Eastern Electrical Co. v. Martin

52 Mass. App. Dec. 41, 1973 Mass. App. LEXIS 618
CourtMassachusetts District Court, Appellate Division
DecidedSeptember 11, 1973
DocketNo. 8033; No. 15805
StatusPublished
Cited by5 cases

This text of 52 Mass. App. Dec. 41 (Eastern Electrical Co. v. Martin) is published on Counsel Stack Legal Research, covering Massachusetts District Court, Appellate Division primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Eastern Electrical Co. v. Martin, 52 Mass. App. Dec. 41, 1973 Mass. App. LEXIS 618 (Mass. Ct. App. 1973).

Opinion

Flynn, J.

This is an action of contract to recover for labor and materials allegedly performed for and supplied by the plaintiff to the defendant.

Plaintiff’s declaration is on a common count in the sum of $9,580.13. The defendant’s answer is (1) a general denial; (2) a plea of [43]*43payment; (3) an allegation that the plaintiff dealt with the defendant as an agent of another and the labor performed and materials supplied were for an account of another; and (4) the Statute of Frauds (Gr.L. c. 259, $ 1 — no note or memorandum of a special promise to answer for the debt of another.)

The court found for the plaintiff in the sum of $8,877.22.

At the trial there was evidence tending to show:

The plaintiff is an electrical contractor and was awarded a sub-contract for electrical work in connection with the construction of a new building and renovation of an old building owned by The Lutheran, Social Services, Inc., and both located in Brockton, Massachusetts.

The defendant is an architect and was employed in that capacity by The Lutheran Social Services, Inc., for the design and supervision of the renovation and construction of its buildings in Brockton, Massachusetts.

The defendant in many instances approved modifications and changes to plaintiff's subcontract for electrical work and in addition supervised all of the plaintiff's work on the project.

In January 1971 the defendant asked the plaintiff to provide an added electrical service from the transformer to the main switch gear. The plaintiff was to perform this, work on. a time and materials basis, which it did, [44]*44and by invoice dated April 8, 1971, charged the defendant the sum of $2,889.00. Thereafter, the defendant made a $1,500.00 payment on account leaving a balance due of $1,389.00, which the defendant admitted it owed the plaintiff.

By three invoices dated October 5, 1971, the plaintiff charged the defendant for additional labor and materials in connection with (1) electrical work on heat in penthouse; (2) wiring of air-conditioner; and (3) added electrical work in electrical room.

The defendant by letter dated June 3, 1971 authorized the plaintiff to perform additional electrical work on the Lutheran Home project. The letter referred to the Lutheran Home project and is signed" “Doak Martin, A.I.A.” The letter commenced — “In order to reduce and balance the load in the Motor Center, this is tb authorize you to perform the following work ...” All of the work performed by plaintiff for which it seeks to charge the defendant was performed on the Lutheran Home project.

At the close of the evidence, and before the final arguments, the defendant made requests for rulings, which, with the court’s disposition thereof, are as follows:

1. On all the law and evidence a finding for the defendant is warranted. Allowed.

2. On all the law and evidence a find[45]*45ing for the plaintiff is not warranted. Denied.

3. Defendant as an architect at all times pertinent to this claim was an agent of Lutheran Social Services, Inc. Denied as contrary to facts found.

4. Plaintiff, at all times pertinent to this claim, dealt with defendant in his capacity as an agent of Lutheran Social Services, Inc., and not as a principal for whom' he was to perform labor and supply materials. Denied as contrary to facts found.

5. Defendant is not personally liable to plaintiff for work done for Lutheran Social Services, Inc., as the plaintiff at all times pertinent to its claim, knew the defendant was an. agent for a disclosed principal. Denied as a request for a finding of fact.

6. That at all times pertinent to its claim, plaintiff performed labor and supplied materials for buildings owned by Lutheran Social Services, Inc., and since there is no written note or memorandum signed by the defendant agreeing to pay for such labor and materials, plaintiff cannot maintain such an action against the defendant since the defendant would be charged to answer for the debt of the Lutheran Social Services, Inc., without a writing as required by statute. (Chapter [46]*46295, § 1, Gr.L.). Denied as contrary to facts found.

7. At all times pertinent to its claim, plaintiff knew that the defendant received no part of the labor performed and materials supplied by it and therefore the consideration necessary for the formation of a contract between the parties does not exist and therefore no contract or action for quantum meruit may be maintained. Denied as contrary to facts found.

The plaintiff filed no requests for rulings.

The trial judge found the following facts:

“This is an action for work, labor and materials on a common count in the sum of $9,580.13.”
“I find that Cleary Construction Company was the general contractor for the construction of thé Lutheran Nursing Home in Brock-ton, Massachusetts; that the plaintiff was a file bid sub-contractor for the electrical contracting and that the defendant was the architect employed by Lutheran Social Services, Inc., to supervise construction and to approve modifications and changes' in the base contract. ”
“I find that the plaintiff was paid in the amount of the base contract and that certain changes were made during construction which were not included in the original contract price.”
“I find that changes requested during con-.. [47]*47struction required authorization by way of change orders approved by the architect, owner and general contractor.”
“I find that there were certain design deficiencies in the feeder to the main electrical service and that the defendant authorized the plaintiff to add additional cables necessitating labor and materials in the sum of $2,889.00 which were not authorized by the owner or the general contractor, but were contracted for individually by the defendant with the plaintiff.”
“I further find that the defendant, made a partial payment and is entitled to a credit of $1,500.00.!’
“I find that the electrical work performed in the wiring of heating units in the penthouse and the wiring of the air conditioners were part of the original contract; that those services were remedial and were obligations and the file sub bid contractors responsible for their installation.”
“I find that the defendant designed, specified and approved all changes; that there were no change orders for added electrical work in the electrical room; that the electrical service was not allowed to be connected due to design deficiencies; that by letter of June 3, 1971, the plaintiff was authorized by the defendant, in his individual capacity, to reduce and balance the electrical load in the motor center to correct the design deficiencies.”
[48]*48“I find that the additional work authorized in the electrical room was to be on a time and material basis; that the material costs were in the sum of $2,952.22, and the time (labor) charges were in the sum of $4,536.00.”

The defendant claims to be aggrieved by the Court’s failure to allow defendant’s request for rulings Nos. 2 through 7.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Brady v. Allstate Insurance
1984 Mass. App. Div. 242 (Mass. Dist. Ct., App. Div., 1984)
Baker v. Tokarz
1984 Mass. App. Div. 210 (Mass. Dist. Ct., App. Div., 1984)
Cifizzari v. D'Annunzio
1984 Mass. App. Div. 102 (Mass. Dist. Ct., App. Div., 1984)
B&M Siding Corp. v. Sucu
3 Mass. Supp. 428 (Massachusetts District Court, 1982)
B & M Siding Corp. v. Sucu
1982 Mass. App. Div. 62 (Mass. Dist. Ct., App. Div., 1982)

Cite This Page — Counsel Stack

Bluebook (online)
52 Mass. App. Dec. 41, 1973 Mass. App. LEXIS 618, Counsel Stack Legal Research, https://law.counselstack.com/opinion/eastern-electrical-co-v-martin-massdistctapp-1973.