall be resolved in accordance with the provisions set forth in this Article 9 and Article 5 of the

General Conditions”; (2) Article 5.4.1. of the General Conditions contains an arbitration clause that is broad in that it gives the party making the claim or dispute (the “Aggrieved Party”) the option to either litigate or arbitrate; (3) when an agreement to arbitrate is broad, binding Second Circuit precedent (and New York law) holds that there exists a “presumption of arbitrability” that can be overcome only “if it may be said with positive assurance that the arbitration clause is not susceptible of an interpretation that covers the asserted dispute” (with any “[d]oubts” to “be resolved in favor of coverage”); (4) as a result, here, a strong presumption of arbitration exists and can be defeated by Respondent only by showing that Petitioner’s claim does not arise from, or is not otherwise related to, the parties’ Trade Contract Agreement; (5) however, Petitioner’s

claim clearly arises from, and is related to, the parties’ Trade Contract Agreement, because the furnishing and installing of the panels is expressly identified within Petitioner’s scope of “Work” in that Trade Contract Agreement; (6) to the extent there is any ambiguity in the Trade Contract Agreement, that ambiguity must be resolved in favor of arbitration; and (7) as a result, the broad arbitration clause here gives Petitioner, as the Aggrieved Party referenced in Article 5.4.1. of the General Conditions, the option to arbitrate its claim. (Id.) Second, Petitioner argues that the Supreme Court’s recent decision in Morgan v.

1 Page citations in this Decision and Order refer to the screen number used on the Court’s Case Management/Electronic Filing (“CM/ECF”) System, rather than the page number stated on the document shown on the screen. 3 Sundance, Inc., 142 S. Ct. 1708 (2022), does nothing to deprive Petitioner of its (above- explained) right to select arbitration under the circumstances. (Id. at 11-13.) 2. Respondent’s Combined Opposition Memorandum of Law and Memorandum of Law in Chief Generally, in its combined opposition memorandum of law and memorandum of law in chief, Respondent asserts three arguments. (Dkt. No. 6, Attach. 4.) First, Respondent argues, the Petition must be denied and arbitration stayed, because, as a threshold matter, the parties did not agree to arbitrate (given that, later in Article 9 of the Prime Contract, they agreed to strike arbitration from their Trade Contract Agreement). (Id. at 14-17.) More specifically, Respondent argues as follows: (a) Article 9.2 of the Prime Contract (which is also part of the “dispute and

resolution/litigation provision” that was expressly adopted by Paragraph 12.8 of the Trade Contract Agreement) provides that “[f]or any Claim subject to, but not resolved by mediation pursuant to Article 5 of the General Conditions, the method of binding dispute resolution shall be . . . Litigation in a court of competent jurisdiction” (emphasis in original), and here the underlying dispute was not resolved by mediation; (b) Petitioner’s effort to wholly replace the Trade Contract Agreement (and Article 9.2 of the Prime Contract) with the entire dispute resolution process contained within Article 5 of the General Conditions is unavailing, because the specific litigation provision in Article 9.2 of the Prime Contract was clearly and unequivocally added to the Trade Contract Agreement (thus eliminating arbitration as dispute resolution), and such a specific modification cannot be overcome through general references to

incorporation (especially where, as here, doing so would run afoul of the provision in Article 17.3.1 of the Trade Contract Conditions, providing that any “Owner’s Dispute Resolution Process” would be applicable only in the event, and to the extent, that claims between 4 Respondent and the Owner “include or involve the Trade Contractor [Petitioner],” which Petitioner’s claim does not do here); and (c) any preference in the Federal Arbitration Act for arbitration cannot impact the above analysis in the absence of an agreement to arbitrate (a point of law recognized in the Supreme Court case cited by Petitioner, Morgan v. Sundance, Inc., 142 S. Ct. 1708 [2022]). (Id. at 17-23.)

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Harrington v. Atlantic Sounding Co., Inc.
602 F.3d 113 (Second Circuit, 2010)
Hines v. Overstock.Com, Inc.
380 F. App'x 22 (Second Circuit, 2010)
Bensadoun v. Jobe-Riat
316 F.3d 171 (Second Circuit, 2003)
Morgan v. Sundance, Inc.
596 U.S. 411 (Supreme Court, 2022)
Nicosia v. Amazon.com, Inc.
834 F.3d 220 (Second Circuit, 2016)

Cite This Page — Counsel Stack

Bluebook (online)
Eastern Exterior Wall Systems, Inc. v. Gilbane Building Company, Counsel Stack Legal Research, https://law.counselstack.com/opinion/eastern-exterior-wall-systems-inc-v-gilbane-building-company-nynd-2023.